- Company
- The Better Mouse Trap Co.
- Project / product line
- Drone trap
- Document
- Drone Trap — New product development: the project review
- Document no.
- BMT-DRONE-CHECK-SHEET-PROJECT-001
- Revision
- C1
- Status
- Planning draft
- Start date
- 2026-10-24
- Revision date
- 2026-10-24
- Prepared by / owner
- Jordan Vale, flight research, DRONE-C1
- Checklist ID
- BMT-DRONE-CHECK-SHEET-PROJECT-001, Rev C1
- Scope
- DRONE-C1 project review on BMT-DRONE-CHECK-SHEET-PROJECT-001.
- Reviewer
- Casey Holt, Holt Sample Counsel (Planning draft read, not engaged)
- Review date
- 2026-11-01
- Team
- Alex Meadow, packet owner and no-flight gate; Jordan Vale, flight research; Sam Reed, mechanical interface; Robin Keel,
- Approved by
- review pending.
| Item / review question | Answer / finding | Result / status | Evidence | Responsibility / action |
|---|---|---|---|---|
Item ID: PROJECT-01 Question: Who will use it, who pays, and what problem is worth solving? | Answer / assumption: The named segment on BMT-DRONE-MARKET-CHECK-001 Rev C1 is controlled rural-site research partners, not a buyer and not a launch customer. Task as drawn: move one trap from a wall-side dock to a field position and back, without a consumer household as the operator. BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 holds 16 rows from 2026-08-04 through 2026-10-22. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 counts seven Grade B research interviews. Glen Archer (ME-D-01) uses a $240.00 ground contract, would allow a supervised walk-through, would not allow an unsupervised flight, and stated Not applicable — no transaction in this planning record for an aircraft. Hope Archer (ME-D-02) can permit entry and stated Not applicable — no transaction in this planning record for the product, with a $150.00 access fee for her time. Mina Croft (ME-D-04) refused to name a buyer. No row shows a switch from ground service to a flight. Year-1 commercial units authorized: 0. The 20-interview gate is not met. Company decision 2026-08-16 and risk B04: no consumer launch, no commercial unit, and no flight. Morgan Hale and the 5-store hardware path are Basic channel slots. They are not Drone customers. The commercial forecast on BMT-DRONE-SENSITIVITY-001 Rev C1 is 0 at every costing volume. Explanation: These notes are research-role interviews. They are not a served market and not a purchase. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 records the same seven interviews and no buyer. A count of zero conversations would contradict that sheet and BMT-DRONE-MARKET-CHECK-001. | Result (Y/N/NA): N Status: Open — 7 research interviews, no buyer | BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001, ME-D-01 through ME-D-16, 2026-08-04 through 2026-10-22; BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01; BMT-DRONE-MARKET-CHECK-001 Rev C1, | Owner: Alex Meadow Next action: Keep hardware off the sites named in the register. If further interviews are filed, keep the research role separate from any payer. Do not recruit a homeowner panel. Simulation and specialist review remain the 2027-06-15 gate. The 2026-11-15 session has not been held. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-01 remains open on the interview count. |
Item ID: PROJECT-02 Question: What are we making, and what is outside the first version? | Answer / assumption: Drone Trap C1: a trap capsule on a wall-side charging base; an autonomous aircraft would carry the capsule to a field, release on the ground, and return. Bluetooth and phone links are in the concept. Research drawing only. Out of every authorized version today: outdoor flight, live-animal carriage, a consumer sale, disease-control claims, child use, export, an FCC ID, a Remote ID claim, and a UL, NRTL, or UN 38.3 pass. The capsule still carries Basic-like CTQ01 through CTQ06. Flight and dock behavior are CTQ17 through CTQ30. None of those limits have a result. Success is not defined as a unit sold. Explanation: IP-02 names the believed point of novelty as the wall deployment and coupler with ground-only release. That sentence is an invention hypothesis. It is not a permit to fly and not a build release. Jordan Vale owns the concept file. No drawing is released. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; BMT-DRONE-CHECK-SHEET-IP-001 Rev C1 IP-02; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ17 through CTQ30; BMT-DRONE-REGULATORY-SCREENING-001 Rev | Owner: Jordan Vale Next action: Keep the file marked research concept. Do not release a mission profile. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-02 Estimate only. |
Item ID: PROJECT-03 Question: How many might we sell, at what price, through which channel and by when? | Answer / assumption: Costing illustration only: low/base/high 50/100/200 units a year. These are not a sales plan. BMT-DRONE-SENSITIVITY-001 Rev C1 states commercial sales are 0 at every costing volume. Hold price $1,499.00. Hardware sell-in assumption $824.45. Fee assumptions, not schedules: own website 3%, Amazon merchant fulfillment 15%. Channel order copied from BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 (website, then 5 hardware stores, then Amazon merchant fulfillment) is not adopted for this product. FBA and export are unchosen. Geography remains the U.S. illustrative base, and no field is selected. Company cash books 0 Drone units. Schedule G5 2027-06-28 is Not occurred and is not a ship date. No account is open. Explanation: A 100-unit column exists so the piece cost can be illustrated. It is not prospects times a purchase rate. No prospect list exists. Hardware wholesale contribution at that illustration is negative, so that channel would fail a stop test even if a sale were allowed, and a sale is not allowed. | Result (Y/N/NA): N Status: estimate — unvalidated | BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-01 and ECONOMICS-02; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 commercial-evidence line; | Owner: Alex Meadow Next action: Label 50/100/200 as costing only on every later Drone sheet. Do not enter a unit into the cash forecast. Revisit only inside the B04 review due 2027-03-01. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-03 Estimate only. |
Item ID: PROJECT-04 Question: What evidence says someone will buy it? | Answer / assumption: BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 is not an empty file. It holds 16 rows from 2026-08-04 through 2026-10-22, the register BMT-DRONE-CHECK-SHEET-LAUNCH-001 cites. Seven Grade B research interviews are filed. Price cards were refused and are not an offer: Sara Witt (ME-D-06) refused $1,199.00, $1,499.00, and $1,799.00. Hal Venn (ME-D-07) noted $1,499.00 and stated Not applicable — no transaction in this planning record. Wes Harrow (ME-D-16) chose the no-sale line and Not applicable — no transaction in this planning record. Every product amount on the 16 rows is Not applicable — no transaction in this planning record. Letters of intent 0. Paid orders 0. Repeat customers 0. The $1,499.00 figure is a hold price on a product marked no commercial unit. BMT-DRONE-LAUNCH-WORKSHEET-001 Rev C1 has no listing. Remy Sol is parked. Risk B04 forbids a consumer launch. The research interviews are not a consumer panel. BMT-COMPANY-TEMPLATE-SPENDING-REGISTER-001 shows Not applicable — no transaction in this planning record paid and Not applicable — no transaction in this planning record committed. Year-1 commercial units authorized: 0. Explanation: A refused card is a recorded choice, not willingness to pay and not a flight claim. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-02 records the same refusals and a pay line of Not applicable — no transaction in this planning record. Replacing the register with an empty file would hide ME-D-01 through ME-D-16. | Result (Y/N/NA): N Status: Open — research notes filed, pay line Not applicable — no transaction in this planning record | BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 ME-D-01 through ME-D-16; BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 and LAUNCH-02; BMT-DRONE-MARKET-CHECK-001 Rev C1; | Owner: Alex Meadow Next action: Do not run an external price test and do not open a listing. Leave the refused cards in the register. The B04 review is due 2027-03-01. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-04 remains open. Paid orders stay at 0. |
