- Company
- The Better Mouse Trap Co.
- Project / product line
- Basic trap
- Document
- Basic — Suppliers and production readiness
- Document no.
- BMT-BASIC-CHECK-SHEET-PRODUCTION-001
- Revision
- C1
- Status
- Planning draft
- Start date
- 2026-10-24
- Revision date
- 2026-10-24
- Prepared by / owner
- Sam Reed, mechanical, BASIC-C1
- Checklist ID
- BMT-BASIC-CHECK-SHEET-PRODUCTION-001, Rev C1
- Scope
- BASIC-C1 supplier readiness for BASIC-01 through BASIC-16.
- Reviewer
- Casey Holt
- Review date
- Planned 2026-11-01. Pending as of 2026-10-28. The review has not been held.
- Team
- Alex Meadow, packet owner; Sam Reed, mechanical lead; Robin Keel, animal-welfare reviewer; Ira Bell, Bell Sample Lab (test lab)
- Approved by
- review pending. Alex Meadow, Planning draft C1, unsigned.
| Item / review question | Answer / finding | Result / status | Evidence | Responsibility / action |
|---|---|---|---|---|
Item ID: PRODUCTION-01 Question: Are all suppliers quoting the same thing? | Answer / assumption: Eighteen dated bids are on BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, refs FSW-B-2026-01 through NLM-B-2026-18, parts BASIC-01 through BASIC-06, unawarded, no purchase order, cash disbursed Not applicable — no transaction in this planning record. The obsolete two-supplier blank sheet is withdrawn. BASIC-01 shell bids: FSW-B-2026-01 (Fictional Sample Works, Perry Voss) dated 2026-09-12, valid through 2026-12-11, P20 steel mold, molded-in window, 1 cavity, 500,000 shots, tooling $13,850.00, volume piece $1.64, annual qty 3,000, tool lead 14 weeks, tool owner: The Better Mouse Trap Co. when paid. MPS-B-2026-02 (Fictional Meadow Prototype Shop, Willa Marsh) dated 2026-09-16, valid through 2026-11-15, Aluminum bridge mold, bonded window, 1 cavity, 25,000 shots, tooling $6,400.00, volume piece $2.75, annual qty 800, tool lead 5 weeks, tool owner: Meadow Prototype Shop until buyout. NLM-B-2026-03 (Fictional Northline Molding, Eden Crowe) dated 2026-09-28, valid through 2026-12-27, Pre-hard 2-cavity mold, molded-in window, 2 cavities, 400,000 shots, tooling $18,600.00, volume piece $1.42, annual qty 3,000, tool lead 16 weeks, tool owner: The Better Mouse Trap Co. before kickoff. The internal $12,000. Drawings are not released, so the bids are not one common released revision. The company correspondence log has no outbound letter to Perry Voss, Willa Marsh, or Eden Crowe. That gap does not erase the bids. BOM C1 splits BASIC-07 through BASIC-14 as included cost inside the $4.45 pre-tool sum, so a second price on those lines would double count. BOM C1 records a labor-line name clash on BASIC-05: the cost sheet still names Fictional Sample Works, and the BOM says that name is not an order. 3,000 a year for 3 years is 9,000 shots. The Meadow Prototype Shop life of 25,000 shots covers 9,000. That bid's own volume column remains 800 a year. Explanation: G1 is Hold tooling pending evidence. Eighteen unawarded bids are not an award and are not a released common revision. A reader who treats $5.78 or the $12,000.00 allowance as a supplier bid is reading the cost sheet. Gate G4 is No purchase order. | Result (Y/N/NA): N Status: Open — bids unawarded, drawing not released | BMT-BASIC-BOM-001 Rev C1 BASIC-01 through BASIC-16; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 18 dated bids, FSW-B-2026-01 through NLM-B-2026-18, unawarded. | Owner: Sam Reed Next action: Sam Reed does not award a bid and does not issue a purchase order. Perry Voss, Willa Marsh, and Eden Crowe stay quote contacts only. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Eighteen bids stay unawarded. There is no common released offer and no purchase order. |
Item ID: PRODUCTION-02 Question: Can the supplier actually make and inspect it? | Answer / assumption: No audit or capability study; fixture, gauge, and process qualification are required before any pilot. The eighteen bids are not an audit. No process-limit study, sample plaque, quality-system scope, subcontractor list, or production address is on file beyond the quote rows. Perry Voss, Willa Marsh, and Eden Crowe are quote contacts. Directory names and dated bids are not qualification. No award and no purchase order. CP01 through CP16 are draft and the phase is prototype. Controlling process steps are P01 through P14. Receive is P01. Latch assembly is P05. BASIC-05 is in-house labor for Sam Reed and is not engaged. The assembly site is unleased. Ira Bell at Bell Sample Lab is not contacted. Jordan Vale has no Basic electrical scope. Explanation: Qualification has to exist before a pilot. A dated bid is not a capability study. Naming a shop on BOM C1 does not create it. G4 remains No purchase order. | Result (Y/N/NA): N Status: Open — no capability evidence | BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 bids on file, no award; BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16 draft; process flow P01 | Owner: Sam Reed Next action: Sam Reed asks for no shop audit until a released drawing exists. The three bids stay unawarded. Ira Bell stays not contacted. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No audit, process limit, or production address is on file. Directory names are not qualification. |
Item ID: PRODUCTION-03 Question: What are the real costs and commitments? | Answer / assumption: No spending committed; tooling allowance $12,000.00; per-unit packed cost $5.78 estimate.00 (T1), tests and welfare $4,000.00 (T2), market research $2,000.00 (T3), design $2,000.00 (T4), and unallocated reserve $2,000.00 (T5). The $12,000.00 BASIC-16 allowance is outside that cap and is not one of these lines. BOM C1 puts the same tool on BASIC-16 as $12,000.00 NRE, a single-cavity prototype mold, not ordered. Lines on BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1: BASIC-01 Shell/window line $3.13; BASIC-02 Door and latch line $0.80; BASIC-03 Trigger/hinge line $0.50; BASIC-04 Captive bait pocket line $0.25; BASIC-05 Assembly inspection line $0.55; BASIC-06 Retail carton/instructions line $0.55. Running total $5.78. Shell amortization $1.33 on tooling $12,000.00 at 3000 units/year for 3 years. BOM pre-tool sum $4.45. Adding the NRE mold row again would count the tool twice. Ten times $5.78 is $57.83 of estimated packed cost, and that arithmetic is not a quote and not freight. BOM C1 calls $24.00 a shelf hypothesis on the contact file. It is not a price on this sheet. Owner capital on BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 of $80,000.00 is not deposited. Explanation: The $12,000. It is not a fit test against the $5,000.00 prototype line, and it is not a supplier bid. The funding sheet stops before production tooling. Classifying BASIC-16 as a prototype mold does not authorize steel. G1 still says hold tooling. | Result (Y/N/NA): N Status: Open — allowances uncommitted | BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1 running total $5.78; BMT-BASIC-BOM-001 Rev C1 piece $5.78 and BASIC-16; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed leaves the $12,000. Alex Meadow has not signed a consent that names a line. Sam Reed shows the $4.45 versus $5.78 tie-out. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Allowances are recorded and uncommitted. The $12,000.00 tool is outside the cap. Nothing in this row is an awarded price. |
