THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD
Time / cost / quality trade-off — D1 pilot plan
Scope: standalone synthetic teaching exercise for Time / cost / quality trade-off. All monetary inputs are invented example figures; no own-product offer, company finances or real transaction is asserted.
Isolated teaching estimates; no sale prices
| Product / option | Elapsed time | Incremental effort USD | Quality / safety effect | Decision |
|---|---|---|---|---|
| Basic skip gauge | 2 days | 0 | Retains visual ambiguity 72/80 checker agreement | Reject |
| Basic gauge + independent retest | 5 days | 480 | 80/80 agreement; 0/1000 rebounds | Select / Sam |
| Hotel ideal-only test | 1 day | 120 | Misses dropout coverage | Reject |
| Hotel replay + fault injection | 4 days | 600 | 0/1000 misses; 100/100 valid resets | Select / Jordan |
| Drone powered flight demo | 7 days | 2000 | Unassessed flight exposure | Reject regardless of speed |
| Drone isolated bench | 3 days | 360 | 30/30 loss cases inhibit; no flight evidence | Select / Ira |
Decision logic
| Constraint | Approval / actual |
|---|---|
| Safety criteria and independent evidence are mandatory; schedule and illustrative effort can trade only after that constraint is met | Alex approved May 10; test finish June 18 was two days late due fixture preparation; quality checks retained. Signed June 25. |
Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.
Compare the reference example. Teaching data and signed dispositions: D1 scenario register.