Item ID: PROJECT-05 Question: What must be learned before the next investment? | Answer / assumption: No Drone investment is in front of the company. Worksheet allowance $250,000.00 (rig $100,000.00; specialist testing and welfare $75,000.00; engineering and market $50,000.00; reserve $25,000.00) stops before production tooling and is not secured. It is outside the $80,000. Downside cash includes Not applicable — no transaction in this planning record of it. Next learning, if a later consent ever exists: ground simulation only, no flight. Finish condition for that future pack: release inhibited unless ground contact is confirmed (CTQ18, CTQ23), and a containment geofence that does not depend on the mission planner (CTQ20), with results filed or an explicit fail. Owner of the technical question: Jordan Vale. Action A03, connected-product and drone regulatory scope, is due 2026-12-15 and is open. Risk B04 is due 2027-03-01. Explanation: The BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 repeats $250,000.00 as a feasibility allowance. Company books do not. Quoting the worksheet number as an approved cap would overstate the cash plan. Nothing is committed. No lender is selected. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 unfunded-lines row; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; action A03; risk B04; | Owner: Jordan Vale Next action: Simulation and specialist review first; target 2027-06-15. Do not request the $250,000.00 allowance. Close the regulatory-scope note, or leave it open, by 2026-12-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-05 Estimate only. |
Item ID: PROJECT-06 Question: What are the milestones and dependencies? | Answer / assumption: BMT-DRONE-STAGE-GATES-001 Rev C1 read the same six names as Basic, and none are passed. G0 private planning only. G1 hold tooling. G2 hold external use. G3 no freeze. G4 no purchase order. G5 no launch. BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1, owner Jordan Vale, status Not occurred: G0 2027-01-28 through G5 2027-06-28, 30 days apart. Those dates are unfilled forecasts. They are not a release to spend and not a flight window. Company order is stricter: Drone stays research until Basic evidence exists and until B04 (due 2027-03-01) is closed. Outdoor flight is not a milestone on the authorized path. A ground simulation review targeted 2027-06-15 is the only technical look-ahead written on the BMT-DRONE-BOM-001 Rev C1 for navigation and Remote ID allowances. Explanation: A calendar G1 in February 2027 would still be blocked, because no surrogate result exists and the allowance is not funded. FAA screening status is No outdoor flight authorized. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-DRONE-STAGE-GATES-001 Rev C1; BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 FAA operation row; risk B04. | Owner: Jordan Vale Next action: Leave schedule actuals as Not occurred. Do not treat G5 2027-06-28 as a launch. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-06 Estimate only. |
Item ID: PROJECT-07 Question: Who owns each result and decision? | Answer / assumption: Alex Meadow owns the hold decision and any future consent to spend. Jordan Vale is the planned electrical, software, and flight lead, not engaged and not paid, and owns the Drone technical file if later engaged. Sam Reed owns Basic mechanism evidence and does not release Drone drawings. Robin Keel would have to set a welfare interval before any occupied capsule is discussed, and has not been contacted. Ira Bell is a Basic latch-and-vent candidate, not a flight-test lab. Lane Corwin has not cleared an NDA. Nia Calder has not said whether aviation or lithium charging sits inside the illustrative $2,000,000.00 liability figure. No specialist appointment exists. Explanation: Naming a flight lead does not authorize flight. A contractor cannot spend funds or speak for the company. Independent review on this sheet means a seat to be filled later. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-DRONE-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; action A03; BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1. | Owner: Alex Meadow Next action: Do not engage a flight specialist and do not contact a range. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-07 Estimate only. |
Item ID: PROJECT-08 Question: Should we go, revise, hold or stop? | Answer / assumption: Recommendation, not a signature: hold. Research paperwork only. Do not go to a prototype purchase, a flight, a field release, or a sale. Do not revise the concept into a consumer product inside this C1 file. Stop conditions already met for any commercial path: commercial unit count is 0, hardware-wholesale contribution is negative on the costing illustration, 12 severity-10 failure modes are open, and no outdoor flight is authorized. Unresolved before any future allowance: A03 regulatory scope, B04, welfare interval, FAA and FCC and battery rows, and an NDA. Authorized next work: none that spends money. A ground-simulation plan may be written. It may not be flown and it may not be bought. Explanation: BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16 already parks Drone outside the cash plan. This row does not reopen that decision. Revise would require a new concept revision, not an edit to the forecast. | Result (Y/N/NA): N Status: estimate — unvalidated | BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; risk B04; BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 FAA row; BMT-DRONE-DFMEA-001 Rev C1 | Owner: Alex Meadow Next action: Record the hold against B04. Do not place a Drone line on the 2026-11-15 Basic agenda as a spend item. Technical look-ahead remains 2027-06-15 and is unfunded. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-08 Estimate only. |
Item ID: PROJECT-09 Question: Which requirements and critical characteristics gate any future work? | Answer / assumption: CTQ01 through CTQ30 are proposed, review pending. Capsule set CTQ01 through CTQ06 matches the Basic door, vent, release, wash, bait, and inspection limits, including 100 dry cycles, two vent paths, 30 mm finger clearance, and a 20 N bait pull. Added safety-critical items include CTQ08 occupancy sensing with zero false-empty in the concept trial, CTQ12 rechargeable pack with no wet charging and a proposed 45 C cutoff, CTQ17 carriage stop before contact, CTQ18 two retention paths and no release before ground contact, CTQ19 no rotor spin until a guarded clearance is verified, CTQ20 geofence independent of the planner, CTQ23 door inhibited in flight, CTQ25 operation inside a permitted regime, CTQ26 Remote ID not claimed, CTQ27 dock contacts, and CTQ30 return docking. Tests T01 through T30 are indexes. Results: zero. BMT-DRONE-CONTROL-PLAN-001 Rev C1 CP01 through CP30 is prototype phase. No gauge and no aircraft are purchased. Explanation: The highest-severity characteristics are not the capsule door. They are flight, energy, and release. A passed paper index is not a passed test. Remote ID equipment is a planning allowance of $18.00 on DRONE-14 and is excluded from the $740.00 piece until CTQ26 is closed. | Result (Y/N/NA): N Status: open | BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ30; BMT-DRONE-TEST-PLAN-001 Rev C1 T01 through T30; BMT-DRONE-CONTROL-PLAN-001 Rev C1 CP01 through CP30; BMT-DRONE-BOM-001 | Owner: Jordan Vale Next action: Leave T01 through T30 empty. Do not buy a radio, a cell, or a rotor. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-09 Open. |