Item ID: PRODUCTION-04 Question: Who owns tooling, data and changes? | Answer / assumption: Proposed company ownership of tooling/data; contract and ECN approval before later frozen changes. Tool owner is not one shared clause. FSW-B-2026-01 says the company owns the tool when paid. MPS-B-2026-02 says the shop keeps title until buyout. NLM-B-2026-03 says company title before kickoff, with the mold paid 100% before steel. BOM C1 BASIC-16 assigns that note to Alex Meadow. No custody, maintenance, insurance, or removal clause is signed. G3 is No freeze, so there is no frozen baseline for an ECN to control yet. DFM-06 still bars a resin or latch substitute unless the affected requirement is regressed. Lane Corwin has not cleared disclosure. The RFQ records no NDA and no disclosure. Explanation: Tool title is a proposal on a quote sheet, not a contract. Sending drawings before an NDA would disclose an unreleased concept. No one has done that. | Result (Y/N/NA): N Status: Open — tool title unsigned | BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 tool-title clauses on FSW-B-2026-01, MPS-B-2026-02, and NLM-B-2026-03, none signed; BMT-BASIC-BOM-001 Rev C1 BASIC-16; | Owner: Sam Reed Next action: Alex Meadow does not sign a tool clause that is not drafted. Sam Reed keeps title as proposed only. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Tool title is unsigned. The three bids do not share one title clause. No NDA and no change baseline. |
Item ID: PRODUCTION-05 Question: How will we accept incoming parts and production output? | Answer / assumption: Incoming configuration check, linked CP controls, planned FAI; no inspection evidence. Accept would use BOM C1 and draft controls CP01 through CP16, drawing revision Basic C1, phase prototype. FAI characteristics are Not measured. Tests T01 through T14 are unrun. CTQ01 through CTQ14 are untested. Planned unit IDs BASIC-X1-001 onward have no results. BMT-BASIC-CONTROL-PLAN-001 Rev C1 does not place a software fault-injection rig on Basic. Jordan Vale has no Basic electrical scope. The 2026-10-18 read of the no-electronics line is not an approval. There is no production sample plan and no reliability inference. Work instructions are draft and are not a released shop packet. Controlling process steps are P01 through P14. Receive is P01. Latch assembly is P05. Explanation: A planned FAI with every characteristic Not measured is not incoming inspection. The restart rule on the control plan names Alex and has never been used, because no build exists. | Result (Y/N/NA): N Status: Blocked — FAI not measured | BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16 draft; process flow P01 through P14; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-BASIC-WORK-INSTRUCTIONS-001 Rev | Owner: Sam Reed Next action: Sam Reed does not open an FAI result. Controls stay draft. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. FAI characteristics are Not measured. Draft controls are not acceptance. |
Item ID: PRODUCTION-06 Question: Can we deliver and recover from interruption? | Answer / assumption: Assume single source initially; qualify backup before scale; no promised delivery. The comparison bids are not a delivery promise. A 10-unit first article is not built. The 3,000-a-year figure is a year-1 hypothesis and the amortization denominator, not a forecast and not a build quantity. Fictional Sample Works and Northline Molding bid 3,000 a year. Meadow Prototype Shop bids 800 a year and is not qualified as a backup. Risk B03 on BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, backup source due 2027-02-01, is planned and is not closed. Quoted tool leads on BASIC-01 are 14 weeks, 5 weeks, and 16 weeks. Those leads are not an 8-week promise. G1 is Hold tooling pending evidence. Tindall Sample Storage (Bea Tindall) is a storage candidate, not a factory. No reorder point and no delivery promise. Explanation: Capacity is not demonstrated by a cost denominator. Three unawarded mold bids plus an unqualified backup are not a recovery plan. | Result (Y/N/NA): N Status: Open — no recovery source | BMT-BASIC-RFQ-PACKAGE-001 Rev C1 quantities and timeline; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 BASIC-01 tool leads 14 weeks, 5 weeks, and 16 weeks, unawarded; | Owner: Sam Reed Next action: Sam Reed does not promise a date. The backup shop stays unqualified. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The volume figure is a cost denominator. No delivery date is promised. |
Item ID: PRODUCTION-07 Question: What must be in place after sale? | Answer / assumption: Traceability, complaints, recall containment, returns and safe disposal required before sale. None of those processes exist as records. BOM C1 says a draft one-year manufacturing-defect remedy is still off the sheet, so this check sheet is not a warranty. G5 is No launch authorized. Nia Calder has not bound coverage. Robin Keel has not set the occupancy interval that CTQ06 leaves open. BASIC-14 says capacity is unrated, the target is one mouse, and the unit is uncertified. Nothing has been sold. Explanation: After-sale controls are a gate into G5, which is not authorized. An empty complaint log only means no product is in the field. | Result (Y/N/NA): N Status: Blocked — after-sale records absent | BMT-BASIC-BOM-001 Rev C1 BASIC-13 and BASIC-14; BMT-BASIC-STAGE-GATES-001 Rev C1 G5; CTQ06. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed does not write a warranty onto this sheet. The Robin Keel interval stays open. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. After-sale records are absent. Gate G5 is not a launch. |
Item ID: PRODUCTION-08 Question: Is the first production order ready? | Answer / assumption: Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. G3 is No freeze. G4 is No purchase order. Missing drawings, supplier qualification, physical tests, and reviewed controls each block an order on their own. This row records the block. It is not a release by Alex Meadow or by Sam Reed. Explanation: PRODUCTION-08 is the stop rule for the sheet. A later quote does not satisfy it. The funding role has not confirmed cash. | Result (Y/N/NA): N Status: Blocked — release not recorded | BMT-BASIC-STAGE-GATES-001 Rev C1 G0, G3, and G4; DFM-07; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1 status Not funded/committed. Dated 2026-10-24. | Owner: Sam Reed Next action: Nobody places a purchase order. Revisit this row only when the evidence dated on this sheet is actually in the file. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. This row is the buy stop. It is not a release by Alex Meadow. |
Item ID: PRODUCTION-09 Question: Is one released revision ready so the quoted shops would be on the same released part? | Answer / assumption: Not ready. DFM-07 records BOM, cost, reviews, and requirements at C1, and no released CAD or drawings. DFM-03 (draft, walls, vent steel, latch undercuts) and DFM-04 (door fit, 30 mm grip clearance, shrink, wash aging, wear) are open. DFM-08 records no manufacturer comments and no accepted change. Eighteen bids are already on file for BASIC-01 through BASIC-06 and are not one released revision. No drawing has been released, so PRODUCTION-01 stays no. The package is not sent as an award. Explanation: Without one released revision, PRODUCTION-01 cannot be answered yes. The three shops' bids are not tied to one released window, pin, and carton. | Result (Y/N/NA): N Status: Blocked — drawing not released | BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1 items DFM-03, DFM-04, DFM-07, DFM-08; BMT-BASIC-RFQ-PACKAGE-001 Rev C1 revision field. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed lists each open DFM row as a drawing note or a quote exclusion and does not send the package. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No released drawing, so the bids on file are not one released part. |
