The Better Mouse Trap Co. / sample paperwork

Mouse Hotel — Design for manufacture and assembly

Mouse HotelRevision C12026-10-24Planning draft18 entries
Mouse Hotel — Design for manufacture and assemblyBMT-HOTEL-CHECK-SHEET-DFM-001 · Rev C1
Company
The Better Mouse Trap Co.
Project / product line
Hotel trap
Document
Mouse Hotel — Design for manufacture and assembly
Document no.
BMT-HOTEL-CHECK-SHEET-DFM-001
Revision
C1
Status
Planning draft
Start date
2026-10-24
Revision date
2026-10-24
Prepared by / owner
Jordan Vale, Hotel electronics, with Sam Reed on the shell
Checklist ID
BMT-HOTEL-CHECK-SHEET-DFM-001 Rev C1
Scope
HOTEL-C1 three-chamber shell HOTEL-01 and the electronics cassette.
Reviewer
Casey Holt
Review date
Planned 2026-11-01. Pending as of 2026-10-28. The review has not been held.
Team
Alex Meadow, packet owner; Jordan Vale, Hotel electronics; Sam Reed, mechanical reference; Robin Keel, animal-welfare reviewer
Approved by
review pending. Alex Meadow, Planning draft C1, unsigned. The $60,000.00 Hotel allowance is not drawn.
Mouse Hotel — Design for Manufacture and Assembly
Item / review questionAnswer / findingResult / statusEvidenceResponsibility / action

Item ID: DFM-01

Question: What performance and safety requirements drive the design?

Answer / assumption: R01–R16 and CTQ01–CTQ20 drive the C1 geometry. Shared trap features stay: latch (DF01, RPN 210), raised vents (DF02, RPN 252), 30 mm slider clearance (DF03, RPN 192), tool-free wash (DF04, RPN 240), captive bait (DF05, RPN 162), and the occupancy window (DF06, RPN 432). Hotel adds three chambers and one-way baffles (DF07, RPN 280, HOTEL-02 qty 3), a sensor window (DF08, RPN 360), a local indicator that does not depend on Wi-Fi (DF09, RPN 432), a protected pack (DF12, RPN 320), a dry electronics cassette (DF13, RPN 315), an antenna keep-out (DF15, RPN 360), and separate compartments when full (DF16, RPN 360). There is no propeller.

Explanation: Connected alerts do not replace the local window or the manual check. A tool or PCB layout that deletes any of those rows is a requirement change. CTQ01–CTQ16 is a short index. The C1 set is CTQ01–CTQ20, DFMEA DF01–DF32, and control plan CP01–CP20. Tests T01–T20 are unrun. Process steps are P01–P21, and the radio-integration hold is P18. DF01–DF16 is not the full DFMEA. RPNs are proposed and untested. Residual RPN on the ranking sheet is 3567, the 80% review line is 2853.6, and accepted residual is 0.

Result (Y/N/NA): Y

Status: Recorded — requirements listed, untested

BMT-HOTEL-SPEC-SHEET-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1 DF01–DF32; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01–CTQ20; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01–CP20;

Owner: Jordan Vale

Next action: Trace CTQ01–CTQ20 onto the unreleased three-chamber sketch and the cassette layout. Alex Meadow has not frozen geometry. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. CTQ list is the C1 intent to check. Geometry is not frozen.

Item ID: DFM-02

Question: Does the process fit material, geometry and volume?

Answer / assumption: The molded part is the HOTEL-01 three-chamber PP shell and clear lid, one cavity assumed. Buy items are HOTEL-02 baffles and latches at qty 3, HOTEL-03 sensor array, HOTEL-04 radio cassette, HOTEL-05 protected battery, HOTEL-06 external charger, and HOTEL-08 carton. HOTEL-07 assembly and flashing is in-house labor. The BMT-HOTEL-TEMPLATE-COST-SHEET-001 uses 600 units a year for 3 years. A printed bridge shell may support unloaded HOTEL-X1 checks. It is not the production process. The aircraft-style parts on the Drone set are out of this sheet. BMT-HOTEL-BOM-001 is 19 rows: HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16. Labor is HOTEL-07 and tooling is HOTEL-16. The buy list above is not the whole bill.