Item ID: PROJECT-10 Question: Which open failure chains can stop the project, and what RPN is still open? | Answer / assumption: Drone BMT-DRONE-DFMEA-001 Rev C1 has 30 scored rows. Open RPN sum is 10,980. Severity split: 12 at S10, 12 at S9, 4 at S8, 2 at S7. Highest open RPNs: DF25 aircraft operation scope 630 (S10 O7 D9, projected 350); DF24 release on unsuitable land 567 (S9 O7 D9, projected 315); DF21 mission battery exhausted 480 (S10 O6 D8, projected 240); DF28 launch in weather 480 (S10 O6 D8, projected 240); DF30 missed return dock 480 (S10 O6 D8, projected 240). Also open at 450: DF20 navigation 450 (projected 210), DF22 command link 450 (projected 210), DF29 malicious command 450 (projected 210). BMT-DRONE-RISK-PRIORITY-001 Rev C1 order uses the projected M-lines, led by DF25-M 350. Projected RPN is not a demonstrated residual. Every S10 and S9 row stays open regardless of rank. Process FMEA PF01 through PF30 mirrors the set. No row is closed. Explanation: A low projected rank cannot retire a flyaway, a falling capsule, or an in-flight door. DF25 alone, at occurrence 7 and detection 9, is an unproven concept, not a controlled operation. | Result (Y/N/NA): Y Status: open | BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-RISK-PRIORITY-001 Rev C1; BMT-DRONE-PFMEA-001 Rev C1 PF01 through PF30. | Owner: Jordan Vale Next action: Do not rank the project ready because a projected RPN exists. Keep all 12 severity-10 modes open. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-10 Open. |
Item ID: PROJECT-11 Question: What does one illustrated unit cost, and what contribution remains by channel? | Answer / assumption: Illustrated piece, not a quote. Cash content behind the base is the $540.00 sum on the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 plus $200.00 of tooling amortization. Amortized piece: low 50 units $940.00; base 100 units $740.00; high 200 units $640.00. Tooling allowance $60,000.00 sits on DRONE-18 and on the capsule line. Adding DRONE-18 into the piece again would count the tool twice, so the held piece stays $740.00. Hold price $1,499.00. ECONOMICS-06 contributions at the base illustration: own website $550.08; hardware wholesale -$49.50; Amazon merchant fulfillment $355.20. Product-sheet allocated annual fixed cost $100,000.00. That $100,000.00 is not in the company downside. Company downside Drone development spend is Not applicable — no transaction in this planning record. Return reserve and a lifetime cloud reserve are explicit on the BMT-DRONE-CHANNEL-ECONOMICS-001 Rev C1 and are unverified. No supplier quote supports any material line. Explanation: Negative hardware contribution means the 5-store path fails on the illustration. Positive website contribution is not cash, because commercial units are 0 and no website account exists. Founder pay is excluded. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 piece $740.00; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-03 and ECONOMICS-06; | Owner: Alex Meadow Next action: Do not put $60,000.00 tooling or the $100,000.00 fixed allocation into the company cash sheet. Leave the piece at $740.00 until CTQ26 changes the Remote ID allowance. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-11 Estimate only. |
Item ID: PROJECT-12 Question: What cash is planned for this product, and what allowance is excluded? | Answer / assumption: No Drone cash is planned. Owner capital $80,000. Worksheet allowance, not secured and not a consent: $250,000.00, split rig $100,000.00, testing and welfare $75,000.00, engineering and market $50,000.00, reserve $25,000.00, stop before production tooling. Downside closes (January $72,000.00, February $64,000.00, March $44,000.00, November floor $20,000.00, December $17,000.00) include Not applicable — no transaction in this planning record Drone development. Debt Not applicable — no transaction in this planning record. No investor, lender, or grant is selected. Insurance illustration $2,000,000.00 is not a binder, and Nia Calder has not said whether lithium charging or aviation is inside it. A release of Drone funds would also have to clear the $20,000.00 floor. No such release exists. Explanation: The BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 can be misread as a $250,000.00 next round. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 row 14 is the controlling statement: the allowance is outside the contribution and outside the cap. Action A12 reconciled Basic splits only. It did not fund Drone. | Result (Y/N/NA): Y Status: estimate — unvalidated | BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 rows for amount, cash downside, reserve floor, and unfunded lines; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1; action A12. | Owner: Alex Meadow Next action: Do not request a draw, a card, or a purchase. Leave the allowance parked through the B04 date of 2027-03-01. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-12 Estimate only. |
Item ID: PROJECT-13 Question: What is believed to be new, who owns it, and what has already been disclosed? | Answer / assumption: Believed new, unvalidated (IP-02): wall deployment and coupler, and a ground-only release architecture. Contributors, assignments unsigned: Alex Meadow concept; Sam Reed mechanism; Jordan Vale electronics and flight. Disclosure history: no external disclosure, no sale, no offer. Route chosen: private BMT-DRONE-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1 and a search plan. Provisional filing not chosen. Trademark unsearched. Freedom-to-operate review not performed. A patent, if one were later filed, would not authorize flight and would not clear third-party airframe, radio, or battery rights. Drawings stay withheld. Perry Voss and Willa Marsh are Basic tooling names on the BMT-DRONE-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 and have no quote on file. They are not a Drone source. Explanation: Counsel review is recommended before any disclosure. Lane Corwin has not been asked. No opinion exists. | Result (Y/N/NA): N Status: open | BMT-DRONE-CHECK-SHEET-IP-001 Rev C1 IP-02, IP-04, IP-05, IP-06, IP-08; BMT-DRONE-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-DRONE-BOM-001 Rev C1 quote note on DRONE-18. | Owner: Jordan Vale Next action: Send no drawing and no mission description outside the company file. Do not file a provisional. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-13 Open. |
Item ID: PROJECT-14 Question: Which regulatory questions are open, and which operations are refused? | Answer / assumption: BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 has the four physical-trap rows plus six more, all uncleared. CPSC: No CPC claimed. EPA and state device: No EPA approval or registration claim. Animal release: No destination approved. Materials and claims: no poison, no medical claim, no certified-humane claim. FCC: No FCC ID or authorization exists. Electrical and battery: No UL, NRTL, IP, or UN 38.3 pass claimed. Privacy and security: No privacy certification asserted. FAA operation: No outdoor flight authorized. FAA registration and Remote ID: No registration or Remote ID claim. Animal carriage: no live-animal flight without an independent welfare protocol, and none is planned. Jordan Vale owns the open scope note, action A03, due 2026-12-15. Explanation: Screening is not a waiver and not a certificate. Writing Remote ID equipment into the BMT-DRONE-BOM-001 Rev C1 as an $18.00 allowance does not create a Remote ID claim. CTQ26 stays open on purpose. | Result (Y/N/NA): Y Status: open | BMT-DRONE-REGULATORY-SCREENING-001 Rev C1, 10 regimes; action A03; CTQ15, CTQ25, CTQ26; BMT-DRONE-BOM-001 Rev C1 DRONE-14. | Owner: Jordan Vale Next action: File the scope note as still open if the source review is not done. Due 2026-12-15. Do not request an outdoor flight. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-14 Open. |