Item ID: PRODUCTION-10 Question: Is every CTQ measurable on a first-article record with a defined gauge and sample? | Answer / assumption: Not measurable as a first article yet. Draft methods are CTQ01 100 dry cycles and a 5 N pull, CTQ02 two vent paths, CTQ03 30 mm finger clearance on 10 adult users, CTQ04 wash soil check, CTQ05 20 N bait pull, and CTQ06 occupancy visible without opening. FAI report C1 is Not measured and Not assessed. Suitability review on BMT-BASIC-CONTROL-PLAN-001 Rev C1 is pending. BASIC-15, the latch and vent gauge, is Not applicable — no transaction in this planning record on the piece, supplier Bell Sample Lab, Ira Bell not contacted, and no samples shipped. BOM C1 points that gauge at the adopted $4,000.00 tests-and-welfare line (T2). Basic has no software feature and no fault-injection rig. Jordan Vale has no Basic electrical scope. Draft method notes on the first six characteristics are not the full CTQ01 through CTQ14 set. CTQ07 through CTQ14 are also untested: pin retention, latch set, pane separation, bedding over the vents, multi-catch misuse, parcel cracks, unreleased vent height, and wash loosening the latch. Tests T01 through T14 are unrun. Explanation: Gauge suitability is still pending. Copying a software sample onto this mechanical trap would be wrong. Basic has no software feature. The tests-and-welfare line is the adopted $4,000.00, unfunded. FAI is not ready. | Result (Y/N/NA): N Status: Open — CTQ gauges not suitable | CTQ01 through CTQ14; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-BASIC-BOM-001 Rev C1 BASIC-15; BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 | Owner: Sam Reed Next action: Sam Reed maps one gauge to CTQ01 through CTQ14, records the $4,000.00 tests-and-welfare line, and does not contact Ira Bell. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Gauge suitability is pending. FAI stays Not measured. |
Item ID: PRODUCTION-11 Question: Is pilot cash identified, and is production tooling still stopped? | Answer / assumption: Pilot cash is identified only as an unfunded estimate, and production tooling is stopped. The T1 prototype line is $5,000.00 on the adopted split. It is unfunded. The $57.83 packed-cost arithmetic is not a purchase order. BASIC-16 at $12,000.00 line. The funding sheet says stop before production tooling. The company is not formed. Ellis Brook at Example Meadow Bank is a depository contact only. Credit is not requested. There is no account and no deposit. The account request planned for 2027-01-15 has not been made. Owner capital of $80,000.00 is not deposited. Explanation: Numeric room inside an allowance is not a release. The $12,000. G4 is No purchase order. G0 through G5 are pending. | Result (Y/N/NA): Y Status: Recorded — stop holds; cash unfunded | BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1; BMT-BASIC-BOM-001 Rev C1 BASIC-16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 capital and bank lines. Dated 2026-10-24. | Owner: Sam Reed Next action: Alex Meadow does not release the $5,000.00 prototype line and does not fold the $12,000.00 tool into the cap. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The tooling stop holds. Pilot cash is an unfunded estimate, not a release. |
Item ID: PRODUCTION-12 Question: Are sub-tier parts and special processes identified to a named source? | Answer / assumption: Sub-tier sources beyond the three quote contacts are not named as awarded sources. Dated bids cover BASIC-01 through BASIC-06 only and are unawarded. Fictional Sample Works, Meadow Prototype Shop, and Fictional Northline Molding are quote contacts. BASIC-05 is in-house and is not engaged. BASIC-15 is Bell Sample Lab, and Ira Bell is not contacted. BASIC-07 through BASIC-14 are included splits. Their allowances sit inside the parent lines and are excluded from being added again to the $4.45 sum. No resin grade, no stainless grade, and no carton printer. DFM-06 bars a substitute resin or latch without regression. Explanation: Three named molders have unawarded bids on BASIC-01 through BASIC-06. That is not an awarded window process, stainless pin process, and print shop. Until those sub-tier sources are named, PRODUCTION-01 is still incomplete for BASIC-07 through BASIC-14. | Result (Y/N/NA): N Status: Open — sub-tier sources unnamed | BMT-BASIC-BOM-001 Rev C1 BASIC-07 through BASIC-15 supplier and source columns; DFM-06. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed adds a blank sub-tier list to the held package and leaves the blanks empty. He does not award a bid. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Sub-tier sources are unnamed. Included splits must not be priced twice. |
Item ID: PRODUCTION-13 Question: Is the carton, the instruction revision, and the shipping trial defined for the packed unit? | Answer / assumption: Not defined as a shippable pack. BASIC-06 is recycled card at $0.55 inside the $4.45 pre-tool sum and inside the $5.78 amortized piece. BASIC-13 and BASIC-14 are included splits of that $0.55, with allowances $0.08 and $0.12, and are excluded from being added again. The RFQ says a shipping qualification is planned. It has not been run. Freight and duty are excluded on every bid, so there is no landed freight term. BASIC-01 payment terms are filled on the three bids and are not a signed contract. The $5.78 figure is not a landed cost. Explanation: Using the packed estimate as a delivered cost would ignore freight, a carton trial, and the fact that the instruction sheet is still a BOM description. | Result (Y/N/NA): N Status: Open — pack and freight undefined | BMT-BASIC-BOM-001 Rev C1 BASIC-06, BASIC-13, BASIC-14; BMT-BASIC-RFQ-PACKAGE-001 Rev C1 packaging field; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 payment terms filled on the | Owner: Sam Reed Next action: Sam Reed marks freight and the shipping trial as exclusions on any later quote. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The instruction text is a bill-of-materials note. Freight is excluded on the bids and is not a landed cost. |
Item ID: PRODUCTION-14 Question: Can each packed unit be traced to component lots and the assembly record? | Answer / assumption: Not traceable yet. The control plan says: Planned unit IDs BASIC-X1-001 onward; no results There is no lot-code format, no traveler, no resin lot, no pivot lot, no retain, and no carton date code. PRODUCTION-07 requires traceability before any sale. The method is blank. Explanation: Without a lot definition, a later complaint cannot be contained to a mold shot or a pin batch. That is the recall limit, and it is unmet. | Result (Y/N/NA): N Status: Open — traceability blank | BMT-BASIC-CONTROL-PLAN-001 Rev C1 traceability field; BMT-BASIC-BOM-001 Rev C1 no lot code. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed drafts the lot-code rule on this sheet only and does not print labels. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Planned serials have no lot code, traveler, or retain. |