Explanation: Six hundred a year is a manufacturing sensitivity, not demand evidence. Twenty-four dated bids are on file for HOTEL-01 through HOTEL-08: Fictional Sample Works (Perry Voss, 2026-09-19, valid through 2026-12-18), Fictional Meadow Prototype Shop (Willa Marsh, 2026-09-23, valid through 2026-11-22), and Fictional Northline Molding (Eden Crowe, 2026-09-30, valid through 2026-12-29). None is awarded and none is a purchase order. Press tonnage, cycle time, and a PCB fab limit are not on those bids. The $30,000.00 HOTEL-01 / HOTEL-16 allowance is not one of the bids.

Result (Y/N/NA): N

Status: Open — bids on file, process limits blank

BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 unawarded bids dated 2026-09-19, 2026-09-23, and

Owner: Jordan Vale

Next action: State, against the 24 unawarded bids, whether 600 a year fits one cavity and whether the cassette is a purchased module. Leave BMT-HOTEL-RFQ-PACKAGE-001 unissued. Do not award a tool. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Volume case is a sensitivity. No process is accepted.

Item ID: DFM-03

Question: Are features realistic for the chosen process?

Answer / assumption: No shell feature is approved. Open molding points are lid draft on a three-chamber part, nominal wall, three baffle shutoffs, vent steel proud of the floor, and latch undercuts. Open purchased-part points are the cassette seal gland, the sensor window, and the antenna keep-out around HOTEL-04. A bridge print will not show lid warp, sink, or seal compression.

Explanation: The electronics are purchased modules, not molded shapes, but the shell has to locate them. Supplier limits for both the mold and the module outline are blank.

Result (Y/N/NA): N

Status: Open — supplier limits blank

BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; DF02, DF07, DF13, and DF15 still proposed; BMT-HOTEL-RFQ-PACKAGE-001 capability questions unanswered; no moldflow. 2026-10-24.

Owner: Jordan Vale

Next action: Split the feature checklist into shell steel and cassette interface, and leave every limit blank. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Feature list is open. No supplier limit is adopted.

Item ID: DFM-04

Question: Are tolerances functional and inspectable?

Answer / assumption: Untoleranced stacks that are already functional are the latch (CTQ01, 100 dry cycles and 5 N), the 30 mm finger line (CTQ03), baffle anti-backdrive (CTQ07), sensor-window position (CTQ08), cassette seal compression (CTQ13), and antenna keep-out (CTQ15). Each stack has to include PP shrink or warp of the lid, wash aging, seal set, and latch wear. No drawing datum and no gauge repeatability study exist.

Explanation: Cosmetic lid flatness is not the latch datum and not the sensor datum. Tight tolerances that do not serve those CTQs will be marked reference.

Result (Y/N/NA): N

Status: Open — no dimensioned drawing

BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01, CTQ03, CTQ07, CTQ08, CTQ13, CTQ15; no dimensioned drawing. 2026-10-24.

Owner: Jordan Vale

Next action: Balloon only those CTQ dimensions on the unreleased C1 sketch and name the datum for the lid. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No datum is released. Tight tolerances are not purchased.

Item ID: DFM-05

Question: Can the parts be assembled consistently?

Answer / assumption: Assembly intent is a keyed hinge, a one-way baffle in each chamber, a cassette that clocks one way, and a keyed battery connector. BMT-HOTEL-BOM-001 Rev C1 has 19 rows: assembly HOTEL-C1-ASSY plus HOTEL-01 through HOTEL-16, including labor HOTEL-07, tooling HOTEL-16, and the roll-up. It is not an eight-line bill. HOTEL-02 quantity is 3, so a chamber-specific baffle must not fit a neighboring chamber unless the three stops are truly identical. That choice is not made. HOTEL-07 flashing can leave DF11 (corrupt update, RPN 288) if power is lost; the fixture does not yet block a single-bank part. No build has been timed.

Explanation: Process steps P01–P21 and PFMEA rows PF01–PF60 are the planned controls. Latch assembly is P05. Radio-integration hold is P18. Configuration error is still the written PFMEA cause, and no wrong-way trial exists.

