The Better Mouse Trap Co. / sample paperwork

Drone Trap — What the prototype needs to prove

Drone TrapRevision C12026-10-24Planning draft18 entries
Drone Trap — What the prototype needs to proveBMT-DRONE-CHECK-SHEET-PROTOTYPE-001 · Rev C1
Company
The Better Mouse Trap Co.
Project / product line
Drone trap
Document
Drone Trap — What the prototype needs to prove
Document no.
BMT-DRONE-CHECK-SHEET-PROTOTYPE-001
Revision
C1
Status
Planning draft
Start date
2026-10-24
Revision date
2026-10-24
Prepared by / owner
Jordan Vale, flight research, DRONE-C1
Checklist ID
BMT-DRONE-CHECK-SHEET-PROTOTYPE-001, Rev C1
Scope
DRONE-C1 capsule on the bench and in simulation.
Reviewer
Casey Holt
Review date
2026-11-01
Team
Alex Meadow, packet owner and no-flight gate; Jordan Vale, flight research; Sam Reed, mechanical interface; Robin Keel,
Approved by
review pending.
Drone Trap — What the Prototype Needs to Prove
Item / review questionAnswer / findingResult / statusEvidenceResponsibility / action

Item ID: PROTOTYPE-01

Question: Which question is this prototype answering?

Answer / assumption: First question is the capsule door, on the bench. CTQ01 / R01 / DF01, RPN 210: the door stays latched through 100 dry cycles on each of 10 capsule surrogates, then a 5 N pull (BMT-DRONE-TEST-MATRIX-001 Rev C1 T01). Flight, release in the air, and outdoor operation are not this question. Drone Trap C1 is a research concept: a wall-side base, an aircraft that carries the capsule to a field, a release, and a return. The commercial forecast is 0 units. There is no consumer launch. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 records T01 through T34 as Not run. The $250,000.00 allowance is not secured. Risk B04 (Jordan Vale, due 2027-03-01) keeps flight closed.

Explanation: The capsule door is the bench question. Outdoor flight is not this prototype. Risk B04 is open. DF01 RPN 210 is proposed.

Result (Y/N/NA): Y

Status: Recorded — first question named, untested

BMT-DRONE-TEST-MATRIX-001 Rev C1 T01; BMT-DRONE-DFMEA-001 Rev C1 DF01 RPN 210; risk B04 due 2027-03-01 open; 2026-10-24; Not run

Owner: Jordan Vale

Next action: Simulation and specialist review first; write the bench T01 method card for the capsule door; do not schedule a flight; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. First question is recorded as C1 intent and is not accepted.

Item ID: PROTOTYPE-02

Question: What is the exact configuration?

Answer / assumption: Configuration is Drone Trap C1, research only. BMT-DRONE-BOM-001 Rev C1: DRONE-01 ventilated capsule, DRONE-02 wall deployment carriage, DRONE-03 guarded frame, DRONE-04 motors, ESC, and prop set (qty 4), DRONE-05 navigation (GNSS, IMU, and vision), DRONE-06 redundant payload latch, DRONE-07 flight battery, DRONE-08 dock charger and interlocks, DRONE-09 radio and local gateway, DRONE-10 assembly and HIL calibration, DRONE-11 shipping crate and manual. Reserved IDs DRONE-X1-001 through DRONE-X1-010 for capsules and one HIL harness. No aircraft leaves a guarded fixture under this plan. Nothing is built. BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total is $740.00 against the $1,499.00 hold price. That total is a worksheet, not a quote. DRONE-01 on BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 is $213.00 after low-volume amortization, not the $13.00 piece price. Thirty-three dated bids are on file and none is awarded: Fictional Sample Works (Perry Voss, 2026-10-02, valid through 2026-12-31), Fictional Meadow Prototype Shop (Willa Marsh, 2026-10-06, valid through 2026-12-05), and Fictional Northline Molding (Eden Crowe, 2026-10-09, valid through 2027-01-07), parts DRONE-01 through DRONE-11. The C1 bill is 21 rows, assembly DRONE-C1-ASSY plus DRONE-01 through DRONE-18. Labor is DRONE-10. Tooling is DRONE-18. Commercial units authorized remain 0. No FCC ID is invented. Remote ID applicability (CTQ26 / T26) is unresolved and blocks any outdoor flight.

Explanation: DRONE-01 through DRONE-11 are the quoted subset. The C1 bill runs through DRONE-18. No free-flight article is in this revision. No FCC identification is claimed.

Result (Y/N/NA): Y

Status: Recorded — configuration listed, none built

BMT-DRONE-BOM-001 Rev C1, 21 rows, DRONE-C1-ASSY and DRONE-01 through DRONE-18; quoted subset DRONE-01 through DRONE-11; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total

Owner: Jordan Vale

Next action: Simulation and specialist review first; hold ID templates DRONE-X1-001 through DRONE-X1-010 and the HIL harness; record that no free-flight article is in C1; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Configuration matches the C1 bill.

Item ID: PROTOTYPE-03

Question: How will we judge success before testing?

Answer / assumption: Criteria are copied from BMT-DRONE-TEST-MATRIX-001 Rev C1 and are review pending. Capsule bench, n=10 where the matrix says so: T01 door, 100 dry cycles and 5 N (CTQ01, DF01 RPN 210); T02 two vent paths open in a bedding surrogate (CTQ02, DF02 RPN 252); T03 fingers 30 mm clear, 10 adults, unloaded (CTQ03, DF03 RPN 192); T04 tool-free open and no visible fluorescent soil, n=10, not a biological claim (CTQ04, DF04 RPN 240); T05 bait captive at 20 N (CTQ05, DF05 RPN 162); T06 occupancy visible without opening, interval unset (CTQ06, DF06 RPN 432); T07 baffle not back-driven at 2 N, three-compartment target (CTQ07, DF07 RPN 280). Capsule electronics on the isolated rig: T08 zero false-empty in 100 dusted placements (CTQ08, DF08 RPN 360); T09 local indicator works offline and the app marks offline within 5 minutes (CTQ09, DF09 RPN 432); T10 physical-button provisioning and 50 denied unauthorized attempts (CTQ10, DF10 RPN 320); T11 capture indication survives power loss at each update phase (CTQ11, DF11 RPN 288); T12 no wet charge, proposed 45 C cutoff, specialist only (CTQ12, DF12 RPN 320, severity 10); T13 power inhibited when the cassette is unseated (CTQ13, DF13 RPN 315); T14 no precise location, 30-day retention, deletion path (CTQ14, DF14 RPN 280); T15 no module choice until grant and host rules are reviewed, no FCC ID invented (CTQ15, DF15 RPN 360); T16 capacity not rated (CTQ16, DF16 RPN 360). Aircraft items are simulation or a guarded fixture only, not outdoor flights: T17 carriage stops before contact, supervised enable (CTQ17, DF17 RPN 360); T18 two retention paths, release only after ground-contact confirmation (CTQ18, DF18 RPN 400, severity 10); T19 no rotor spin until the guarded zone is verified (CTQ19, DF19 RPN 350, severity 10); T20 geofence independent of the planner, abort on estimator disagreement (CTQ20, DF20 RPN 450); T21 modeled return reserve at least 40% (CTQ21, DF21 RPN 480); T22 phone is not safety-critical, safe state on link loss (CTQ22, DF22 RPN 450); T23 release only when stationary, motors stopped, on a validated surface (CTQ23, DF23 RPN 320); T24 no field release until species rules, landowner permission, and a welfare note exist (CTQ24, DF24 RPN 567); T25 no unattended outdoor launch (CTQ25, DF25 RPN 630); T26 Remote ID applicability resolved before any outdoor flight (CTQ26, DF26 RPN 360); T27 no charge after a failed dock alignment (CTQ27, DF27 RPN 400); T28 research envelope only, dry and wind below 3 m/s, not a cleared flight limit (CTQ28, DF28 RPN 480); T29 signed mission plan, no remote bypass of the safety envelope (CTQ29, DF29 RPN 450); T30 one failed docking attempt, then a designated safe land, no repeated wall approach (CTQ30, DF30 RPN 480). The highest first-pass RPN is DF25 at 630. The highest projected line is DF25-M at 350, severity 10. Residual RPN total is 8464. The 80% review line is 6771.2. Accepted residual is 0. All of these limits are proposed. T31 through T34 and CTQ31 through CTQ34 are on the same matrix, unapproved, and Not run. DFMEA C1 is DF01 through DF60 (60 data rows). Radio-module hold is process step P18. Test T15 is not process step P15.