Item ID: PRODUCTION-15 Question: Which open process failures block acceptance of a pilot lot? | Answer / assumption: Do not accept a pilot lot. BMT-BASIC-PFMEA-001 Rev C1 has 48 data rows, PF01 through PF48. Status is Open, Hold, or Blocked. No row is accepted. Severity 9 lines, highest RPN first: PF06 RPN 432 severity 9 (Window check skipped and the unit closed as acceptable; Open); PF02 RPN 252 severity 9 (Both vent ribs left on the floor side, beside the bait; Open); PF28 RPN 216 severity 9 (Gate closed without a written check interval; Blocked); PF30 RPN 216 severity 9 (Restart signed while a severity 9 row is still open; Hold); PF15 RPN 180 severity 9 (Retainer ribs short of the 20 N hold; Open); PF05 RPN 162 severity 9 (Uncaptured insert left in the bait opening; Open); PF09 RPN 144 severity 9 (Parting-line flash left across one rib root; Open); PF12 RPN 144 severity 9 (Pane missing, hazed, or soiled shut; Open); PF13 RPN 135 severity 9 (Instruction sheet states a multi-mouse capacity; Blocked); PF29 RPN 135 severity 9 (Live-animal note added to the gate to save a step; Blocked); PF36 RPN 135 severity 9 (Surrogate result written against the wrong shell; Open); PF45 RPN 135 severity 9 (Humane-claim sentence added to close the gate; Blocked); PF16 RPN 108 severity 9 (Prototype insert kitted in place of the captive pocket; Hold); PF39 RPN 108 severity 9 (Warning film from an older draft applied; Open). Robin Keel has not set the check interval and is not contacted. Robin Keel does not certify the trap. Linked controls are CP01 through CP16, draft. CP01 is the latch control and its shop step is P05. Receive is P01. Tests T01 through T14 are unrun. No build exists, and Alex Meadow has not authorized a restart. Explanation: Accepting a pilot while every process row is still open, on hold, or blocked would skip the reaction rules on the control plan. The highest block cited here is PF06, window check skipped, RPN 432, severity 9. | Result (Y/N/NA): Y Status: Recorded — pilot lot refused | BMT-BASIC-PFMEA-001 Rev C1 PF01 through PF48, none accepted; BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16. Dated 2026-10-24. | Owner: Sam Reed Next action: Sam Reed keeps the pilot quantity at zero while PF01 through PF48 stay unaccepted. Target 2026-12-15, planned. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Open PFMEA rows stay unaccepted. A pilot lot is refused. RPN is unchanged. |
Item ID: PRODUCTION-16 Question: What has to be signed before an RFQ goes out or tool steel is cut? | Answer / assumption: Nothing is signed. Still missing: an NDA before disclosure (Lane Corwin is not engaged; the RFQ says no agreement and no disclosure), company tool title with removal rights, an ECN change notice, payment and cancellation, a quote expiry, gauge and FAI inclusions, warranty and scrap, and a sentence that being named on this sheet is not qualification. Perry Voss, Willa Marsh, and Eden Crowe have bids on file. No award and no purchase order. Cutting steel is already stopped under PRODUCTION-11. Explanation: An RFQ sent now would ask for a price on undefined steel and would disclose the concept without an NDA. That fails PRODUCTION-01 and PRODUCTION-04 together. | Result (Y/N/NA): N Status: Blocked — terms and NDA unsigned | BMT-BASIC-RFQ-PACKAGE-001 Rev C1 NDA field; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 bid terms filled and not signed as a contract; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 | Owner: Sam Reed Next action: Sam Reed holds the file. This row does not engage Lane Corwin. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No NDA, tool clause, or payment term is signed. The file stays in house. |
Item ID: PRODUCTION-17 Question: Is the shell mold defined enough to cut the $12,000.00 tool? | Answer / assumption: No. BASIC-16 is the internal $12,000. The comparison sheet quotes three BASIC-01 tools, unawarded: FSW-B-2026-01 (Fictional Sample Works, Perry Voss) dated 2026-09-12, valid through 2026-12-11, P20 steel mold, molded-in window, 1 cavity, 500,000 shots, tooling $13,850.00, volume piece $1.64, annual qty 3,000, tool lead 14 weeks, tool owner: The Better Mouse Trap Co. when paid. MPS-B-2026-02 (Fictional Meadow Prototype Shop, Willa Marsh) dated 2026-09-16, valid through 2026-11-15, Aluminum bridge mold, bonded window, 1 cavity, 25,000 shots, tooling $6,400.00, volume piece $2.75, annual qty 800, tool lead 5 weeks, tool owner: Meadow Prototype Shop until buyout. NLM-B-2026-03 (Fictional Northline Molding, Eden Crowe) dated 2026-09-28, valid through 2026-12-27, Pre-hard 2-cavity mold, molded-in window, 2 cavities, 400,000 shots, tooling $18,600.00, volume piece $1.42, annual qty 3,000, tool lead 16 weeks, tool owner: The Better Mouse Trap Co. before kickoff. 3,000 a year for 3 years is 9,000 shots. 25,000 shots cover 9,000. The Meadow Prototype Shop volume column is still 800 a year. DFM-02 calls for a bridge process before a production tool. There is no accepted T0 or T1 plan and no shrink study for the door fit in DFM-04. Spreading the internal allowance at $1.33 over 3,000 units for 3 years does not mean the tool exists. G1 says hold tooling pending evidence. No purchase order. Explanation: The internal $12,000.00 allowance is already inside the $5. Ordering BASIC-16 would breach the stop-before-tooling rule. The supplier tools are different dollars and are unawarded. Adding a bid tool on top of the allowance would double count. | Result (Y/N/NA): N Status: Blocked — mold not released to cut | BMT-BASIC-BOM-001 Rev C1 BASIC-16 allowance $12,000.00 outside the cap; BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1 amortization $1.33; DFM-02; | Owner: Sam Reed Next action: Do not cut steel. BASIC-16 stays an allowance. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The mold is an allowance. Steel is not released. |
Item ID: PRODUCTION-18 Question: What blocks a first production order even with bids on file? | Answer / assumption: Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. The eighteen unawarded bids feed PRODUCTION-03. It would not be a purchase order. Alex Meadow has not recorded a release. This sheet is not that record. Explanation: The decision being prepared is the next private feasibility gate, not a buy. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. This row keeps the order unplaced after the rest of the sheet is read. | Result (Y/N/NA): Y Status: Recorded — order stays unplaced | BMT-BASIC-STAGE-GATES-001 Rev C1 G0, G3, G4; PRODUCTION-08 on this sheet; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24. | Owner: Sam Reed Next action: Leave the order unplaced. Target 2026-12-15. Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The blocks are independent. A later quote does not place the order. |
Basic — Suppliers and Production Readiness — supporting detail
Basic — Are all suppliers quoting the same thing?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-01
Question. Are all suppliers quoting the same thing?
