THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD

Engineering change notice — D1 implemented changes

DocumentBMT-CHANGE-ON-PURPOSE-D1
Revision / review dateD1 · 2027-06-30
Accountable ownerAlex Meadow

Scope: Engineering change notice — D1 implemented changes. Read the observations and decisions below within their stated conditions.

ECN register

ChangeBefore → after / reasonVerification / affected recordsApproval / effective
ECN-D1-01 BasicFloating hinge → keyed positive latch; 12/100 rebounds0/1000; drawing, DFMEA, PFMEA, control plan and WI D1Alex May 10; Sam implemented May 20
ECN-D1-02 HotelMomentary flag → retained local occupancy; 8/100 misses0/1000; state machine, fault suite and WI D1Alex May 10; Jordan implemented May 22
ECN-D1-03 DroneReset permissive → hardware inhibit; 3/100 command faults30/30 losses inhibited; isolation diagram, test script D1Alex May 10; Jordan implemented May 24

Release audit

WithdrawalClose-out
C1 removed from 4/4 benches June 20; historical read-only C1 retainedIra verified evidence June 18; Alex signed controlled-scope effectiveness June 30.

Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.

Compare the reference example. Teaching data and signed dispositions: D1 scenario register.