Explanation: T01 through T34 limits are targets. Aircraft rows are fixture, harness, or document checks. First-pass DF25 is 630. Projected DF25-M is 350. The residual total is 8464.

Result (Y/N/NA): N

Status: Open — acceptance lines not initialed

BMT-DRONE-TEST-MATRIX-001 Rev C1 T01-T34; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01-CTQ34; BMT-DRONE-DFMEA-001 Rev C1 DF01-DF60; first-pass DF25 630; projected DF25-M 350;

Owner: Jordan Vale

Next action: Simulation and specialist review first; copy T01 through T34 acceptance lines and mark aircraft rows as fixture, HIL, or document check; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Limits are copied and not initialed.

Item ID: PROTOTYPE-04

Question: Is the test safe and representative?

Answer / assumption: Surrogates first. No live-animal protocol is approved, and no outdoor-flight protocol is approved. B04 stays open: no flight. If the allowance were ever released, rotor work would start in a guarded ground fixture with guards fitted (CTQ19, DF19 RPN 350). Payload release is not demonstrated in the air (CTQ18 RPN 400 and CTQ23). Carriage trials are unloaded and supervised (CTQ17). Dock and pack faults go to a battery specialist. Jordan Vale does not run destructive pack tests (CTQ12 and CTQ27, both severity 10). Phone loss is a safe-state case, not a cue to continue (CTQ22, DF22 RPN 450). The weather line is a research envelope, not permission to launch (CTQ28). Stop on unexpected motion, heat, estimator disagreement, an interlock defeat, or a second docking approach (CTQ30). Nia Calder (Calder Sample Risk) has not been contacted. Aviation, lithium, and autonomous-flight questions on the BMT-COMPANY-INSURANCE-REQUEST-001 are open. The $2,000,000.00 liability figure is an illustration, not a binder, and drone flight sits outside that illustration.

Explanation: Heat, unexpected motion, link loss, and a second docking approach are written stops. B04 stays open. Nia Calder has not been contacted.

Result (Y/N/NA): N

Status: Open — safeguards not signed

BMT-DRONE-DFMEA-001 Rev C1 DF19, DF18, DF22, DF25, DF30; BMT-COMPANY-TEMPLATE-BUSINESS-RISKS-001 risk B04; BMT-COMPANY-INSURANCE-REQUEST-001, Nia Calder not contacted; 2026-10-24

Owner: Jordan Vale

Next action: Simulation and specialist review first; write fixture stop rules for heat, motion, link loss, and a second docking approach; leave B04 open; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Safeguards are written and not signed.

Item ID: PROTOTYPE-05

Question: What happened, including failures?

Answer / assumption: No tests have been run. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 records T01 through T34 as Not run. No cycle counts, no HIL logs, no temperature readings, and no fixture video. Projected RPNs are predictions. The highest projected line is DF25-M at 350. First-pass DF25 is 630 and is not a result. Residual RPN total is 8464. Simulation output, if it is produced later, is labeled simulated and is not a flight result. No failure has been observed, and no pass has been recorded.

Explanation: T01 through T34 are Not run. There is no harness log and no fixture video to file as a result.

Result (Y/N/NA): N

Status: Blocked — no run on file

BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 T01-T34 Not run; 2026-10-24; no HIL log and no fixture video

Owner: Jordan Vale

Next action: Simulation and specialist review first; leave BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 T01 through T34 at Not run; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No raw sheet is on file.

Item ID: PROTOTYPE-06

Question: What can we conclude, and what remains unproven?

Answer / assumption: Only planning completeness can be assessed. There is no verification of R01 through R30, and tests T31 through T34 are also Not run. Research notes are on file and are not a flight clearance or a sale. BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001, recorded by Alex Meadow, holds 16 research rows dated 2026-08-04 through 2026-10-22. There is no homeowner panel. Grade B interviews are 7: ME-D-01 Glen Archer, ME-D-02 Hope Archer, ME-D-03 Cal Brewer, ME-D-04 Mina Croft, ME-D-09 Joel Pruitt, ME-D-12 Farah Ost, and ME-D-14 Ida Kline. Five pay-line cards are filed at Not applicable — no transaction in this planning record: ME-D-06 Sara Witt, ME-D-07 Hal Venn, ME-D-08 Cora Bend, ME-D-10 Anya Briggs, and ME-D-16 Wes Harrow. ME-D-11 Levi Dunn is wording with no price. Every product pay line on the cards is Not applicable — no transaction in this planning record. That set is not a commercial price test. The concept price of $1,499.00 is not an offer. No research partner authorized a flight. Still unproven on the hardware: a field capture, a legal flight, Remote ID compliance, return reserve in real wind, animal welfare in the air, production repeatability, and any sale at $1,499.00. Residual RPN total is 8464. The 80% review line is 6771.2. Accepted residual is 0. First-pass DF25 is 630. The highest projected line is DF25-M unattended route at 350, severity 10. Radio-module hold is process step P18. Commercial units are 0. Jordan Vale owns a failed characteristic and a full retest of that test ID. A pass on T01 would not open outdoor flight. The only later recommendation this packet could support is G1 for the bench capsule, after a consent that does not exist. G2 through G5 stay shut. No release claim is made.

Explanation: No flight, welfare, Remote ID, or sales conclusion is available. Year-1 commercial units authorized: 0.

Result (Y/N/NA): N

Status: Blocked — evidence not established

BMT-DRONE-MARKET-CHECK-001 Rev C1 and BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 Rev C1, 16 research rows, 7 Grade B, 5 pay-line cards at Not applicable — no transaction in this planning record; BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev

Owner: Jordan Vale

Next action: Simulation and specialist review first; record that no flight, welfare, Remote ID, or sales conclusion is available; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No performance conclusion is available.

Item ID: PROTOTYPE-07

Question: Which characteristics must this prototype prove, and which are deferred?

Answer / assumption: The written plan covers CTQ01 through CTQ34 and T01 through T34. CTQ01 through CTQ30 is a short index of that plan. The build scope, if a consent ever exists, is narrower than the plan: capsule surrogates for T01 through T07; the HIL harness for T08 through T16 and for simulated T20, T21, T22, T25, T26, T28, and T29; a guarded ground fixture for T17, T18, T19, T23, T27, and T30. T24 and T25 are document checks, not flights. Outdoor launch, a live animal, a field release, a consumer sale, and production tooling stay deferred. They sit outside the allowance line that stops before tooling. Production control-plan rows CP01 through CP34 do not replace these tests. Radio-module hold is process step P18, not P15. Test T15 does not rename that step. Action A03 (regulatory scope, Jordan Vale, due 2026-12-15) is open and blocks treating the aircraft as cleared.