Item ID: PROJECT-15 Question: Who could build hardware, and which purchases are forbidden now? | Answer / assumption: BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18 is an illustration dated 2026-10-24. Examples, all without a supplier quote: capsule material $8.00 plus process $5.00; wall carriage material $35.00 plus process $15.00; guarded frame material $60.00 plus process $20.00; flight battery material $65.00 plus process $5.00; dock charger material $35.00 plus process $10.00. Assembly labor DRONE-10 names Fictional Sample Works on the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 and states that the name is not an order. DRONE-18 repeats the same $60,000.00 tool and lists Fictional Sample Works and Meadow Prototype Shop (Willa Marsh) with no quote on file, no validity date, and no correspondence. No RFQ has been sent. No purchase order exists. G4 text is No purchase order. Basic candidates are not cleared for this drawing. Explanation: A budgetary tool figure is not a supplier selection. Releasing the capsule mold drawing would also be a disclosure under IP-05, which records no disclosure so far. | Result (Y/N/NA): N Status: blocked | BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18; BMT-DRONE-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 no quote on file; BMT-DRONE-ROADBLOCKS-001 Rev C1; action A07 pattern, Basic RFQ | Owner: Jordan Vale Next action: Send no RFQ and no model file. Leave both named shops uncontacted for this product. Look again only after B04, due 2027-03-01, and still do not buy. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-15 Blocked. |
Item ID: PROJECT-16 Question: What test and welfare evidence exists, and what trial is forbidden? | Answer / assumption: T01 through T30 are indexed to the CTQ set, including flight, dock, weather, and cyber rows. Methods that mention a rig are proposed. No rig, no battery, and no airframe have been bought. Result count is zero. Live animals are forbidden. Occupied-capsule flight is forbidden. Outdoor flight is forbidden. Robin Keel has not set a check interval, including for a capsule that never leaves the bench. Ira Bell is not engaged and is not a flight lab. Weather, return-to-dock, and in-flight release are simulation questions until a specialist review says otherwise. That review is not scheduled as a purchased test. Explanation: The original learning sentence that only names the capture door is incomplete for this product. Door and vent still matter for the capsule. They do not address DF25, DF21, DF24, or DF23. Those modes are why the next look is a simulation rather than a tool. | Result (Y/N/NA): N Status: blocked | BMT-DRONE-TEST-PLAN-001 Rev C1 T01 through T30; BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 empty; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 animal-carriage row; | Owner: Jordan Vale Next action: Do not book a range, a live trial, or a charged-pack test. Simulation and specialist review first; target 2027-06-15. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-16 Blocked. |
Item ID: PROJECT-17 Question: Which company controls block this product even if a simulation looks acceptable? | Answer / assumption: The LLC is not formed. No EIN. No account. No debt facility. Nia Calder has not been asked whether lithium charging or aviation sits inside the illustrative $2,000,000.00 liability figure, and no policy is bound. Lot trace, complaint log, and recall note are blocked with Basic action A14, due 2026-12-01, and are equally empty for a Drone unit. No pilot unit may be built. Ellis Brook is not a credit source. Casey Holt has not cleared a filing. A research hold does not create an insurance exception. Explanation: Even a clean bench simulation would not open a flight or a sale. G5 conditions are unmet, and B04 independently forbids the commercial path. | Result (Y/N/NA): N Status: blocked | BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Nia Calder and Ellis Brook; action A14; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1. | Owner: Alex Meadow Next action: Do not send a broker packet that asks for an aviation bind. Leave the question unasked until counsel clears formation. Broker date on BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1 is 2026-12-01. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-17 Blocked. |
Item ID: PROJECT-18 Question: What is frozen, and which records must move when an input changes? | Answer / assumption: Nothing is frozen. ECN practice on the C1 package is an initial issue with no design change. This review is sheet revision 1, prepared 2026-10-24, Planning draft. Downstream records that must move together: CTQ01 through CTQ30, BMT-DRONE-DFMEA-001 Rev C1 and BMT-DRONE-PFMEA-001 Rev C1, CP01 through CP30, T01 through T30, BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18, the $740.00 piece, BMT-DRONE-SENSITIVITY-001 Rev C1 volumes, the $250,000.00 unsecured allowance, and the FAA and FCC screening rows. Changing the Remote ID allowance, the tooling count, or a severity score without those sheets creates a false piece cost or a false residual. Commercial unit count stays 0 unless a company decision withdraws B04. No such decision exists. Explanation: Schedule dates owned by Jordan Vale are unfilled forecasts. Editing them to look current would imply a flight window. The rule is a written change, then the downstream list. | Result (Y/N/NA): Y Status: open | this sheet revision 1, 2026-10-24; BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-BOM-001 Rev C1; BMT-COMPANY-TEMPLATE-BUSINESS-DECISION-LOG-001 Rev C1 2026-08-16. | Owner: Jordan Vale Next action: Do not open a design ECN for a flight change, because no flight change is authorized. Next document look is the unfunded 2027-06-15 simulation review. Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-18 Open. |
Drone Trap — New Product Development: The Project Review — supporting detail
Drone Trap — Who will use it, who pays, and what problem is worth solving?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-01
Question. Who will use it, who pays, and what problem is worth solving?
Evidence to record. Name the user, buyer, task, alternatives and evidence from actual conversations. Separate founder beliefs from observations. State whether any commercial buyer is in scope.
Answer / assumption. The named segment on BMT-DRONE-MARKET-CHECK-001 Rev C1 is controlled rural-site research partners, not a buyer and not a launch customer. Task as drawn: move one trap from a wall-side dock to a field position and back, without a consumer household as the operator. BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 holds 16 rows from 2026-08-04 through 2026-10-22. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 counts seven Grade B research interviews. Glen Archer (ME-D-01) uses a $240.00 ground contract, would allow a supervised walk-through, would not allow an unsupervised flight, and stated Not applicable — no transaction in this planning record for an aircraft. Hope Archer (ME-D-02) can permit entry and stated Not applicable — no transaction in this planning record for the product, with a $150.00 access fee for her time. Mina Croft (ME-D-04) refused to name a buyer. No row shows a switch from ground service to a flight. Year-1 commercial units authorized: 0. The 20-interview gate is not met. Company decision 2026-08-16 and risk B04: no consumer launch, no commercial unit, and no flight. Morgan Hale and the 5-store hardware path are Basic channel slots. They are not Drone customers. The commercial forecast on BMT-DRONE-SENSITIVITY-001 Rev C1 is 0 at every costing volume.