Result (Y/N/NA): N

Status: Open — no build trial

BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; BMT-HOTEL-PROCESS-FLOW-001 Rev C1 P01–P21, latch at P05, radio-integration hold at P18;

Owner: Jordan Vale

Next action: Decide whether the three baffles are identical or keyed, and add that characteristic to PF07 before any X1 build. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Assembly intent is not a witnessed build.

Item ID: DFM-06

Question: Can material or supplier substitutions change performance?

Answer / assumption: Do not substitute the PP lid grade, the baffle material on HOTEL-02, an unprotected cell for HOTEL-05, an uncertified adapter for HOTEL-06, or a different radio module or antenna on HOTEL-04, unless the affected CTQ is regressed. An antenna or layout change reopens DF15 at a proposed RPN of 360. Hotel has no propeller and no flight battery. Clear lid stock and opaque body stock are different callouts.

Explanation: Designer references stay separate from purchasing sources. No approved-alternate list exists, and Fictional Sample Works has not been asked for one.

Result (Y/N/NA): N

Status: Open — no approved alternate

BMT-HOTEL-BOM-001 Rev C1 materials; DF12, DF13, and DF15; BMT-HOTEL-TEMPLATE-COST-SHEET-001 make or buy; no alternate list. 2026-10-24.

Owner: Jordan Vale

Next action: Write allowed-material and allowed-module lines for HOTEL-01, HOTEL-04, HOTEL-05, and HOTEL-06. Mark every other part not allowed. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Substitution ban is recorded. No alternate is approved.

Item ID: DFM-07

Question: Are the files complete and at one revision?

Answer / assumption: BMT-HOTEL-BOM-001, BMT-HOTEL-TEMPLATE-COST-SHEET-001, BMT-HOTEL-DFMEA-001, BMT-HOTEL-CONTROL-PLAN-001, R01–R16, and this sheet are all marked C1. There is no released STEP solid, no dimensioned drawing, no cassette interface drawing, and no ballooned CTQ print. Quantity cases are 600 a year, 50% of that rate, and 200% of that rate, as sensitivity only. A render is not the release package.

Explanation: Design freeze is not claimed. Nineteen BOM rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16, share one revision label, and the manufacturing file set is missing.

Result (Y/N/NA): N

Status: Blocked — no released CAD

BMT-HOTEL-SPEC-SHEET-001 Rev C1; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; no CAD revision. 2026-10-24.

Owner: Jordan Vale

Next action: List the missing C1 files, including the cassette keep-out drawing, and keep the pack unreleased. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Revision label is C1. Manufacturing files are missing.

Item ID: DFM-08

Question: What did the manufacturer flag, and who accepted changes?

Answer / assumption: No manufacturer has flagged a change, and nobody has accepted one. Fictional Sample Works is not selected. Twenty-four dated bids are on file and unawarded; they are not a DFM markup and not a purchase order. BMT-HOTEL-RFQ-PACKAGE-001 is not issued, and its capability questions are still unanswered. A later markup needs a date, the CTQ touched, tool or piece-price impact, and acceptance by Alex Meadow. None of that exists.

Explanation: The HOTEL-01 / HOTEL-16 shell figure of $30,000.00 is an invented tooling allowance, not a quote, and it sits outside the $60,000.00 ceiling. The Hotel allowance of $60,000.00 is not secured, is not drawn, and stops before production tooling.

Result (Y/N/NA): NA

Status: No DFM markup on file

BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 unawarded bids, no purchase order; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 not issued, capability questions unanswered;

Owner: Jordan Vale

Next action: Leave BMT-HOTEL-RFQ-PACKAGE-001 unissued until DFM-03 and DFM-09 are filled in. No disposition to log until a DFM markup exists. Do not award a tool. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. No supplier markup exists. Nothing is accepted.

Item ID: DFM-09

Question: Does the tooling spend fit the funded allowance and the volume used to amortize it?