Explanation: Outdoor launch, a live payload, and a field release stay off the build list. Action A03 is open.

Result (Y/N/NA): Y

Status: Recorded — outdoor work deferred

BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01-CTQ34; action A03 due 2026-12-15 open; 2026-10-24; outdoor flight deferred

Owner: Jordan Vale

Next action: Simulation and specialist review first; keep outdoor launch, live payload, and field release off the build list; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The in-scope list is recorded as intent and is not accepted.

Item ID: PROTOTYPE-08

Question: What is the sample size rationale and how is each unit identified?

Answer / assumption: DRONE-X1-001 through DRONE-X1-010 cover capsule mechanics. Order on those units is cycles, then the bait pull, then wash, and only on units that still meet the latch line. n=10 is the CTQ01 screening count, not a reliability sample and not a fleet sample. The HIL harness is one rig, not ten aircraft. T08 is 100 placements. T10 is 50 denied attempts. T21 is a model case at the proposed 40% return reserve, not a flown discharge. There is no flight-article sample in C1. A damaged capsule is retired, not quietly replaced. No ID is cut until Alex Meadow consents, and this sheet does not ask for that consent ahead of Basic evidence.

Explanation: n=10 capsules is the screen. DRONE-X1-001 through DRONE-X1-010 are not issued. There is no flight-article sample.

Result (Y/N/NA): N

Status: Open — serials reserved, none issued

BMT-DRONE-TEST-MATRIX-001 Rev C1 sample notes; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; 2026-10-24; no flight article; IDs not issued

Owner: Jordan Vale

Next action: Simulation and specialist review first; document n=10 capsules and one HIL rig; issue no hardware ID ahead of Basic evidence; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Serials are reserved and not issued.

Item ID: PROTOTYPE-09

Question: What build method differs from the intended production part?

Answer / assumption: Production intent includes a composite guarded frame (DRONE-03) and a protected lithium pack (DRONE-07). The C1 prototype plan does not build a free-flight article. A bench capsule may be printed if vent, door, and latch geometry match C1. A dev-board gateway is not DRONE-09. Motors may be fitted only in the guarded fixture. A bench spin is not an aircraft acceptance. The $740.00 BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 total and the $213.00 amortized capsule are not demonstrated by a printed part. Remote ID hardware is not selected. CTQ26 stays unresolved. Thirty-three dated bids are on file, none is awarded, and no supplier is on a purchase order.

Explanation: A printed capsule is not the composite frame, and a dev-board gateway is not DRONE-09. CTQ26 stays unresolved. The worksheet total is not demonstrated.

Result (Y/N/NA): Y

Status: Recorded — deviation rule written

BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total $740.00; BMT-DRONE-BOM-001 Rev C1 DRONE-03 and DRONE-07; CTQ26 unresolved; 2026-10-24

Owner: Jordan Vale

Next action: Simulation and specialist review first; separate a printed capsule and a dev-board gateway from DRONE-01 and DRONE-09 on the unit card; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The deviation rule is recorded as intent and is not accepted.

Item ID: PROTOTYPE-10

Question: What equipment and calibration are required before a run counts?

Answer / assumption: A force gauge for 5 N, 20 N, and 2 N, checked the day of a run. An uncalibrated gauge voids that run. Video on the guarded fixture. An HIL harness for estimator disagreement, link loss, and rejection of an unsigned plan. A temperature method for the pack and the dock, owned by a battery specialist who is not appointed. No outdoor range, no open-air GNSS test, and no live Remote ID broadcast are in this plan. An unlabeled simulation cannot be filed as a measured pass. The rig slice of the unfunded drone allowance is $100,000.00. It is not released. Drone rig costs are not paid from the Basic $5,000.00 prototype line.

Explanation: An uncalibrated gauge voids the run. The harness sits in the unreleased rig slice. No outdoor range is in the plan.

Result (Y/N/NA): N

Status: Open — instruments not released

BMT-DRONE-TEST-MATRIX-001 Rev C1 equipment lines; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 rig slice $100,000.00 unreleased; 2026-10-24

Owner: Jordan Vale

Next action: Simulation and specialist review first; list the gauge, fixture video, and HIL harness inside the unreleased $100,000.00 rig slice; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No instrument spend is released.

Item ID: PROTOTYPE-11

Question: What cost is authorized for this prototype, and what is excluded?

Answer / assumption: The drone allowance on the BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 is $250,000.00: rig $100,000.00, testing and welfare $75,000.00, engineering and market $50,000.00, and reserve $25,000.00. It uses the same four-way pattern as the Hotel allowance. It is not secured. It is outside the $80,000. The BMT-COMPANY-TEMPLATE-CASH-FLOW-001 Rev C1 includes no drone development spend. Hold price $1,499.00. Year-1 commercial units are 0. Sensitivities of 50 / 100 / 200 units are cost math, not a sales forecast. Sixteen research rows name controlled rural-site partners. None has an agreement, and none authorized a flight. Alex Meadow has not been asked to release drone funds. Paid this year is Not applicable — no transaction in this planning record. Debt is Not applicable — no transaction in this planning record. The allowance stops before the $60,000.00 DRONE-01 capsule allowance and before any flight. That capsule allowance is outside the $250,000.00 ceiling.

Explanation: The $250,000.00 allowance is unfunded and outside the owner contribution. Paid this year is Not applicable — no transaction in this planning record. The allowance stops before the $60,000.00 DRONE-01 capsule allowance and before any flight. That capsule allowance is outside the $250,000.00 ceiling.

Result (Y/N/NA): N

Status: Blocked — allowance unfunded

BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 unfunded lines, Drone $250,000.00 split $100,000.00 / $75,000.00 / $50,000.00 / $25,000.00; 2026-10-24

Owner: Alex Meadow

Next action: Simulation and specialist review first; leave the $250,000.00 allowance unreleased; do not ask for drone consent ahead of Basic evidence; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No allowance is consented.

Item ID: PROTOTYPE-12

Question: What are the stop rules, and who may restart?

Answer / assumption: Jordan Vale stops a bench or fixture run on unexpected motion, heat, a second docking approach, estimator disagreement, an interlock defeat, water at a pack, or a method change. A rotor case restarts only with Jordan Vale and the specialist, in writing. Nobody authorizes outdoor flight on this sheet. B04, due 2027-03-01, is a no-flight gate and is open. Link loss must end in the predefined safe state (CTQ22), not in a further phone instruction. Live animals are not loaded. Children are not subjects. A document check for T24 or T26 does not become a flight by renaming it.

Explanation: Nobody on this sheet may authorize outdoor flight. A rotor case restarts only with Jordan Vale and a specialist, in writing.

Result (Y/N/NA): N

Status: Open — no-flight rule not on the cards

BMT-DRONE-DFMEA-001 Rev C1 DF22, first-pass DF25 630, projected DF25-M 350, DF30; residual total 8464; risk B04 due 2027-03-01 open; 2026-10-24

Owner: Jordan Vale

Next action: Simulation and specialist review first; attach the no-flight rule and the B04 date to every aircraft method card; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The stop card is not on the method cards.

Item ID: PROTOTYPE-13

Question: How will measured, simulated, and predicted results be separated?

Answer / assumption: Measured means a gauge value, a count, a photo, or a fixture log on DRONE-X1-001 through DRONE-X1-010 or on the guarded stand. Simulated means the HIL harness output and is labeled simulated. It may inform T20, T21, T22, T28, and T29. It cannot close T01 and it cannot authorize T25. Predicted means the DFMEA projected RPN and is not evidence. A later flight log would be a different evidence class and is not planned. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 stays Not run for T01 through T34 until a measured row, or a clearly labeled simulated row, is filed. A simulated row is not a pass of an outdoor test.