Evidence to record. Exact revision/material/finish/quantities, inspection, packaging and acceptance requirements; assumptions and exclusions alongside each quote.
Result (Y/N/NA). N
Explanation. G1 is Hold tooling pending evidence. Eighteen unawarded bids are not an award and are not a released common revision. A reader who treats $5.78 or the $12,000.00 allowance as a supplier bid is reading the cost sheet. Gate G4 is No purchase order.
Status. Open — bids unawarded, drawing not released
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1 BASIC-01 through BASIC-16; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 18 dated bids, FSW-B-2026-01 through NLM-B-2026-18, unawarded. Recorded 2026-10-24. The Casey Holt read is planned for 2026-11-01 and has not been held.
Owner. Sam Reed
Next action. Sam Reed does not award a bid and does not issue a purchase order. Perry Voss, Willa Marsh, and Eden Crowe stay quote contacts only. Target 2026-12-15, planned.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Eighteen bids stay unawarded. There is no common released offer and no purchase order.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-BASIC-RFQ-PACKAGE-001 Rev C1
Basic — Can the supplier actually make and inspect it?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-02
Question. Can the supplier actually make and inspect it?
Evidence to record. Relevant capabilities, process limits, capacity, sample evidence, documented process scope, references, subcontractors and production location. Directory membership alone is not qualification.
Answer / assumption. No audit or capability study; fixture, gauge, and process qualification are required before any pilot. The eighteen bids are not an audit. No process-limit study, sample plaque, quality-system scope, subcontractor list, or production address is on file beyond the quote rows. Perry Voss, Willa Marsh, and Eden Crowe are quote contacts. Directory names and dated bids are not qualification. No award and no purchase order. CP01 through CP16 are draft and the phase is prototype. Controlling process steps are P01 through P14. Receive is P01. Latch assembly is P05. BASIC-05 is in-house labor for Sam Reed and is not engaged. The assembly site is unleased. Ira Bell at Bell Sample Lab is not contacted. Jordan Vale has no Basic electrical scope.
Result (Y/N/NA). N
Explanation. Qualification has to exist before a pilot. A dated bid is not a capability study. Naming a shop on BOM C1 does not create it. G4 remains No purchase order.
Status. Open — no capability evidence
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 bids on file, no award; BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16 draft; process flow P01 through P14. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed asks for no shop audit until a released drawing exists. The three bids stay unawarded. Ira Bell stays not contacted. Target 2026-12-15, planned.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No audit, process limit, or production address is on file. Directory names are not qualification.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1
Basic — What are the real costs and commitments?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-03
Question. What are the real costs and commitments?
Evidence to record. Unit prices at realistic volumes, tooling/NRE, MOQ, lead times, payment/deposit terms, currency, freight/trade terms, duties, scrap, quote expiry and cancellation/change terms.
Result (Y/N/NA). N
Status. Open — allowances uncommitted
Evidence / exact revision / URL and date. BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1 running total $5.78; BMT-BASIC-BOM-001 Rev C1 piece $5.78 and BASIC-16; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.
Owner. Sam Reed
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Allowances are recorded and uncommitted. The $12,000.00 tool is outside the cap. Nothing in this row is an awarded price.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1; BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1
Basic — Who owns tooling, data and changes?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-04
Question. Who owns tooling, data and changes?
Evidence to record. Tool ownership, custody, maintenance and transfer access; drawings and IP, approved substitutions and who can authorize changes.
Answer / assumption. Proposed company ownership of tooling/data; contract and ECN approval before later frozen changes. Tool owner is not one shared clause. FSW-B-2026-01 says the company owns the tool when paid. MPS-B-2026-02 says the shop keeps title until buyout. NLM-B-2026-03 says company title before kickoff, with the mold paid 100% before steel. BOM C1 BASIC-16 assigns that note to Alex Meadow. No custody, maintenance, insurance, or removal clause is signed. G3 is No freeze, so there is no frozen baseline for an ECN to control yet. DFM-06 still bars a resin or latch substitute unless the affected requirement is regressed. Lane Corwin has not cleared disclosure. The RFQ records no NDA and no disclosure.
Result (Y/N/NA). N
Explanation. Tool title is a proposal on a quote sheet, not a contract. Sending drawings before an NDA would disclose an unreleased concept. No one has done that.
Status. Open — tool title unsigned
Evidence / exact revision / URL and date. BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 tool-title clauses on FSW-B-2026-01, MPS-B-2026-02, and NLM-B-2026-03, none signed; BMT-BASIC-BOM-001 Rev C1 BASIC-16; BMT-BASIC-RFQ-PACKAGE-001 Rev C1 NDA field. Dated 2026-10-24.
Owner. Sam Reed
Next action. Alex Meadow does not sign a tool clause that is not drafted. Sam Reed keeps title as proposed only. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Tool title is unsigned. The three bids do not share one title clause. No NDA and no change baseline.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-RFQ-PACKAGE-001 Rev C1
Basic — How will we accept incoming parts and production output?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-05
Question. How will we accept incoming parts and production output?
