THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD

RAID register — completed pilot decisions

DocumentBMT-RAID-LOG-D1
Revision / review dateD1 · 2027-06-30
Accountable ownerAlex Meadow

Scope: RAID register — completed pilot decisions. Read the observations and decisions below within their stated conditions.

R risks · A assumptions · I issues · D dependencies

ID / typeDescription / impactOwnerResponse / dependencyStatus / evidence
R01 / RiskBasic hinge can rebound; containment lossSam ReedKey hinge and retention gaugeClosed for pilot June 18; TR-B-D1 0/1000
R02 / RiskHotel alert loss can hide occupancyJordan ValeRetained local stateClosed for bench June 18; TR-H-D1 0/1000
R03 / RiskDrone flight hazards outside bench evidenceAlex MeadowNo-flight gate; isolate motorsAccepted as blocked scope June 25; no flight authorized
A01 / AssumptionSurrogate rig represents mechanical closure, not animal behaviorRobin KeelLimit claim to surrogate reliabilityValidated boundary June 25; animal performance not claimed
I01 / IssueFixture misalignment delayed run two daysSam ReedAlign and verify with gaugeResolved June 16; readiness WI issued June 30
D01 / DependencyIra check must precede gateIra BellTR-B/H/D-D1 → G4 reviewSatisfied June 18 → June 25
D02 / DependencyD1 work instructions before next pilotAlex MeadowWithdraw C1; station checkSatisfied June 20; 4/4 stations D1

Review cadence

Last reviewSign-off
Daily through test, weekly after June 18; June 30 review: zero overdue actionsAlex Meadow signed June 30; next review July 07

Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.

Compare the reference example. Teaching data and signed dispositions: D1 scenario register.