Explanation: Harness output is simulated. It may inform selected rows. It cannot close T01 or authorize T25. A projected RPN is not evidence.

Result (Y/N/NA): Y

Status: Recorded — evidence classes defined

BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1 projected RPN column; 2026-10-24; no measured row

Owner: Jordan Vale

Next action: Simulation and specialist review first; require a simulated label on every HIL harness output before it can be filed; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Measured, simulated, and predicted are separated.

Item ID: PROTOTYPE-14

Question: Who owns a failed proof, and what retest is required?

Answer / assumption: Jordan Vale owns a failed drone characteristic. A capsule fail repeats the full count on 10 units after the DFMEA action or a written alternative. A fail of T18, T23, or T30 blocks any later proposal to leave the fixture, including a proposal that is only a simulation. A fail of T25 or T26 is closed only by a written regulatory answer, not by a code change. Alex Meadow does not close a technical fail by releasing more of the $250,000.00. No retest is scheduled, because no first test is scheduled.

Explanation: A capsule fail repeats the full count on 10 units. A fail of T25 or T26 closes only with a written regulatory answer.

Result (Y/N/NA): Y

Status: Recorded — fail owner named

BMT-DRONE-DFMEA-001 Rev C1 DF18 RPN 400 and DF01 action; owner Jordan Vale; 2026-10-24; not implemented or tested

Owner: Jordan Vale

Next action: Simulation and specialist review first; name Jordan Vale on the fail-and-retest line for T01 through T34; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The fail owner is named.

Item ID: PROTOTYPE-15

Question: Which gate can this packet support, and which gates stay shut?

Answer / assumption: This packet does not open a gate on 2026-10-24. If the allowance were later released, the capsule bench could support a private G1 recommendation only. Aircraft items stay at simulation and specialist review. G2 user/welfare, G3 freeze, G4 pilot, and G5 launch stay shut. A consumer launch is outside the project. Commercial units are 0. The sheet target is 2027-06-15, which is after B04 (2027-03-01) and after A03 (2026-12-15). Missing those earlier gates does not move work into a flight. The company decision being prepared is the Basic feasibility gate, not a drone flight approval.

Explanation: This packet does not open a gate on 2026-10-24. G2 through G5 stay shut, and aircraft work stays behind B04 and A03.

Result (Y/N/NA): Y

Status: Recorded — later gates stay shut

BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1 PROJECT-06 and PROJECT-08; B04 2027-03-01; A03 2026-12-15; sheet target 2027-06-15

Owner: Jordan Vale

Next action: Simulation and specialist review first; keep G2 through G5 shut and keep aircraft work behind B04 and A03; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. G2 through G5 stay shut.

Item ID: PROTOTYPE-16

Question: What must be in the evidence package before the review date?

Answer / assumption: Before any reviewer is named: this sheet; BMT-DRONE-BOM-001 Rev C1; the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total of $740.00 labeled as a worksheet; DFMEA C1 for DF01 through DF60 (60 data rows); BMT-DRONE-TEST-MATRIX-001 Rev C1 for T01 through T34; method cards marked fixture, HIL, or document check; BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 still Not run; a line that the $250,000.00 allowance is unreleased; the status of B04; the status of A03; and a statement that no FCC ID and no Remote ID approval are claimed. If any item is missing, the answer is not ready. A Casey Holt read is planned for 2026-11-01 and has not been held as of 2026-10-28. That planned read is not a close while any package item is missing.

Explanation: The package names the unreleased allowance, B04, A03, and the absence of a Remote ID approval. The package is not complete.

Result (Y/N/NA): N

Status: Open — package incomplete

BMT-DRONE-CHECK-SHEET-PROTOTYPE-001 Rev C1; ; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; 2026-10-24; planned read 2026-11-01 not held, package not closed; $250,000.00 unreleased; no

Owner: Jordan Vale

Next action: Simulation and specialist review first; assemble the package with the unreleased-allowance line and do not close the package on the planned 2026-11-01 read, which has not been held; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The package list is incomplete.

Item ID: PROTOTYPE-17

Question: What user and misuse conditions is the prototype required to represent?

Answer / assumption: PROJECT-01 names controlled-site rural research partners. Sixteen research rows are on file, including seven Grade B interviews, and there is no homeowner panel. No partner authorized a flight and no site is approved, so the prototype does not represent their land. It represents an indoor bench and a guarded fixture. Misuse in scope: a hand near a rotor guard, an unauthorized command, link loss, a failed dock alignment, and a second approach to the wall. Out of scope until separate approvals exist: outdoor launch, wind at or above 3 m/s, rain, a live payload, a field release, unattended flight, and any household surveillance use (CTQ29). No export launch. No child use.

Explanation: No flight site is approved, so the prototype represents a bench and a guarded fixture. Seven Grade B interviews are filed. Household surveillance use is out of scope.

Result (Y/N/NA): Y

Status: Recorded — user boundary written

BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1 PROJECT-01 and PROJECT-02; CTQ29; 2026-10-24; 16 research rows on file; no flight site approved

Owner: Jordan Vale

Next action: Simulation and specialist review first; state the bench and guarded-fixture boundary; name no approved flight site because none is approved; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The user boundary is recorded as intent and is not accepted.

Item ID: PROTOTYPE-18

Question: What would make the prototype effort stop rather than revise?

Answer / assumption: Do not start drone hardware while Basic latch and ventilation evidence is missing and while B04 and A03 are open. If a consent were ever written, stop rather than revise inside the allowance when the capsule door fails after one redesign, or when the guarded fixture cannot show two retention paths (CTQ18, DF18 RPN 400). Do not spend the $25,000.00 reserve to buy a flight. A stop proposal goes to Alex Meadow. No stop is declared on 2026-10-24, because the work has not started. The next action remains simulation and specialist review, at 2027-06-15, and that action is not itself a flight.

Explanation: Drone hardware does not start while Basic evidence is missing and B04 and A03 are open. The reserve is not a flight purchase.

Result (Y/N/NA): Y

Status: Recorded — stop rule written, not declared

BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1, Drone outside the Basic cap and the BMT-COMPANY-TEMPLATE-CASH-FLOW-001 Rev C1; 2026-10-24; no stop declared

Owner: Alex Meadow

Next action: Simulation and specialist review first; write the one-redesign and no-flight-purchase stop rule for Alex Meadow; declare no stop; target 2027-06-15

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. The stop rule is not a declared stop.

Drone Trap — What the Prototype Needs to Prove — supporting detail

Drone Trap — Which question is this prototype answering?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-01

Question. Which question is this prototype answering?

Evidence to record. Appearance, usability, fit, mechanism, strength, life, process or customer acceptance; list what it cannot demonstrate.

Answer / assumption. First question is the capsule door, on the bench. CTQ01 / R01 / DF01, RPN 210: the door stays latched through 100 dry cycles on each of 10 capsule surrogates, then a 5 N pull (BMT-DRONE-TEST-MATRIX-001 Rev C1 T01). Flight, release in the air, and outdoor operation are not this question. Drone Trap C1 is a research concept: a wall-side base, an aircraft that carries the capsule to a field, a release, and a return. The commercial forecast is 0 units. There is no consumer launch. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 records T01 through T34 as Not run. The $250,000.00 allowance is not secured. Risk B04 (Jordan Vale, due 2027-03-01) keeps flight closed.

Result (Y/N/NA). Y

Explanation. The capsule door is the bench question. Outdoor flight is not this prototype. Risk B04 is open. DF01 RPN 210 is proposed.

