THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD

Capacity and bottleneck study — pilot assembly

DocumentBMT-CAPACITY-AND-BOTTLENECKS-D1
Revision / review dateD1 · 2027-06-30
Accountable ownerAlex Meadow

Scope: Capacity and bottleneck study — pilot assembly. Read the observations and decisions below within their stated conditions.

480-minute day; net available 420 min; demand 60 Basic / 20 Hotel units

Product / stepCycle minServersCapacity per dayConstraint / action
Basic kit31140Not constraint
Basic assemble6170Not constraint
Basic inspect8152.5Constraint; takt 420/60 = 7 min; add fixture
Basic inspect D15184After fixture: assembly constraint 70; 60 demand met
Hotel assemble15128Not constraint; takt 21 min
Hotel fault test24117.5Constraint; two parallel fixtures → 35/day

Verification

BasisDecision
Ten observed cycles per station, June 20; median shown; shared labor scheduled separately, not assumed simultaneousSam Reed verified 60 Basic and 20 Hotel-equivalent surrogate assemblies over separate shifts; Alex accepted June 25. Recheck before mixed-model scheduling.

Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.

Compare the reference example. Teaching data and signed dispositions: D1 scenario register.