Result (Y/N/NA). N
Explanation. These notes are research-role interviews. They are not a served market and not a purchase. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 records the same seven interviews and no buyer. A count of zero conversations would contradict that sheet and BMT-DRONE-MARKET-CHECK-001.
Status. Open — 7 research interviews, no buyer
Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001, ME-D-01 through ME-D-16, 2026-08-04 through 2026-10-22; BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01; BMT-DRONE-MARKET-CHECK-001 Rev C1, commercial sales 0; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16.
Owner. Alex Meadow
Next action. Keep hardware off the sites named in the register. If further interviews are filed, keep the research role separate from any payer. Do not recruit a homeowner panel. Simulation and specialist review remain the 2027-06-15 gate. The 2026-11-15 session has not been held.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-01 remains open on the interview count.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-MARKET-CHECK-001 Rev C1; BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1
Drone Trap — What are we making, and what is outside the first version?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-02
Question. What are we making, and what is outside the first version?
Evidence to record. Concept revision, intended use, must-have outcomes, exclusions and measurable success criteria where known. Name the flight and live-animal exclusions in the same sentence as the concept.
Answer / assumption. Drone Trap C1: a trap capsule on a wall-side charging base; an autonomous aircraft would carry the capsule to a field, release on the ground, and return. Bluetooth and phone links are in the concept. Research drawing only. Out of every authorized version today: outdoor flight, live-animal carriage, a consumer sale, disease-control claims, child use, export, an FCC ID, a Remote ID claim, and a UL, NRTL, or UN 38.3 pass. The capsule still carries Basic-like CTQ01 through CTQ06. Flight and dock behavior are CTQ17 through CTQ30. None of those limits have a result. Success is not defined as a unit sold.
Result (Y/N/NA). Y
Explanation. IP-02 names the believed point of novelty as the wall deployment and coupler with ground-only release. That sentence is an invention hypothesis. It is not a permit to fly and not a build release. Jordan Vale owns the concept file. No drawing is released.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; BMT-DRONE-CHECK-SHEET-IP-001 Rev C1 IP-02; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ17 through CTQ30; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 FAA rows.
Owner. Jordan Vale
Next action. Keep the file marked research concept. Do not release a mission profile. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-02 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; BMT-DRONE-CHECK-SHEET-IP-001 Rev C1; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1
Drone Trap — How many might we sell, at what price, through which channel and by when?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-03
Question. How many might we sell, at what price, through which channel and by when?
Evidence to record. Low/base/high units by month or quarter, geography and channel. Show prospects × purchase rate × units or stores × units per store per week × weeks. Record assumptions and capacity limits; market size is not a sales forecast. Show the company rule that commercial units are zero.
Answer / assumption. Costing illustration only: low/base/high 50/100/200 units a year. These are not a sales plan. BMT-DRONE-SENSITIVITY-001 Rev C1 states commercial sales are 0 at every costing volume. Hold price $1,499.00. Hardware sell-in assumption $824.45. Fee assumptions, not schedules: own website 3%, Amazon merchant fulfillment 15%. Channel order copied from BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 (website, then 5 hardware stores, then Amazon merchant fulfillment) is not adopted for this product. FBA and export are unchosen. Geography remains the U.S. illustrative base, and no field is selected. Company cash books 0 Drone units. Schedule G5 2027-06-28 is Not occurred and is not a ship date. No account is open.
Result (Y/N/NA). N
Explanation. A 100-unit column exists so the piece cost can be illustrated. It is not prospects times a purchase rate. No prospect list exists. Hardware wholesale contribution at that illustration is negative, so that channel would fail a stop test even if a sale were allowed, and a sale is not allowed.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-01 and ECONOMICS-02; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 commercial-evidence line; BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1.
Owner. Alex Meadow
Next action. Label 50/100/200 as costing only on every later Drone sheet. Do not enter a unit into the cash forecast. Revisit only inside the B04 review due 2027-03-01.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-03 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1
Drone Trap — What evidence says someone will buy it?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-04
Question. What evidence says someone will buy it?
Evidence to record. Dated interviews, observed problems, price tests, pilots, orders or other evidence. Distinguish interest, nonbinding intent, paid orders and repeat sales. State the commercial-evidence rule for this product.
Result (Y/N/NA). N
Explanation. A refused card is a recorded choice, not willingness to pay and not a flight claim. BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-02 records the same refusals and a pay line of Not applicable — no transaction in this planning record. Replacing the register with an empty file would hide ME-D-01 through ME-D-16.
Status. Open — research notes filed, pay line Not applicable — no transaction in this planning record
Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 ME-D-01 through ME-D-16; BMT-DRONE-CHECK-SHEET-LAUNCH-001 LAUNCH-01 and LAUNCH-02; BMT-DRONE-MARKET-CHECK-001 Rev C1; BMT-DRONE-LAUNCH-WORKSHEET-001 Rev C1; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16 and 2026-09-13.
Owner. Alex Meadow
Next action. Do not run an external price test and do not open a listing. Leave the refused cards in the register. The B04 review is due 2027-03-01.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-04 remains open. Paid orders stay at 0.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-MARKET-CHECK-001 Rev C1; BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 Rev C1; BMT-DRONE-LAUNCH-WORKSHEET-001 Rev C1; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1
Drone Trap — What must be learned before the next investment?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-05
Question. What must be learned before the next investment?
Evidence to record. Open customer, IP, safety, technical, cost and channel risks; one next experiment, owner, finish condition and capped budget. Separate a worksheet allowance from cash the company has actually set aside.
Result (Y/N/NA). Y
Explanation. The BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 repeats $250,000.00 as a feasibility allowance. Company books do not. Quoting the worksheet number as an approved cap would overstate the cash plan. Nothing is committed. No lender is selected.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 unfunded-lines row; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; action A03; risk B04; CTQ18, CTQ20, CTQ23.
Owner. Jordan Vale
Next action. Simulation and specialist review first; target 2027-06-15. Do not request the $250,000.00 allowance. Close the regulatory-scope note, or leave it open, by 2026-12-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-05 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1
Drone Trap — What are the milestones and dependencies?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-06
Question. What are the milestones and dependencies?
Evidence to record. Concept review → feasibility and economics → prototype/user evidence → production readiness → launch → post-launch review. Tailor the sequence; do not imply every gate is already passed. Say which dates are unfilled forecasts.
Answer / assumption. BMT-DRONE-STAGE-GATES-001 Rev C1 read the same six names as Basic, and none are passed. G0 private planning only. G1 hold tooling. G2 hold external use. G3 no freeze. G4 no purchase order. G5 no launch. BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1, owner Jordan Vale, status Not occurred: G0 2027-01-28 through G5 2027-06-28, 30 days apart. Those dates are unfilled forecasts. They are not a release to spend and not a flight window. Company order is stricter: Drone stays research until Basic evidence exists and until B04 (due 2027-03-01) is closed. Outdoor flight is not a milestone on the authorized path. A ground simulation review targeted 2027-06-15 is the only technical look-ahead written on the BMT-DRONE-BOM-001 Rev C1 for navigation and Remote ID allowances.