Status. Recorded — first question named, untested

Evidence / exact revision / URL and date. BMT-DRONE-TEST-MATRIX-001 Rev C1 T01; BMT-DRONE-DFMEA-001 Rev C1 DF01 RPN 210; risk B04 due 2027-03-01 open; 2026-10-24; Not run

Owner. Jordan Vale

Next action. Simulation and specialist review first; write the bench T01 method card for the capsule door; do not schedule a flight; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. First question is recorded as C1 intent and is not accepted.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEST-MATRIX-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1

Drone Trap — What is the exact configuration?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-02

Question. What is the exact configuration?

Evidence to record. Model/drawing/BOM revision, materials, deviations from production, build method and sample identifiers.

Answer / assumption. Configuration is Drone Trap C1, research only. BMT-DRONE-BOM-001 Rev C1: DRONE-01 ventilated capsule, DRONE-02 wall deployment carriage, DRONE-03 guarded frame, DRONE-04 motors, ESC, and prop set (qty 4), DRONE-05 navigation (GNSS, IMU, and vision), DRONE-06 redundant payload latch, DRONE-07 flight battery, DRONE-08 dock charger and interlocks, DRONE-09 radio and local gateway, DRONE-10 assembly and HIL calibration, DRONE-11 shipping crate and manual. Reserved IDs DRONE-X1-001 through DRONE-X1-010 for capsules and one HIL harness. No aircraft leaves a guarded fixture under this plan. Nothing is built. BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total is $740.00 against the $1,499.00 hold price. That total is a worksheet, not a quote. DRONE-01 on BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 is $213.00 after low-volume amortization, not the $13.00 piece price. Thirty-three dated bids are on file and none is awarded: Fictional Sample Works (Perry Voss, 2026-10-02, valid through 2026-12-31), Fictional Meadow Prototype Shop (Willa Marsh, 2026-10-06, valid through 2026-12-05), and Fictional Northline Molding (Eden Crowe, 2026-10-09, valid through 2027-01-07), parts DRONE-01 through DRONE-11. The C1 bill is 21 rows, assembly DRONE-C1-ASSY plus DRONE-01 through DRONE-18. Labor is DRONE-10. Tooling is DRONE-18. Commercial units authorized remain 0. No FCC ID is invented. Remote ID applicability (CTQ26 / T26) is unresolved and blocks any outdoor flight.

Result (Y/N/NA). Y

Explanation. DRONE-01 through DRONE-11 are the quoted subset. The C1 bill runs through DRONE-18. No free-flight article is in this revision. No FCC identification is claimed.

Status. Recorded — configuration listed, none built

Evidence / exact revision / URL and date. BMT-DRONE-BOM-001 Rev C1, 21 rows, DRONE-C1-ASSY and DRONE-01 through DRONE-18; quoted subset DRONE-01 through DRONE-11; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total $740.00; DRONE-01 amortized $213.00; 2026-10-24; 33 unawarded bids on file; no purchase order; no FCC ID

Owner. Jordan Vale

Next action. Simulation and specialist review first; hold ID templates DRONE-X1-001 through DRONE-X1-010 and the HIL harness; record that no free-flight article is in C1; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Configuration matches the C1 bill.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-BOM-001 Rev C1; BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1

Drone Trap — How will we judge success before testing?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-03

Question. How will we judge success before testing?

Evidence to record. Requirement ID, method, numerical/observable acceptance criterion, environment, equipment, calibration where needed and planned sample size rationale.

Answer / assumption. Criteria are copied from BMT-DRONE-TEST-MATRIX-001 Rev C1 and are review pending. Capsule bench, n=10 where the matrix says so: T01 door, 100 dry cycles and 5 N (CTQ01, DF01 RPN 210); T02 two vent paths open in a bedding surrogate (CTQ02, DF02 RPN 252); T03 fingers 30 mm clear, 10 adults, unloaded (CTQ03, DF03 RPN 192); T04 tool-free open and no visible fluorescent soil, n=10, not a biological claim (CTQ04, DF04 RPN 240); T05 bait captive at 20 N (CTQ05, DF05 RPN 162); T06 occupancy visible without opening, interval unset (CTQ06, DF06 RPN 432); T07 baffle not back-driven at 2 N, three-compartment target (CTQ07, DF07 RPN 280). Capsule electronics on the isolated rig: T08 zero false-empty in 100 dusted placements (CTQ08, DF08 RPN 360); T09 local indicator works offline and the app marks offline within 5 minutes (CTQ09, DF09 RPN 432); T10 physical-button provisioning and 50 denied unauthorized attempts (CTQ10, DF10 RPN 320); T11 capture indication survives power loss at each update phase (CTQ11, DF11 RPN 288); T12 no wet charge, proposed 45 C cutoff, specialist only (CTQ12, DF12 RPN 320, severity 10); T13 power inhibited when the cassette is unseated (CTQ13, DF13 RPN 315); T14 no precise location, 30-day retention, deletion path (CTQ14, DF14 RPN 280); T15 no module choice until grant and host rules are reviewed, no FCC ID invented (CTQ15, DF15 RPN 360); T16 capacity not rated (CTQ16, DF16 RPN 360). Aircraft items are simulation or a guarded fixture only, not outdoor flights: T17 carriage stops before contact, supervised enable (CTQ17, DF17 RPN 360); T18 two retention paths, release only after ground-contact confirmation (CTQ18, DF18 RPN 400, severity 10); T19 no rotor spin until the guarded zone is verified (CTQ19, DF19 RPN 350, severity 10); T20 geofence independent of the planner, abort on estimator disagreement (CTQ20, DF20 RPN 450); T21 modeled return reserve at least 40% (CTQ21, DF21 RPN 480); T22 phone is not safety-critical, safe state on link loss (CTQ22, DF22 RPN 450); T23 release only when stationary, motors stopped, on a validated surface (CTQ23, DF23 RPN 320); T24 no field release until species rules, landowner permission, and a welfare note exist (CTQ24, DF24 RPN 567); T25 no unattended outdoor launch (CTQ25, DF25 RPN 630); T26 Remote ID applicability resolved before any outdoor flight (CTQ26, DF26 RPN 360); T27 no charge after a failed dock alignment (CTQ27, DF27 RPN 400); T28 research envelope only, dry and wind below 3 m/s, not a cleared flight limit (CTQ28, DF28 RPN 480); T29 signed mission plan, no remote bypass of the safety envelope (CTQ29, DF29 RPN 450); T30 one failed docking attempt, then a designated safe land, no repeated wall approach (CTQ30, DF30 RPN 480). The highest first-pass RPN is DF25 at 630. The highest projected line is DF25-M at 350, severity 10. Residual RPN total is 8464. The 80% review line is 6771.2. Accepted residual is 0. All of these limits are proposed. T31 through T34 and CTQ31 through CTQ34 are on the same matrix, unapproved, and Not run. DFMEA C1 is DF01 through DF60 (60 data rows). Radio-module hold is process step P18. Test T15 is not process step P15.

Result (Y/N/NA). N

Explanation. T01 through T34 limits are targets. Aircraft rows are fixture, harness, or document checks. First-pass DF25 is 630. Projected DF25-M is 350. The residual total is 8464.

Status. Open — acceptance lines not initialed

Evidence / exact revision / URL and date. BMT-DRONE-TEST-MATRIX-001 Rev C1 T01-T34; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01-CTQ34; BMT-DRONE-DFMEA-001 Rev C1 DF01-DF60; first-pass DF25 630; projected DF25-M 350; residual total 8464; 2026-10-24

Owner. Jordan Vale

Next action. Simulation and specialist review first; copy T01 through T34 acceptance lines and mark aircraft rows as fixture, HIL, or document check; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Limits are copied and not initialed.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEST-MATRIX-001 Rev C1; BMT-DRONE-CRITICAL-QUALITY-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1

Drone Trap — Is the test safe and representative?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-04

Question. Is the test safe and representative?