Evidence to record. First-article/pilot evidence, critical characteristics, sampling rationale, measurement methods, traceability, nonconformance/rework and corrective actions.
Answer / assumption. Incoming configuration check, linked CP controls, planned FAI; no inspection evidence. Accept would use BOM C1 and draft controls CP01 through CP16, drawing revision Basic C1, phase prototype. FAI characteristics are Not measured. Tests T01 through T14 are unrun. CTQ01 through CTQ14 are untested. Planned unit IDs BASIC-X1-001 onward have no results. BMT-BASIC-CONTROL-PLAN-001 Rev C1 does not place a software fault-injection rig on Basic. Jordan Vale has no Basic electrical scope. The 2026-10-18 read of the no-electronics line is not an approval. There is no production sample plan and no reliability inference. Work instructions are draft and are not a released shop packet. Controlling process steps are P01 through P14. Receive is P01. Latch assembly is P05.
Result (Y/N/NA). N
Explanation. A planned FAI with every characteristic Not measured is not incoming inspection. The restart rule on the control plan names Alex and has never been used, because no build exists.
Status. Blocked — FAI not measured
Evidence / exact revision / URL and date. BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16 draft; process flow P01 through P14; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-BASIC-WORK-INSTRUCTIONS-001 Rev C1. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed does not open an FAI result. Controls stay draft. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. FAI characteristics are Not measured. Draft controls are not acceptance.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1; BMT-BASIC-WORK-INSTRUCTIONS-001 Rev C1
Basic — Can we deliver and recover from interruption?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-06
Question. Can we deliver and recover from interruption?
Evidence to record. Pilot quantity, ramp/capacity plan, long-lead parts, approved alternate sources, packaging/shipping trials, inventory and reorder points.
Answer / assumption. Assume single source initially; qualify backup before scale; no promised delivery. The comparison bids are not a delivery promise. A 10-unit first article is not built. The 3,000-a-year figure is a year-1 hypothesis and the amortization denominator, not a forecast and not a build quantity. Fictional Sample Works and Northline Molding bid 3,000 a year. Meadow Prototype Shop bids 800 a year and is not qualified as a backup. Risk B03 on BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, backup source due 2027-02-01, is planned and is not closed. Quoted tool leads on BASIC-01 are 14 weeks, 5 weeks, and 16 weeks. Those leads are not an 8-week promise. G1 is Hold tooling pending evidence. Tindall Sample Storage (Bea Tindall) is a storage candidate, not a factory. No reorder point and no delivery promise.
Result (Y/N/NA). N
Explanation. Capacity is not demonstrated by a cost denominator. Three unawarded mold bids plus an unqualified backup are not a recovery plan.
Status. Open — no recovery source
Evidence / exact revision / URL and date. BMT-BASIC-RFQ-PACKAGE-001 Rev C1 quantities and timeline; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 BASIC-01 tool leads 14 weeks, 5 weeks, and 16 weeks, unawarded; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 B03. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed does not promise a date. The backup shop stays unqualified. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The volume figure is a cost denominator. No delivery date is promised.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-RFQ-PACKAGE-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1
Basic — What must be in place after sale?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-07
Question. What must be in place after sale?
Evidence to record. Warranty, spare parts, service, complaints, traceability and recall/incident process appropriate to product/market.
Answer / assumption. Traceability, complaints, recall containment, returns and safe disposal required before sale. None of those processes exist as records. BOM C1 says a draft one-year manufacturing-defect remedy is still off the sheet, so this check sheet is not a warranty. G5 is No launch authorized. Nia Calder has not bound coverage. Robin Keel has not set the occupancy interval that CTQ06 leaves open. BASIC-14 says capacity is unrated, the target is one mouse, and the unit is uncertified. Nothing has been sold.
Result (Y/N/NA). N
Explanation. After-sale controls are a gate into G5, which is not authorized. An empty complaint log only means no product is in the field.
Status. Blocked — after-sale records absent
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1 BASIC-13 and BASIC-14; BMT-BASIC-STAGE-GATES-001 Rev C1 G5; CTQ06. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed does not write a warranty onto this sheet. The Robin Keel interval stays open. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. After-sale records are absent. Gate G5 is not a launch.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-STAGE-GATES-001 Rev C1; BMT-BASIC-CRITICAL-QUALITY-001 Rev C1
Basic — Is the first production order ready?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-08
Question. Is the first production order ready?
Evidence to record. Close or explicitly disposition DFM/test gaps, confirm current file package and cash need with the funding role. Record the person’s release decision; never infer authorization to place an order.
Answer / assumption. Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. G3 is No freeze. G4 is No purchase order. Missing drawings, supplier qualification, physical tests, and reviewed controls each block an order on their own. This row records the block. It is not a release by Alex Meadow or by Sam Reed.
Result (Y/N/NA). N
Explanation. PRODUCTION-08 is the stop rule for the sheet. A later quote does not satisfy it. The funding role has not confirmed cash.
Status. Blocked — release not recorded
Evidence / exact revision / URL and date. BMT-BASIC-STAGE-GATES-001 Rev C1 G0, G3, and G4; DFM-07; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1 status Not funded/committed. Dated 2026-10-24.
Owner. Sam Reed
Next action. Nobody places a purchase order. Revisit this row only when the evidence dated on this sheet is actually in the file. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. This row is the buy stop. It is not a release by Alex Meadow.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-STAGE-GATES-001 Rev C1; BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1
Basic — Is one released revision ready so the quoted shops would be on the same released part?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-09
Question. Is one released revision ready so the quoted shops would be on the same released part?
Evidence to record. Released drawing revision, BOM revision, material and finish, quantities, inspection, packaging, exclusions, and a disposition of every open DFM row, sent as one package.
Answer / assumption. Not ready. DFM-07 records BOM, cost, reviews, and requirements at C1, and no released CAD or drawings. DFM-03 (draft, walls, vent steel, latch undercuts) and DFM-04 (door fit, 30 mm grip clearance, shrink, wash aging, wear) are open. DFM-08 records no manufacturer comments and no accepted change. Eighteen bids are already on file for BASIC-01 through BASIC-06 and are not one released revision. No drawing has been released, so PRODUCTION-01 stays no. The package is not sent as an award.
Result (Y/N/NA). N
Explanation. Without one released revision, PRODUCTION-01 cannot be answered yes. The three shops' bids are not tied to one released window, pin, and carton.