Result (Y/N/NA). Y
Explanation. A calendar G1 in February 2027 would still be blocked, because no surrogate result exists and the allowance is not funded. FAA screening status is No outdoor flight authorized.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-STAGE-GATES-001 Rev C1; BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 FAA operation row; risk B04.
Owner. Jordan Vale
Next action. Leave schedule actuals as Not occurred. Do not treat G5 2027-06-28 as a launch. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-06 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-STAGE-GATES-001 Rev C1; BMT-DRONE-TEMPLATE-SCHEDULE-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1
Drone Trap — Who owns each result and decision?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-07
Question. Who owns each result and decision?
Evidence to record. Named responsible people/assistants, exact inputs and revisions, agreed review participants and dates only when agreed.
Answer / assumption. Alex Meadow owns the hold decision and any future consent to spend. Jordan Vale is the planned electrical, software, and flight lead, not engaged and not paid, and owns the Drone technical file if later engaged. Sam Reed owns Basic mechanism evidence and does not release Drone drawings. Robin Keel would have to set a welfare interval before any occupied capsule is discussed, and has not been contacted. Ira Bell is a Basic latch-and-vent candidate, not a flight-test lab. Lane Corwin has not cleared an NDA. Nia Calder has not said whether aviation or lithium charging sits inside the illustrative $2,000,000.00 liability figure. No specialist appointment exists.
Result (Y/N/NA). Y
Explanation. Naming a flight lead does not authorize flight. A contractor cannot spend funds or speak for the company. Independent review on this sheet means a seat to be filled later.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-DRONE-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; action A03; BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1.
Owner. Alex Meadow
Next action. Do not engage a flight specialist and do not contact a range. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-07 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-DRONE-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1
Drone Trap — Should we go, revise, hold or stop?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-08
Question. Should we go, revise, hold or stop?
Evidence to record. Evidence reviewed, decision author/date, unresolved conditions, authorized next work and links to the exact released files. Revisit downstream sheets when an input changes.
Answer / assumption. Recommendation, not a signature: hold. Research paperwork only. Do not go to a prototype purchase, a flight, a field release, or a sale. Do not revise the concept into a consumer product inside this C1 file. Stop conditions already met for any commercial path: commercial unit count is 0, hardware-wholesale contribution is negative on the costing illustration, 12 severity-10 failure modes are open, and no outdoor flight is authorized. Unresolved before any future allowance: A03 regulatory scope, B04, welfare interval, FAA and FCC and battery rows, and an NDA. Authorized next work: none that spends money. A ground-simulation plan may be written. It may not be flown and it may not be bought.
Result (Y/N/NA). N
Explanation. BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16 already parks Drone outside the cash plan. This row does not reopen that decision. Revise would require a new concept revision, not an edit to the forecast.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; risk B04; BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 FAA row; BMT-DRONE-DFMEA-001 Rev C1 severity count.
Owner. Alex Meadow
Next action. Record the hold against B04. Do not place a Drone line on the 2026-11-15 Basic agenda as a spend item. Technical look-ahead remains 2027-06-15 and is unfunded.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-08 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-TEMPLATE-DECISION-LOG-001 Rev C1; BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1
Drone Trap — Which requirements and critical characteristics gate any future work?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-09
Question. Which requirements and critical characteristics gate any future work?
Evidence to record. Requirement ID, CTQ ID, proposed criticality, acceptance limit, linked test, and whether any result exists. Cover the capsule set and the flight set.
Answer / assumption. CTQ01 through CTQ30 are proposed, review pending. Capsule set CTQ01 through CTQ06 matches the Basic door, vent, release, wash, bait, and inspection limits, including 100 dry cycles, two vent paths, 30 mm finger clearance, and a 20 N bait pull. Added safety-critical items include CTQ08 occupancy sensing with zero false-empty in the concept trial, CTQ12 rechargeable pack with no wet charging and a proposed 45 C cutoff, CTQ17 carriage stop before contact, CTQ18 two retention paths and no release before ground contact, CTQ19 no rotor spin until a guarded clearance is verified, CTQ20 geofence independent of the planner, CTQ23 door inhibited in flight, CTQ25 operation inside a permitted regime, CTQ26 Remote ID not claimed, CTQ27 dock contacts, and CTQ30 return docking. Tests T01 through T30 are indexes. Results: zero. BMT-DRONE-CONTROL-PLAN-001 Rev C1 CP01 through CP30 is prototype phase. No gauge and no aircraft are purchased.
Result (Y/N/NA). N
Explanation. The highest-severity characteristics are not the capsule door. They are flight, energy, and release. A passed paper index is not a passed test. Remote ID equipment is a planning allowance of $18.00 on DRONE-14 and is excluded from the $740.00 piece until CTQ26 is closed.
Status. open
Evidence / exact revision / URL and date. BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ30; BMT-DRONE-TEST-PLAN-001 Rev C1 T01 through T30; BMT-DRONE-CONTROL-PLAN-001 Rev C1 CP01 through CP30; BMT-DRONE-BOM-001 Rev C1 DRONE-14.
Owner. Jordan Vale
Next action. Leave T01 through T30 empty. Do not buy a radio, a cell, or a rotor. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-09 Open.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-CRITICAL-QUALITY-001 Rev C1; BMT-DRONE-TEST-PLAN-001 Rev C1; BMT-DRONE-CONTROL-PLAN-001 Rev C1; BMT-DRONE-BOM-001 Rev C1
Drone Trap — Which open failure chains can stop the project, and what RPN is still open?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-10
Question. Which open failure chains can stop the project, and what RPN is still open?
Evidence to record. Design FMEA ID, severity, occurrence, detection, RPN, and projected RPN for the modes that dominate the rank. Use RPN. State how many severity-10 modes exist.
Answer / assumption. Drone BMT-DRONE-DFMEA-001 Rev C1 has 30 scored rows. Open RPN sum is 10,980. Severity split: 12 at S10, 12 at S9, 4 at S8, 2 at S7. Highest open RPNs: DF25 aircraft operation scope 630 (S10 O7 D9, projected 350); DF24 release on unsuitable land 567 (S9 O7 D9, projected 315); DF21 mission battery exhausted 480 (S10 O6 D8, projected 240); DF28 launch in weather 480 (S10 O6 D8, projected 240); DF30 missed return dock 480 (S10 O6 D8, projected 240). Also open at 450: DF20 navigation 450 (projected 210), DF22 command link 450 (projected 210), DF29 malicious command 450 (projected 210). BMT-DRONE-RISK-PRIORITY-001 Rev C1 order uses the projected M-lines, led by DF25-M 350. Projected RPN is not a demonstrated residual. Every S10 and S9 row stays open regardless of rank. Process FMEA PF01 through PF30 mirrors the set. No row is closed.