Evidence to record. Foreseeable hazards, setup limits, operator competence, exposure safeguards, realistic users/conditions and specialist or lab involvement where needed.

Answer / assumption. Surrogates first. No live-animal protocol is approved, and no outdoor-flight protocol is approved. B04 stays open: no flight. If the allowance were ever released, rotor work would start in a guarded ground fixture with guards fitted (CTQ19, DF19 RPN 350). Payload release is not demonstrated in the air (CTQ18 RPN 400 and CTQ23). Carriage trials are unloaded and supervised (CTQ17). Dock and pack faults go to a battery specialist. Jordan Vale does not run destructive pack tests (CTQ12 and CTQ27, both severity 10). Phone loss is a safe-state case, not a cue to continue (CTQ22, DF22 RPN 450). The weather line is a research envelope, not permission to launch (CTQ28). Stop on unexpected motion, heat, estimator disagreement, an interlock defeat, or a second docking approach (CTQ30). Nia Calder (Calder Sample Risk) has not been contacted. Aviation, lithium, and autonomous-flight questions on the BMT-COMPANY-INSURANCE-REQUEST-001 are open. The $2,000,000.00 liability figure is an illustration, not a binder, and drone flight sits outside that illustration.

Result (Y/N/NA). N

Explanation. Heat, unexpected motion, link loss, and a second docking approach are written stops. B04 stays open. Nia Calder has not been contacted.

Status. Open — safeguards not signed

Evidence / exact revision / URL and date. BMT-DRONE-DFMEA-001 Rev C1 DF19, DF18, DF22, DF25, DF30; BMT-COMPANY-TEMPLATE-BUSINESS-RISKS-001 risk B04; BMT-COMPANY-INSURANCE-REQUEST-001, Nia Calder not contacted; 2026-10-24

Owner. Jordan Vale

Next action. Simulation and specialist review first; write fixture stop rules for heat, motion, link loss, and a second docking approach; leave B04 open; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Safeguards are written and not signed.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-DFMEA-001 Rev C1; BMT-COMPANY-TEMPLATE-BUSINESS-RISKS-001 Rev C1; BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1

Drone Trap — What happened, including failures?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-05

Question. What happened, including failures?

Evidence to record. Raw measurements, units, photos, observations, anomalies and deviation from method. Separate measured from simulated and predicted performance.

Answer / assumption. No tests have been run. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 records T01 through T34 as Not run. No cycle counts, no HIL logs, no temperature readings, and no fixture video. Projected RPNs are predictions. The highest projected line is DF25-M at 350. First-pass DF25 is 630 and is not a result. Residual RPN total is 8464. Simulation output, if it is produced later, is labeled simulated and is not a flight result. No failure has been observed, and no pass has been recorded.

Result (Y/N/NA). N

Explanation. T01 through T34 are Not run. There is no harness log and no fixture video to file as a result.

Status. Blocked — no run on file

Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 T01-T34 Not run; 2026-10-24; no HIL log and no fixture video

Owner. Jordan Vale

Next action. Simulation and specialist review first; leave BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 T01 through T34 at Not run; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No raw sheet is on file.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1

Drone Trap — What can we conclude, and what remains unproven?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-06

Question. What can we conclude, and what remains unproven?

Evidence to record. Verification: meets specified requirements. Validation: serves intended users/use. State sample and prototype limits, owner of failures, required changes and retest before a release claim.

Result (Y/N/NA). N

Explanation. No flight, welfare, Remote ID, or sales conclusion is available. Year-1 commercial units authorized: 0.

Status. Blocked — evidence not established

Evidence / exact revision / URL and date. BMT-DRONE-MARKET-CHECK-001 Rev C1 and BMT-DRONE-TEMPLATE-MARKET-EVIDENCE-001 Rev C1, 16 research rows, 7 Grade B, 5 pay-line cards at Not applicable — no transaction in this planning record; BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1 PROJECT-03 commercial forecast 0 and PROJECT-06; 2026-10-24; no gate sign-off; no flight authorized

Owner. Jordan Vale

Next action. Simulation and specialist review first; record that no flight, welfare, Remote ID, or sales conclusion is available; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No performance conclusion is available.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1

Drone Trap — Which characteristics must this prototype prove, and which are deferred?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-07

Question. Which characteristics must this prototype prove, and which are deferred?

Evidence to record. List each CTQ, requirement, DFMEA ID and test ID in this build; state the deferred characteristics and the gate they move to.

Answer / assumption. The written plan covers CTQ01 through CTQ34 and T01 through T34. CTQ01 through CTQ30 is a short index of that plan. The build scope, if a consent ever exists, is narrower than the plan: capsule surrogates for T01 through T07; the HIL harness for T08 through T16 and for simulated T20, T21, T22, T25, T26, T28, and T29; a guarded ground fixture for T17, T18, T19, T23, T27, and T30. T24 and T25 are document checks, not flights. Outdoor launch, a live animal, a field release, a consumer sale, and production tooling stay deferred. They sit outside the allowance line that stops before tooling. Production control-plan rows CP01 through CP34 do not replace these tests. Radio-module hold is process step P18, not P15. Test T15 does not rename that step. Action A03 (regulatory scope, Jordan Vale, due 2026-12-15) is open and blocks treating the aircraft as cleared.

Result (Y/N/NA). Y

Explanation. Outdoor launch, a live payload, and a field release stay off the build list. Action A03 is open.

Status. Recorded — outdoor work deferred

Evidence / exact revision / URL and date. BMT-DRONE-CRITICAL-QUALITY-001 Rev C1 CTQ01-CTQ34; action A03 due 2026-12-15 open; 2026-10-24; outdoor flight deferred

Owner. Jordan Vale

Next action. Simulation and specialist review first; keep outdoor launch, live payload, and field release off the build list; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The in-scope list is recorded as intent and is not accepted.

Not-applicable reason. Outdoor launch, a live payload, and a field release are deferred. The bench list applies.

Source guidance URLs. BMT-DRONE-CRITICAL-QUALITY-001 Rev C1

Drone Trap — What is the sample size rationale and how is each unit identified?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-08

Question. What is the sample size rationale and how is each unit identified?

Evidence to record. Unit IDs, count, why that count is enough for this gate, reuse order across tests, and the rule for a damaged unit.

Answer / assumption. DRONE-X1-001 through DRONE-X1-010 cover capsule mechanics. Order on those units is cycles, then the bait pull, then wash, and only on units that still meet the latch line. n=10 is the CTQ01 screening count, not a reliability sample and not a fleet sample. The HIL harness is one rig, not ten aircraft. T08 is 100 placements. T10 is 50 denied attempts. T21 is a model case at the proposed 40% return reserve, not a flown discharge. There is no flight-article sample in C1. A damaged capsule is retired, not quietly replaced. No ID is cut until Alex Meadow consents, and this sheet does not ask for that consent ahead of Basic evidence.

Result (Y/N/NA). N

Explanation. n=10 capsules is the screen. DRONE-X1-001 through DRONE-X1-010 are not issued. There is no flight-article sample.