Answer / assumption: HOTEL-01 allowance is $30,000.00 for one cavity, amortized at $16.67 per unit across 600 units a year for 3 years, inside a packed cost of $58.67. At 50% of stated volume, that amortization doubles to $33.33. The BMT-HOTEL-FUNDING-WORKSHEET-001 names $60,000.00 (prototype and rig $24,000.00, specialist testing and welfare $18,000.00, engineering and market $12,000.00, reserve $6,000.00) and stops before production tooling. That allowance is not committed, and the worksheet says future Hotel funding is not secured. The $30,000.00 HOTEL-01 / HOTEL-16 shell allowance sits outside that ceiling and is not one of the 24 dated bids. Side actions are not in the $30,000.00. Wholesale contribution at the base case is -$3.17.

Explanation: A negative wholesale contribution is not a reason to cut a cheaper, weaker tool. Alex Meadow has not authorized any tool draw, and the feasibility path stops before steel.

Result (Y/N/NA): N

Status: Open — tool not funded

BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 HOTEL-01 tooling $30,000.00, amortization $16.67, annual units 600, years 3; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-03 packed

Owner: Alex Meadow

Next action: Jordan Vale attaches the 50% volume amortization so Alex Meadow can refuse the $30,000.00 tool at the feasibility gate. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Tool allowance fails the stop-before-tooling rule.

Item ID: DFM-10

Question: Will gate, knit line, sink, or ejector marks hit a functional or inspection surface?

Answer / assumption: The clear lid is both the CTQ06 viewing surface and the path over the sensor windows. It must not carry a gate, a heavy knit line, or an ejector pin. Baffle pivots (CTQ07) and the latch land (CTQ01) must not sit on a knit line. Chamber ribs that sink will close the raised vents (CTQ02) and the between-chamber air path (CTQ16). No gate side and no moldflow exist.

Explanation: Gating into the lid to fill three chambers would be refused under CTQ06 and CTQ08. That refusal is on this sheet before a bidder offers it.

Result (Y/N/NA): N

Status: Open — no moldflow

CTQ01, CTQ02, CTQ06, CTQ08, CTQ16; HOTEL-01 PP clear lid; no moldflow. 2026-10-24.

Owner: Jordan Vale

Next action: Mark gate, ejector, and knit-line keep-out on the lid, the three sensor windows, and the latch land. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Keep-out is intent only. No moldflow is on file.

Item ID: DFM-11

Question: Are wall, draft, rib, and boss sizes inside a named supplier limit?

Answer / assumption: Not known. No nominal wall, draft, rib ratio, or boss size is released for the three-chamber lid. Warp of that lid is the obvious process risk and has no number on it. The 24 dated bids do not state a wall, draft, rib, or boss limit. The purchased cassette outline is also without a supplier keep-out drawing.

Explanation: These fields may stay blank through the feasibility gate. They may not be filled with a generic wall thickness.

Result (Y/N/NA): N

Status: Open — no supplier limit

BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; RFQ unanswered; no supplier limit for the lid or the HOTEL-04 outline. 2026-10-24.

Owner: Jordan Vale

Next action: Add blank shell-limit lines and a blank cassette-outline line to the unissued BMT-HOTEL-RFQ-PACKAGE-001. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Wall, draft, rib, and boss stay blank.

Item ID: DFM-12

Question: Which undercuts, side actions, inserts, or steel-safe changes are still open?

Answer / assumption: Likely slides or shutoffs: three one-way baffle stops, the latch undercut, the raised vents, and the cassette seal groove. Preferred steel-safe direction is extra metal on the latch land and on the anti-backdrive stop. None of those side actions are priced inside the $30,000.00 allowance, so the allowance is incomplete if slides are required. Deleting the anti-backdrive stop to avoid a slide reopens DF07 at a proposed RPN of 280.

Explanation: Combining the three chambers into one tub to cheapen the tool reopens DF16 at a proposed RPN of 360. That change is not accepted.

Result (Y/N/NA): N

Status: Open — slides not priced

DF07 RPN 280 and DF16 RPN 360; BMT-HOTEL-TEMPLATE-COST-SHEET-001 has no side-action line under the $30,000.00 allowance. 2026-10-24.

Owner: Jordan Vale

Next action: Price each slide as an open add to the allowance, or redesign it out without dropping CTQ07 or CTQ16. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Slides are unnamed. Steel-safe direction is not priced.