Status. Blocked — drawing not released
Evidence / exact revision / URL and date. BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1 items DFM-03, DFM-04, DFM-07, DFM-08; BMT-BASIC-RFQ-PACKAGE-001 Rev C1 revision field. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed lists each open DFM row as a drawing note or a quote exclusion and does not send the package. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No released drawing, so the bids on file are not one released part.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1; BMT-BASIC-RFQ-PACKAGE-001 Rev C1
Basic — Is every CTQ measurable on a first-article record with a defined gauge and sample?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-10
Question. Is every CTQ measurable on a first-article record with a defined gauge and sample?
Evidence to record. For CTQ01 through CTQ14: gauge identity, range, calibration due date, method, sample size, and the FAI row that will store the reading. Record suitability as still pending.
Result (Y/N/NA). N
Explanation. Gauge suitability is still pending. Copying a software sample onto this mechanical trap would be wrong. Basic has no software feature. The tests-and-welfare line is the adopted $4,000.00, unfunded. FAI is not ready.
Status. Open — CTQ gauges not suitable
Evidence / exact revision / URL and date. CTQ01 through CTQ14; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-BASIC-BOM-001 Rev C1 BASIC-15; BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1 tests and welfare $4,000.00. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed maps one gauge to CTQ01 through CTQ14, records the $4,000.00 tests-and-welfare line, and does not contact Ira Bell. Target 2026-12-15, planned.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Gauge suitability is pending. FAI stays Not measured.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-CRITICAL-QUALITY-001 Rev C1; BMT-BASIC-TEMPLATE-FAI-REPORT-001 Rev C1; BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1
Basic — Is pilot cash identified, and is production tooling still stopped?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-11
Question. Is pilot cash identified, and is production tooling still stopped?
Evidence to record. Funded amount, the allowance line it would use, what is excluded, the signer, and the gate that still says hold. Record any mismatch between the funding worksheet and the BOM.
Result (Y/N/NA). Y
Status. Recorded — stop holds; cash unfunded
Evidence / exact revision / URL and date. BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1; BMT-BASIC-BOM-001 Rev C1 BASIC-16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 capital and bank lines. Dated 2026-10-24.
Owner. Sam Reed
Next action. Alex Meadow does not release the $5,000.00 prototype line and does not fold the $12,000.00 tool into the cap. Target 2026-12-15, planned.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The tooling stop holds. Pilot cash is an unfunded estimate, not a release.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1; BMT-BASIC-BOM-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1
Basic — Are sub-tier parts and special processes identified to a named source?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-12
Question. Are sub-tier parts and special processes identified to a named source?
Evidence to record. For the clear pane, vent ribs, slider, keyed pin, living latch, bait retainer, label, and instruction sheet: source, grade, and whether that source was contacted. State which cost is already inside a parent line.
Answer / assumption. Sub-tier sources beyond the three quote contacts are not named as awarded sources. Dated bids cover BASIC-01 through BASIC-06 only and are unawarded. Fictional Sample Works, Meadow Prototype Shop, and Fictional Northline Molding are quote contacts. BASIC-05 is in-house and is not engaged. BASIC-15 is Bell Sample Lab, and Ira Bell is not contacted. BASIC-07 through BASIC-14 are included splits. Their allowances sit inside the parent lines and are excluded from being added again to the $4.45 sum. No resin grade, no stainless grade, and no carton printer. DFM-06 bars a substitute resin or latch without regression.
Result (Y/N/NA). N
Explanation. Three named molders have unawarded bids on BASIC-01 through BASIC-06. That is not an awarded window process, stainless pin process, and print shop. Until those sub-tier sources are named, PRODUCTION-01 is still incomplete for BASIC-07 through BASIC-14.
Status. Open — sub-tier sources unnamed
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1 BASIC-07 through BASIC-15 supplier and source columns; DFM-06. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed adds a blank sub-tier list to the held package and leaves the blanks empty. He does not award a bid. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Sub-tier sources are unnamed. Included splits must not be priced twice.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1
Basic — Is the carton, the instruction revision, and the shipping trial defined for the packed unit?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-13
Question. Is the carton, the instruction revision, and the shipping trial defined for the packed unit?
Evidence to record. Carton spec, instruction revision tied to R03 and R06, case pack, transit trial, and freight term.
Answer / assumption. Not defined as a shippable pack. BASIC-06 is recycled card at $0.55 inside the $4.45 pre-tool sum and inside the $5.78 amortized piece. BASIC-13 and BASIC-14 are included splits of that $0.55, with allowances $0.08 and $0.12, and are excluded from being added again. The RFQ says a shipping qualification is planned. It has not been run. Freight and duty are excluded on every bid, so there is no landed freight term. BASIC-01 payment terms are filled on the three bids and are not a signed contract. The $5.78 figure is not a landed cost.
Result (Y/N/NA). N
Explanation. Using the packed estimate as a delivered cost would ignore freight, a carton trial, and the fact that the instruction sheet is still a BOM description.
Status. Open — pack and freight undefined
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1 BASIC-06, BASIC-13, BASIC-14; BMT-BASIC-RFQ-PACKAGE-001 Rev C1 packaging field; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 payment terms filled on the bids and not signed as a contract. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed marks freight and the shipping trial as exclusions on any later quote. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The instruction text is a bill-of-materials note. Freight is excluded on the bids and is not a landed cost.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-RFQ-PACKAGE-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1
Basic — Can each packed unit be traced to component lots and the assembly record?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-14
Question. Can each packed unit be traced to component lots and the assembly record?
Evidence to record. Lot-code format, traveler, resin lot, pivot lot, assembly record, carton date code, and retain rule.
Answer / assumption. Not traceable yet. The control plan says: Planned unit IDs BASIC-X1-001 onward; no results There is no lot-code format, no traveler, no resin lot, no pivot lot, no retain, and no carton date code. PRODUCTION-07 requires traceability before any sale. The method is blank.
Result (Y/N/NA). N
Explanation. Without a lot definition, a later complaint cannot be contained to a mold shot or a pin batch. That is the recall limit, and it is unmet.
Status. Open — traceability blank
Evidence / exact revision / URL and date. BMT-BASIC-CONTROL-PLAN-001 Rev C1 traceability field; BMT-BASIC-BOM-001 Rev C1 no lot code. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed drafts the lot-code rule on this sheet only and does not print labels. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Planned serials have no lot code, traveler, or retain.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-CONTROL-PLAN-001 Rev C1; BMT-BASIC-BOM-001 Rev C1
Basic — Which open process failures block acceptance of a pilot lot?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-15
Question. Which open process failures block acceptance of a pilot lot?
Evidence to record. Each of PF01 through PF48, its RPN and severity, and the control that would have to catch it. None is accepted.