Status. Open — serials reserved, none issued

Evidence / exact revision / URL and date. BMT-DRONE-TEST-MATRIX-001 Rev C1 sample notes; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; 2026-10-24; no flight article; IDs not issued

Owner. Jordan Vale

Next action. Simulation and specialist review first; document n=10 capsules and one HIL rig; issue no hardware ID ahead of Basic evidence; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Serials are reserved and not issued.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEST-MATRIX-001 Rev C1; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1

Drone Trap — What build method differs from the intended production part?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-09

Question. What build method differs from the intended production part?

Evidence to record. Production-intent process and material versus the prototype process; which dimensions must still match C1; which claims a non-production build cannot support.

Answer / assumption. Production intent includes a composite guarded frame (DRONE-03) and a protected lithium pack (DRONE-07). The C1 prototype plan does not build a free-flight article. A bench capsule may be printed if vent, door, and latch geometry match C1. A dev-board gateway is not DRONE-09. Motors may be fitted only in the guarded fixture. A bench spin is not an aircraft acceptance. The $740.00 BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 total and the $213.00 amortized capsule are not demonstrated by a printed part. Remote ID hardware is not selected. CTQ26 stays unresolved. Thirty-three dated bids are on file, none is awarded, and no supplier is on a purchase order.

Result (Y/N/NA). Y

Explanation. A printed capsule is not the composite frame, and a dev-board gateway is not DRONE-09. CTQ26 stays unresolved. The worksheet total is not demonstrated.

Status. Recorded — deviation rule written

Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total $740.00; BMT-DRONE-BOM-001 Rev C1 DRONE-03 and DRONE-07; CTQ26 unresolved; 2026-10-24

Owner. Jordan Vale

Next action. Simulation and specialist review first; separate a printed capsule and a dev-board gateway from DRONE-01 and DRONE-09 on the unit card; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The deviation rule is recorded as intent and is not accepted.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1; BMT-DRONE-BOM-001 Rev C1

Drone Trap — What equipment and calibration are required before a run counts?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-10

Question. What equipment and calibration are required before a run counts?

Evidence to record. Instrument, check method, what voids a run, and whether the cost sits inside the feasibility cap.

Answer / assumption. A force gauge for 5 N, 20 N, and 2 N, checked the day of a run. An uncalibrated gauge voids that run. Video on the guarded fixture. An HIL harness for estimator disagreement, link loss, and rejection of an unsigned plan. A temperature method for the pack and the dock, owned by a battery specialist who is not appointed. No outdoor range, no open-air GNSS test, and no live Remote ID broadcast are in this plan. An unlabeled simulation cannot be filed as a measured pass. The rig slice of the unfunded drone allowance is $100,000.00. It is not released. Drone rig costs are not paid from the Basic $5,000.00 prototype line.

Result (Y/N/NA). N

Explanation. An uncalibrated gauge voids the run. The harness sits in the unreleased rig slice. No outdoor range is in the plan.

Status. Open — instruments not released

Evidence / exact revision / URL and date. BMT-DRONE-TEST-MATRIX-001 Rev C1 equipment lines; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1 rig slice $100,000.00 unreleased; 2026-10-24

Owner. Jordan Vale

Next action. Simulation and specialist review first; list the gauge, fixture video, and HIL harness inside the unreleased $100,000.00 rig slice; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No instrument spend is released.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEST-MATRIX-001 Rev C1; BMT-DRONE-FUNDING-WORKSHEET-001 Rev C1

Drone Trap — What cost is authorized for this prototype, and what is excluded?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-11

Question. What cost is authorized for this prototype, and what is excluded?

Evidence to record. Cap amount, named budget owner, included spend, excluded spend, candidate cost-sheet total, target price, and confirmation that no supplier is on order.

Result (Y/N/NA). N

Status. Blocked — allowance unfunded

Owner. Alex Meadow

Next action. Simulation and specialist review first; leave the $250,000.00 allowance unreleased; do not ask for drone consent ahead of Basic evidence; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No allowance is consented.

Not-applicable reason. Applicable

Source guidance URLs. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1

Drone Trap — What are the stop rules, and who may restart?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-12

Question. What are the stop rules, and who may restart?

Evidence to record. Stop conditions, who stops, who may restart, and the subjects or environments that are not allowed.

Answer / assumption. Jordan Vale stops a bench or fixture run on unexpected motion, heat, a second docking approach, estimator disagreement, an interlock defeat, water at a pack, or a method change. A rotor case restarts only with Jordan Vale and the specialist, in writing. Nobody authorizes outdoor flight on this sheet. B04, due 2027-03-01, is a no-flight gate and is open. Link loss must end in the predefined safe state (CTQ22), not in a further phone instruction. Live animals are not loaded. Children are not subjects. A document check for T24 or T26 does not become a flight by renaming it.

Result (Y/N/NA). N

Explanation. Nobody on this sheet may authorize outdoor flight. A rotor case restarts only with Jordan Vale and a specialist, in writing.

Status. Open — no-flight rule not on the cards

Evidence / exact revision / URL and date. BMT-DRONE-DFMEA-001 Rev C1 DF22, first-pass DF25 630, projected DF25-M 350, DF30; residual total 8464; risk B04 due 2027-03-01 open; 2026-10-24

Owner. Jordan Vale

Next action. Simulation and specialist review first; attach the no-flight rule and the B04 date to every aircraft method card; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The stop card is not on the method cards.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-DFMEA-001 Rev C1

Drone Trap — How will measured, simulated, and predicted results be separated?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-13

Question. How will measured, simulated, and predicted results be separated?

Evidence to record. Definition of measured, simulated, and predicted; where each is filed; which file stays Not run until a measurement exists.

Answer / assumption. Measured means a gauge value, a count, a photo, or a fixture log on DRONE-X1-001 through DRONE-X1-010 or on the guarded stand. Simulated means the HIL harness output and is labeled simulated. It may inform T20, T21, T22, T28, and T29. It cannot close T01 and it cannot authorize T25. Predicted means the DFMEA projected RPN and is not evidence. A later flight log would be a different evidence class and is not planned. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 stays Not run for T01 through T34 until a measured row, or a clearly labeled simulated row, is filed. A simulated row is not a pass of an outdoor test.

Result (Y/N/NA). Y

Explanation. Harness output is simulated. It may inform selected rows. It cannot close T01 or authorize T25. A projected RPN is not evidence.

Status. Recorded — evidence classes defined

Evidence / exact revision / URL and date. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1 projected RPN column; 2026-10-24; no measured row

Owner. Jordan Vale

Next action. Simulation and specialist review first; require a simulated label on every HIL harness output before it can be filed; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Measured, simulated, and predicted are separated.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1; BMT-DRONE-DFMEA-001 Rev C1

Drone Trap — Who owns a failed proof, and what retest is required?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-14

Question. Who owns a failed proof, and what retest is required?

Evidence to record. Named owner of a fail, the redesign action tied to the DFMEA, the retest sample, and who may not close the fail.

Answer / assumption. Jordan Vale owns a failed drone characteristic. A capsule fail repeats the full count on 10 units after the DFMEA action or a written alternative. A fail of T18, T23, or T30 blocks any later proposal to leave the fixture, including a proposal that is only a simulation. A fail of T25 or T26 is closed only by a written regulatory answer, not by a code change. Alex Meadow does not close a technical fail by releasing more of the $250,000.00. No retest is scheduled, because no first test is scheduled.

Result (Y/N/NA). Y

Explanation. A capsule fail repeats the full count on 10 units. A fail of T25 or T26 closes only with a written regulatory answer.