Item ID: DFM-13

Question: Can orientation errors and loose hardware be prevented in assembly?

Answer / assumption: The cassette clocks one way. The battery connector is keyed. The three baffles are either identical or chamber-keyed; that is undecided. HOTEL-04 orientation sets the antenna keep-out for DF15. The HOTEL-07 flash fixture has to reject a single-bank part because DF11 scores a proposed RPN of 288 on a power-loss update. No loose screw is intended. No wrong-way trial has been run.

Explanation: PFMEA causes are still written as assembly or configuration error. A fixture that only checks that a connector is occupied will miss a reversed baffle.

Result (Y/N/NA): N

Status: Open — no wrong-way trial

BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1; DF11 RPN 288; DF15 RPN 360; no assembly trial. 2026-10-24.

Owner: Jordan Vale

Next action: Add baffle orientation and flash-fixture interlock as characteristics on PF07 and PF11. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Poka-yoke is not tried. Occurrence is unchanged.

Item ID: DFM-14

Question: Can the product be washed, serviced, and reassembled without damaging a sealed or energized part?

Answer / assumption: The shell still has to open without tools for CTQ04. The electronics cassette has to be out of the wet zone, or positively sealed and labeled, before any wash (DF13, proposed RPN 315, shock or overheating if water reaches the board). HOTEL-05 stays with the dry cassette (DF12, proposed RPN 320). HOTEL-06 is an external adapter and is not washed. No ingress rating is claimed. No splash trial has been run.

Explanation: A sealed-in board that cannot be removed, or a user instruction that says to rinse the whole unit, fails DF13. Biological cleaning is not claimed.

Result (Y/N/NA): N

Status: Open — wash not run

DF04, DF12, DF13; CTQ04 and CTQ13; CP rows planned; no ingress test and no IP rating. 2026-10-24.

Owner: Jordan Vale

Next action: Show the cassette coming out before the wash step on the unreleased service sketch, and keep the IP claim off the drawing. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Service path is intent. No wash record exists.

Item ID: DFM-15

Question: Can every CTQ be measured where the process creates it?

Answer / assumption: Shell CTQs use the same methods as the trap family where the function is shared: 100 dry cycles and a 5 N pull (CP01), vent occlusion (CP02), 30 mm finger line (CP03), soil check (CP04), bait pull (CP05), and window visibility (CP06). Later rows need access before the next join: baffle stop before the lid is fixed (CP07), sensor window before any label (CP08), seal gland before the cassette is inserted (CP13), antenna keep-out at cassette install (CP15). The control plan is CP01–CP20. CTQ01–CTQ20 and tests T01–T20 are unrun. Radio-integration hold is process step P18, not P15. Latch assembly is P05. BMT-HOTEL-CONTROL-PLAN-001 calls for 10 prototype units from HOTEL-X1-001 through HOTEL-X1-010 and one fault-injection rig. No gauge and no result exist.

Explanation: Flashing labor on HOTEL-07 does not measure a mold characteristic. A software rig does not close CP01.

Result (Y/N/NA): N

Status: Open — gauge not named

BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01–CP20; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01–CTQ20; BMT-HOTEL-TEST-PLAN-001 Rev C1 T01–T20, unrun; BMT-HOTEL-PROCESS-FLOW-001 Rev C1

Owner: Jordan Vale

Next action: Name the gauge or method on each open CP row, and mark which characteristics disappear after the lid or cassette is installed. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Control-plan methods are unnamed. No result is filed.

Item ID: DFM-16

Question: Do packaging, labels, and secondary operations change the geometry or the cost?

Answer / assumption: HOTEL-08 carton and tray is $2.00 and is already inside the $58.67 packed cost. HOTEL-07 flashing labor is $3.00 and is also inside that pack; it is not a molding secondary. No drop test, barcode, or ultrasonic weld is specified. The lot mark has to survive washing and must not cover a sensor window, the occupancy indicator, or the offline indicator. Shipping-damage testing remains planned.

Explanation: A weld or a full-wrap label added later would change both geometry and the packed cost. Neither is in BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1.