Result (Y/N/NA). Y
Explanation. A low projected rank cannot retire a flyaway, a falling capsule, or an in-flight door. DF25 alone, at occurrence 7 and detection 9, is an unproven concept, not a controlled operation.
Status. open
Evidence / exact revision / URL and date. BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-RISK-PRIORITY-001 Rev C1; BMT-DRONE-PFMEA-001 Rev C1 PF01 through PF30.
Owner. Jordan Vale
Next action. Do not rank the project ready because a projected RPN exists. Keep all 12 severity-10 modes open. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-10 Open.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-RISK-PRIORITY-001 Rev C1; BMT-DRONE-PFMEA-001 Rev C1
Drone Trap — What does one illustrated unit cost, and what contribution remains by channel?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-11
Question. What does one illustrated unit cost, and what contribution remains by channel?
Evidence to record. Cash and amortized piece cost at low/base/high costing volume, tooling cash, hold price, contribution by channel, and the statement that the company cash case does not use these units.
Result (Y/N/NA). Y
Explanation. Negative hardware contribution means the 5-store path fails on the illustration. Positive website contribution is not cash, because commercial units are 0 and no website account exists. Founder pay is excluded.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 piece $740.00; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-03 and ECONOMICS-06; BMT-DRONE-BOM-001 Rev C1 DRONE-18.
Owner. Alex Meadow
Next action. Do not put $60,000.00 tooling or the $100,000.00 fixed allocation into the company cash sheet. Leave the piece at $740.00 until CTQ26 changes the Remote ID allowance.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-11 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-SENSITIVITY-001 Rev C1; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1; BMT-DRONE-CHECK-SHEET-ECONOMICS-001 Rev C1; BMT-DRONE-BOM-001 Rev C1
Drone Trap — What cash is planned for this product, and what allowance is excluded?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-12
Question. What cash is planned for this product, and what allowance is excluded?
Evidence to record. Owner capital, the Basic cap, this product's worksheet allowance and its split, debt, and the downside months that contain no Drone spend.
Result (Y/N/NA). Y
Explanation. The BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 can be misread as a $250,000.00 next round. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 row 14 is the controlling statement: the allowance is outside the contribution and outside the cap. Action A12 reconciled Basic splits only. It did not fund Drone.
Status. estimate — unvalidated
Evidence / exact revision / URL and date. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 rows for amount, cash downside, reserve floor, and unfunded lines; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1; action A12.
Owner. Alex Meadow
Next action. Do not request a draw, a card, or a purchase. Leave the allowance parked through the B04 date of 2027-03-01.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-12 Estimate only.
Not-applicable reason. Applicable
Source guidance URLs. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1
Drone Trap — What is believed to be new, who owns it, and what has already been disclosed?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-13
Question. What is believed to be new, who owns it, and what has already been disclosed?
Evidence to record. Invention point, contributors, disclosure history, route chosen, and freedom-to-operate status. Note that a flight concept is not a clearance to operate.
Answer / assumption. Believed new, unvalidated (IP-02): wall deployment and coupler, and a ground-only release architecture. Contributors, assignments unsigned: Alex Meadow concept; Sam Reed mechanism; Jordan Vale electronics and flight. Disclosure history: no external disclosure, no sale, no offer. Route chosen: private BMT-DRONE-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1 and a search plan. Provisional filing not chosen. Trademark unsearched. Freedom-to-operate review not performed. A patent, if one were later filed, would not authorize flight and would not clear third-party airframe, radio, or battery rights. Drawings stay withheld. Perry Voss and Willa Marsh are Basic tooling names on the BMT-DRONE-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 and have no quote on file. They are not a Drone source.
Result (Y/N/NA). N
Explanation. Counsel review is recommended before any disclosure. Lane Corwin has not been asked. No opinion exists.
Status. open
Evidence / exact revision / URL and date. BMT-DRONE-CHECK-SHEET-IP-001 Rev C1 IP-02, IP-04, IP-05, IP-06, IP-08; BMT-DRONE-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-DRONE-BOM-001 Rev C1 quote note on DRONE-18.
Owner. Jordan Vale
Next action. Send no drawing and no mission description outside the company file. Do not file a provisional. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-13 Open.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-CHECK-SHEET-IP-001 Rev C1; BMT-DRONE-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-DRONE-BOM-001 Rev C1
Drone Trap — Which regulatory questions are open, and which operations are refused?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-14
Question. Which regulatory questions are open, and which operations are refused?
Evidence to record. Each regime on the screening sheet, the status sentence, and the operation that remains unauthorized.
Answer / assumption. BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 has the four physical-trap rows plus six more, all uncleared. CPSC: No CPC claimed. EPA and state device: No EPA approval or registration claim. Animal release: No destination approved. Materials and claims: no poison, no medical claim, no certified-humane claim. FCC: No FCC ID or authorization exists. Electrical and battery: No UL, NRTL, IP, or UN 38.3 pass claimed. Privacy and security: No privacy certification asserted. FAA operation: No outdoor flight authorized. FAA registration and Remote ID: No registration or Remote ID claim. Animal carriage: no live-animal flight without an independent welfare protocol, and none is planned. Jordan Vale owns the open scope note, action A03, due 2026-12-15.
Result (Y/N/NA). Y
Explanation. Screening is not a waiver and not a certificate. Writing Remote ID equipment into the BMT-DRONE-BOM-001 Rev C1 as an $18.00 allowance does not create a Remote ID claim. CTQ26 stays open on purpose.
Status. open
Evidence / exact revision / URL and date. BMT-DRONE-REGULATORY-SCREENING-001 Rev C1, 10 regimes; action A03; CTQ15, CTQ25, CTQ26; BMT-DRONE-BOM-001 Rev C1 DRONE-14.
Owner. Jordan Vale
Next action. File the scope note as still open if the source review is not done. Due 2026-12-15. Do not request an outdoor flight.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-14 Open.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-REGULATORY-SCREENING-001 Rev C1; BMT-DRONE-BOM-001 Rev C1
Drone Trap — Who could build hardware, and which purchases are forbidden now?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-15
Question. Who could build hardware, and which purchases are forbidden now?
Evidence to record. BMT-DRONE-BOM-001 Rev C1 identifier, what the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 assumes, quote status, and the ban on releasing a shop.
Answer / assumption. BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18 is an illustration dated 2026-10-24. Examples, all without a supplier quote: capsule material $8.00 plus process $5.00; wall carriage material $35.00 plus process $15.00; guarded frame material $60.00 plus process $20.00; flight battery material $65.00 plus process $5.00; dock charger material $35.00 plus process $10.00. Assembly labor DRONE-10 names Fictional Sample Works on the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 and states that the name is not an order. DRONE-18 repeats the same $60,000.00 tool and lists Fictional Sample Works and Meadow Prototype Shop (Willa Marsh) with no quote on file, no validity date, and no correspondence. No RFQ has been sent. No purchase order exists. G4 text is No purchase order. Basic candidates are not cleared for this drawing.