Answer / assumption. Do not accept a pilot lot. BMT-BASIC-PFMEA-001 Rev C1 has 48 data rows, PF01 through PF48. Status is Open, Hold, or Blocked. No row is accepted. Severity 9 lines, highest RPN first: PF06 RPN 432 severity 9 (Window check skipped and the unit closed as acceptable; Open); PF02 RPN 252 severity 9 (Both vent ribs left on the floor side, beside the bait; Open); PF28 RPN 216 severity 9 (Gate closed without a written check interval; Blocked); PF30 RPN 216 severity 9 (Restart signed while a severity 9 row is still open; Hold); PF15 RPN 180 severity 9 (Retainer ribs short of the 20 N hold; Open); PF05 RPN 162 severity 9 (Uncaptured insert left in the bait opening; Open); PF09 RPN 144 severity 9 (Parting-line flash left across one rib root; Open); PF12 RPN 144 severity 9 (Pane missing, hazed, or soiled shut; Open); PF13 RPN 135 severity 9 (Instruction sheet states a multi-mouse capacity; Blocked); PF29 RPN 135 severity 9 (Live-animal note added to the gate to save a step; Blocked); PF36 RPN 135 severity 9 (Surrogate result written against the wrong shell; Open); PF45 RPN 135 severity 9 (Humane-claim sentence added to close the gate; Blocked); PF16 RPN 108 severity 9 (Prototype insert kitted in place of the captive pocket; Hold); PF39 RPN 108 severity 9 (Warning film from an older draft applied; Open). Robin Keel has not set the check interval and is not contacted. Robin Keel does not certify the trap. Linked controls are CP01 through CP16, draft. CP01 is the latch control and its shop step is P05. Receive is P01. Tests T01 through T14 are unrun. No build exists, and Alex Meadow has not authorized a restart.
Result (Y/N/NA). Y
Explanation. Accepting a pilot while every process row is still open, on hold, or blocked would skip the reaction rules on the control plan. The highest block cited here is PF06, window check skipped, RPN 432, severity 9.
Status. Recorded — pilot lot refused
Evidence / exact revision / URL and date. BMT-BASIC-PFMEA-001 Rev C1 PF01 through PF48, none accepted; BMT-BASIC-CONTROL-PLAN-001 Rev C1 CP01 through CP16. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed keeps the pilot quantity at zero while PF01 through PF48 stay unaccepted. Target 2026-12-15, planned.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Open PFMEA rows stay unaccepted. A pilot lot is refused. RPN is unchanged.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-PFMEA-001 Rev C1; BMT-BASIC-CONTROL-PLAN-001 Rev C1
Basic — What has to be signed before an RFQ goes out or tool steel is cut?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-16
Question. What has to be signed before an RFQ goes out or tool steel is cut?
Evidence to record. NDA status, tool title and removal, change notice, payment, cancellation, quote expiry, gauge and FAI inclusions, warranty, scrap, and a line that a directory name is not qualification.
Answer / assumption. Nothing is signed. Still missing: an NDA before disclosure (Lane Corwin is not engaged; the RFQ says no agreement and no disclosure), company tool title with removal rights, an ECN change notice, payment and cancellation, a quote expiry, gauge and FAI inclusions, warranty and scrap, and a sentence that being named on this sheet is not qualification. Perry Voss, Willa Marsh, and Eden Crowe have bids on file. No award and no purchase order. Cutting steel is already stopped under PRODUCTION-11.
Result (Y/N/NA). N
Explanation. An RFQ sent now would ask for a price on undefined steel and would disclose the concept without an NDA. That fails PRODUCTION-01 and PRODUCTION-04 together.
Status. Blocked — terms and NDA unsigned
Evidence / exact revision / URL and date. BMT-BASIC-RFQ-PACKAGE-001 Rev C1 NDA field; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 bid terms filled and not signed as a contract; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 Lane Corwin, Perry Voss, Willa Marsh. Dated 2026-10-24.
Owner. Sam Reed
Next action. Sam Reed holds the file. This row does not engage Lane Corwin. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No NDA, tool clause, or payment term is signed. The file stays in house.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-RFQ-PACKAGE-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1
Basic — Is the shell mold defined enough to cut the $12,000.00 tool?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-17
Question. Is the shell mold defined enough to cut the $12,000.00 tool?
Evidence to record. Cavity count, tool life, steel, T0 and T1 plan, shrink allowance for the door fit, who pays, and which gate allows steel.
Result (Y/N/NA). N
Status. Blocked — mold not released to cut
Evidence / exact revision / URL and date. BMT-BASIC-BOM-001 Rev C1 BASIC-16 allowance $12,000.00 outside the cap; BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1 amortization $1.33; DFM-02; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 FSW-B-2026-01, MPS-B-2026-02, and NLM-B-2026-03, unawarded. Dated 2026-10-24.
Owner. Sam Reed
Next action. Do not cut steel. BASIC-16 stays an allowance. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The mold is an allowance. Steel is not released.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-BOM-001 Rev C1; BMT-BASIC-TEMPLATE-COST-SHEET-001 Rev C1; BMT-BASIC-CHECK-SHEET-DFM-001 Rev C1; BMT-BASIC-TEMPLATE-QUOTE-COMPARISON-001 Rev C1
Basic — What blocks a first production order even with bids on file?
Project. Basic
Product revision. C1
Sheet revision. 1
Prepared by. Sam Reed
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. Suppliers and Production Readiness
Lead. Sam Reed
Item ID. PRODUCTION-18
Question. What blocks a first production order even with bids on file?
Evidence to record. The release record named in PRODUCTION-08, plus each independent missing record.
Answer / assumption. Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. The eighteen unawarded bids feed PRODUCTION-03. It would not be a purchase order. Alex Meadow has not recorded a release. This sheet is not that record.
Result (Y/N/NA). Y
Explanation. The decision being prepared is the next private feasibility gate, not a buy. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. This row keeps the order unplaced after the rest of the sheet is read.
Status. Recorded — order stays unplaced
Evidence / exact revision / URL and date. BMT-BASIC-STAGE-GATES-001 Rev C1 G0, G3, G4; PRODUCTION-08 on this sheet; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.
Owner. Sam Reed
Next action. Leave the order unplaced. Target 2026-12-15.
Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The blocks are independent. A later quote does not place the order.
Not-applicable reason. Applicable
Source guidance URLs. BMT-BASIC-STAGE-GATES-001 Rev C1; BMT-BASIC-FUNDING-WORKSHEET-001 Rev C1
Document administration