Status. Recorded — fail owner named

Evidence / exact revision / URL and date. BMT-DRONE-DFMEA-001 Rev C1 DF18 RPN 400 and DF01 action; owner Jordan Vale; 2026-10-24; not implemented or tested

Owner. Jordan Vale

Next action. Simulation and specialist review first; name Jordan Vale on the fail-and-retest line for T01 through T34; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The fail owner is named.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-DFMEA-001 Rev C1

Drone Trap — Which gate can this packet support, and which gates stay shut?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-15

Question. Which gate can this packet support, and which gates stay shut?

Evidence to record. Gate this packet can support, gates that stay shut, and the decision this sheet does not authorize.

Answer / assumption. This packet does not open a gate on 2026-10-24. If the allowance were later released, the capsule bench could support a private G1 recommendation only. Aircraft items stay at simulation and specialist review. G2 user/welfare, G3 freeze, G4 pilot, and G5 launch stay shut. A consumer launch is outside the project. Commercial units are 0. The sheet target is 2027-06-15, which is after B04 (2027-03-01) and after A03 (2026-12-15). Missing those earlier gates does not move work into a flight. The company decision being prepared is the Basic feasibility gate, not a drone flight approval.

Result (Y/N/NA). Y

Explanation. This packet does not open a gate on 2026-10-24. G2 through G5 stay shut, and aircraft work stays behind B04 and A03.

Status. Recorded — later gates stay shut

Evidence / exact revision / URL and date. BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1 PROJECT-06 and PROJECT-08; B04 2027-03-01; A03 2026-12-15; sheet target 2027-06-15

Owner. Jordan Vale

Next action. Simulation and specialist review first; keep G2 through G5 shut and keep aircraft work behind B04 and A03; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. G2 through G5 stay shut.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1

Drone Trap — What must be in the evidence package before the review date?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-16

Question. What must be in the evidence package before the review date?

Evidence to record. Required files, revision, and the rule when one file is missing. Reviewer name stays blank until the package exists.

Answer / assumption. Before any reviewer is named: this sheet; BMT-DRONE-BOM-001 Rev C1; the BMT-DRONE-TEMPLATE-COST-SHEET-001 Rev C1 running total of $740.00 labeled as a worksheet; DFMEA C1 for DF01 through DF60 (60 data rows); BMT-DRONE-TEST-MATRIX-001 Rev C1 for T01 through T34; method cards marked fixture, HIL, or document check; BMT-DRONE-TEMPLATE-TEST-RESULTS-001 Rev C1 still Not run; a line that the $250,000.00 allowance is unreleased; the status of B04; the status of A03; and a statement that no FCC ID and no Remote ID approval are claimed. If any item is missing, the answer is not ready. A Casey Holt read is planned for 2026-11-01 and has not been held as of 2026-10-28. That planned read is not a close while any package item is missing.

Result (Y/N/NA). N

Explanation. The package names the unreleased allowance, B04, A03, and the absence of a Remote ID approval. The package is not complete.

Status. Open — package incomplete

Evidence / exact revision / URL and date. BMT-DRONE-CHECK-SHEET-PROTOTYPE-001 Rev C1; ; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1; 2026-10-24; planned read 2026-11-01 not held, package not closed; $250,000.00 unreleased; no Remote ID approval claimed

Owner. Jordan Vale

Next action. Simulation and specialist review first; assemble the package with the unreleased-allowance line and do not close the package on the planned 2026-11-01 read, which has not been held; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The package list is incomplete.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-CHECK-SHEET-PROTOTYPE-001 Rev C1; BMT-DRONE-CONCEPT-DRAWING-001 Rev C1

Drone Trap — What user and misuse conditions is the prototype required to represent?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-17

Question. What user and misuse conditions is the prototype required to represent?

Evidence to record. User, place, and misuse the build must represent, and the uses named out of scope in the project sheet.

Answer / assumption. PROJECT-01 names controlled-site rural research partners. Sixteen research rows are on file, including seven Grade B interviews, and there is no homeowner panel. No partner authorized a flight and no site is approved, so the prototype does not represent their land. It represents an indoor bench and a guarded fixture. Misuse in scope: a hand near a rotor guard, an unauthorized command, link loss, a failed dock alignment, and a second approach to the wall. Out of scope until separate approvals exist: outdoor launch, wind at or above 3 m/s, rain, a live payload, a field release, unattended flight, and any household surveillance use (CTQ29). No export launch. No child use.

Result (Y/N/NA). Y

Explanation. No flight site is approved, so the prototype represents a bench and a guarded fixture. Seven Grade B interviews are filed. Household surveillance use is out of scope.

Status. Recorded — user boundary written

Evidence / exact revision / URL and date. BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1 PROJECT-01 and PROJECT-02; CTQ29; 2026-10-24; 16 research rows on file; no flight site approved

Owner. Jordan Vale

Next action. Simulation and specialist review first; state the bench and guarded-fixture boundary; name no approved flight site because none is approved; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The user boundary is recorded as intent and is not accepted.

Not-applicable reason. Applicable

Source guidance URLs. BMT-DRONE-CHECK-SHEET-PROJECT-001 Rev C1

Drone Trap — What would make the prototype effort stop rather than revise?

Project. Drone Trap

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. What the Prototype Needs to Prove

Lead. Jordan Vale

Item ID. PROTOTYPE-18

Question. What would make the prototype effort stop rather than revise?

Evidence to record. Conditions that stop the allowance rather than fund another revision, who receives the stop proposal, and the statement that no stop is declared on the preparation date.

Answer / assumption. Do not start drone hardware while Basic latch and ventilation evidence is missing and while B04 and A03 are open. If a consent were ever written, stop rather than revise inside the allowance when the capsule door fails after one redesign, or when the guarded fixture cannot show two retention paths (CTQ18, DF18 RPN 400). Do not spend the $25,000.00 reserve to buy a flight. A stop proposal goes to Alex Meadow. No stop is declared on 2026-10-24, because the work has not started. The next action remains simulation and specialist review, at 2027-06-15, and that action is not itself a flight.

Result (Y/N/NA). Y

Explanation. Drone hardware does not start while Basic evidence is missing and B04 and A03 are open. The reserve is not a flight purchase.

Status. Recorded — stop rule written, not declared

Evidence / exact revision / URL and date. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1, Drone outside the Basic cap and the BMT-COMPANY-TEMPLATE-CASH-FLOW-001 Rev C1; 2026-10-24; no stop declared

Owner. Alex Meadow

Next action. Simulation and specialist review first; write the one-redesign and no-flight-purchase stop rule for Alex Meadow; declare no stop; target 2027-06-15

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. The stop rule is not a declared stop.

Not-applicable reason. Applicable

Source guidance URLs. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-COMPANY-TEMPLATE-CASH-FLOW-001 Rev C1

Document administration

Scope. DRONE-C1 capsule on the bench and in simulation. No flight article. Tests T01 through T30 on BMT-DRONE-TEST-MATRIX-001 are Not run. Bridge serials DRONE-X1-001 through DRONE-X1-010, none built. The $250,000.00 research allowance is unfunded and stops before the $60,000.00 capsule tool. Year-1 commercial units authorized: 0. Checklist BMT-DRONE-CHECK-SHEET-PROTOTYPE-001, Rev C1.

Team. Alex Meadow, packet owner and no-flight gate; Jordan Vale, flight research; Sam Reed, mechanical interface; Robin Keel, animal-welfare reviewer

Approved by. review pending. Alex Meadow, Planning draft C1, unsigned. The $250,000.00 research allowance is not drawn. Year-1 commercial units authorized: 0.

Preparation: Jordan Vale, scenario attribution, 2026-10-24. Signature: unsigned. Review: pending; no reviewer signature or date. Approval: withheld; no approver signature or date.

Prepared byDate
Reviewed byDate
Approved byDate