Result (Y/N/NA). N
Explanation. A budgetary tool figure is not a supplier selection. Releasing the capsule mold drawing would also be a disclosure under IP-05, which records no disclosure so far.
Status. blocked
Evidence / exact revision / URL and date. BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18; BMT-DRONE-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 no quote on file; BMT-DRONE-ROADBLOCKS-001 Rev C1; action A07 pattern, Basic RFQ hold.
Owner. Jordan Vale
Next action. Send no RFQ and no model file. Leave both named shops uncontacted for this product. Look again only after B04, due 2027-03-01, and still do not buy.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-15 Blocked.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-BOM-001 Rev C1; BMT-DRONE-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-DRONE-ROADBLOCKS-001 Rev C1
Drone Trap — What test and welfare evidence exists, and what trial is forbidden?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-16
Question. What test and welfare evidence exists, and what trial is forbidden?
Evidence to record. Test index coverage, result count, live-animal rule, flight rule, and the welfare owner.
Answer / assumption. T01 through T30 are indexed to the CTQ set, including flight, dock, weather, and cyber rows. Methods that mention a rig are proposed. No rig, no battery, and no airframe have been bought. Result count is zero. Live animals are forbidden. Occupied-capsule flight is forbidden. Outdoor flight is forbidden. Robin Keel has not set a check interval, including for a capsule that never leaves the bench. Ira Bell is not engaged and is not a flight lab. Weather, return-to-dock, and in-flight release are simulation questions until a specialist review says otherwise. That review is not scheduled as a purchased test.
Result (Y/N/NA). N
Explanation. The original learning sentence that only names the capture door is incomplete for this product. Door and vent still matter for the capsule. They do not address DF25, DF21, DF24, or DF23. Those modes are why the next look is a simulation rather than a tool.
Status. blocked
Evidence / exact revision / URL and date. BMT-DRONE-TEST-PLAN-001 Rev C1 T01 through T30; BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 empty; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1 animal-carriage row; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Robin Keel.
Owner. Jordan Vale
Next action. Do not book a range, a live trial, or a charged-pack test. Simulation and specialist review first; target 2027-06-15.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-16 Blocked.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-TEST-PLAN-001 Rev C1; BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1; BMT-DRONE-REGULATORY-SCREENING-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1
Drone Trap — Which company controls block this product even if a simulation looks acceptable?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-17
Question. Which company controls block this product even if a simulation looks acceptable?
Evidence to record. Formation, bank, insurance, recall, and the named gaps for aviation and lithium.
Answer / assumption. The LLC is not formed. No EIN. No account. No debt facility. Nia Calder has not been asked whether lithium charging or aviation sits inside the illustrative $2,000,000.00 liability figure, and no policy is bound. Lot trace, complaint log, and recall note are blocked with Basic action A14, due 2026-12-01, and are equally empty for a Drone unit. No pilot unit may be built. Ellis Brook is not a credit source. Casey Holt has not cleared a filing. A research hold does not create an insurance exception.
Result (Y/N/NA). N
Explanation. Even a clean bench simulation would not open a flight or a sale. G5 conditions are unmet, and B04 independently forbids the commercial path.
Status. blocked
Evidence / exact revision / URL and date. BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Nia Calder and Ellis Brook; action A14; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1.
Owner. Alex Meadow
Next action. Do not send a broker packet that asks for an aviation bind. Leave the question unasked until counsel clears formation. Broker date on BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1 is 2026-12-01.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-17 Blocked.
Not-applicable reason. Applicable
Source guidance URLs. BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1
Drone Trap — What is frozen, and which records must move when an input changes?
Project. Drone Trap
Product revision. C1
Sheet revision. 1
Prepared by. Jordan Vale
Date. 2026-10-24
Target market / jurisdiction. U.S. adults; Wisconsin illustrative base
Decision being prepared. Next private feasibility gate
Sheet. New Product Development: The Project Review
Lead. Jordan Vale
Item ID. PROJECT-18
Question. What is frozen, and which records must move when an input changes?
Evidence to record. ECN status, sheet revision, and the downstream Drone records a change would touch.
Answer / assumption. Nothing is frozen. ECN practice on the C1 package is an initial issue with no design change. This review is sheet revision 1, prepared 2026-10-24, Planning draft. Downstream records that must move together: CTQ01 through CTQ30, BMT-DRONE-DFMEA-001 Rev C1 and BMT-DRONE-PFMEA-001 Rev C1, CP01 through CP30, T01 through T30, BMT-DRONE-BOM-001 Rev C1 DRONE-01 through DRONE-18, the $740.00 piece, BMT-DRONE-SENSITIVITY-001 Rev C1 volumes, the $250,000.00 unsecured allowance, and the FAA and FCC screening rows. Changing the Remote ID allowance, the tooling count, or a severity score without those sheets creates a false piece cost or a false residual. Commercial unit count stays 0 unless a company decision withdraws B04. No such decision exists.
Result (Y/N/NA). Y
Explanation. Schedule dates owned by Jordan Vale are unfilled forecasts. Editing them to look current would imply a flight window. The rule is a written change, then the downstream list.
Status. open
Evidence / exact revision / URL and date. this sheet revision 1, 2026-10-24; BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-BOM-001 Rev C1; BMT-COMPANY-TEMPLATE-BUSINESS-DECISION-LOG-001 Rev C1 2026-08-16.
Owner. Jordan Vale
Next action. Do not open a design ECN for a flight change, because no flight change is authorized. Next document look is the unfunded 2027-06-15 simulation review.
Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-18 Open.
Not-applicable reason. Applicable
Source guidance URLs. BMT-DRONE-DFMEA-001 Rev C1; BMT-DRONE-BOM-001 Rev C1; BMT-COMPANY-TEMPLATE-BUSINESS-DECISION-LOG-001 Rev C1
Document administration
Scope. DRONE-C1 project review on BMT-DRONE-CHECK-SHEET-PROJECT-001. Bridge serials DRONE-X1-001 through DRONE-X1-010, none built. No flight article. Year-1 commercial units authorized: 0. Capsule tooling allowance $60,000.00. The $250,000.00 research allowance is unfunded.
Team. Alex Meadow, packet owner and no-flight gate; Jordan Vale, flight research; Sam Reed, mechanical interface; Robin Keel, animal-welfare reviewer
Approved by. review pending. Alex Meadow, Planning draft C1, has not signed. The $250,000.00 research allowance is not drawn. Year-1 commercial units authorized: 0.
Preparation: Jordan Vale, scenario attribution, 2026-10-24. Signature: unsigned. Review: pending; no reviewer signature or date. Approval: withheld; no approver signature or date.