Result (Y/N/NA): N

Status: Open — no packaging trial

BMT-HOTEL-BOM-001 Rev C1 HOTEL-07 and HOTEL-08; BMT-HOTEL-TEMPLATE-COST-SHEET-001 unit costs $3.00 and $2.00; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-03 and

Owner: Jordan Vale

Next action: Reserve a non-optical face for a wash-durable lot mark and hold secondary operations at the two lines already costed. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Pack cost is inside the piece. No pack trial exists.

Item ID: DFM-17

Question: Which high-RPN design features must stay if a supplier offers to simplify the tool or the bill of materials?

Answer / assumption: Freeze, before any simplification offer: latch and keyed pin (DF01, RPN 210), raised vents (DF02, RPN 252), external slider (DF03, RPN 192), removable wash path (DF04, RPN 240), captive bait (DF05, RPN 162), clear window (DF06, RPN 432), one-way baffles (DF07, RPN 280), independent sensor checks (DF08, RPN 360), local indicator not only Wi-Fi (DF09, RPN 432), protected pack (DF12, RPN 320), dry cassette (DF13, RPN 315), frozen antenna layout (DF15, RPN 360), and separate compartments (DF16, RPN 360). Highest proposed RPNs in this set are 432 on DF06 and DF09. Actions are not implemented or tested.

Explanation: Combining chambers, burying the board where it will be washed, or dropping the local indicator to save a tool feature is a welfare or shock change. Jordan Vale refuses those cuts. Alex Meadow has not been asked to accept them.

Result (Y/N/NA): Y

Status: Recorded — freeze list not signed

BMT-HOTEL-DFMEA-001 Rev C1 freeze-list rows through DF16, inside the DF01–DF32 index, proposed RPNs as cited; actions open. 2026-10-24.

Owner: Jordan Vale

Next action: Attach this freeze list to the unissued BMT-HOTEL-RFQ-PACKAGE-001 as characteristics the bidder may not remove. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Freeze list is the refusal rule. Actions stay open.

Item ID: DFM-18

Question: What will the bridge build prove, and what must not be inferred from it?

Answer / assumption: HOTEL-X1-001 through HOTEL-X1-010 bridge units may be printed or machined to check unloaded slider reach, a surrogate baffle probe, and window visibility. They will not represent lid warp, seal compression after washing, antenna layout, battery fault behavior, or firmware rollback (DF11, proposed RPN 288). A bridge pass is not a first article and is not permission to spend the $30,000.00 tool. No unit has been built.

Explanation: BMT-HOTEL-CONTROL-PLAN-001 limits 10 prototype units to no reliability inference, and it separates one fault-injection rig from the mechanical checks. This row keeps that split.

Result (Y/N/NA): Y

Status: Recorded — bridge limit not signed

BMT-HOTEL-CONTROL-PLAN-001 Rev C1, 10 prototype units and 1 fault-injection rig, no results; planned IDs HOTEL-X1-001 through HOTEL-X1-010. 2026-10-24.

Owner: Jordan Vale

Next action: Write the bridge-versus-production column on BMT-HOTEL-TEST-PLAN-001 before any X1 unit is made. Target 2027-02-15.

Reviewer / review date: Pending. Casey Holt, planned 2026-11-01. Bridge limit is recorded. It is not a first article.

Mouse Hotel — Design for Manufacture and Assembly — supporting detail

Mouse Hotel — What performance and safety requirements drive the design?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-01

Question. What performance and safety requirements drive the design?

Evidence to record. Intended use, loads, life, environment, interfaces, applicable market rules and acceptance criteria with sources.

Answer / assumption. R01–R16 and CTQ01–CTQ20 drive the C1 geometry. Shared trap features stay: latch (DF01, RPN 210), raised vents (DF02, RPN 252), 30 mm slider clearance (DF03, RPN 192), tool-free wash (DF04, RPN 240), captive bait (DF05, RPN 162), and the occupancy window (DF06, RPN 432). Hotel adds three chambers and one-way baffles (DF07, RPN 280, HOTEL-02 qty 3), a sensor window (DF08, RPN 360), a local indicator that does not depend on Wi-Fi (DF09, RPN 432), a protected pack (DF12, RPN 320), a dry electronics cassette (DF13, RPN 315), an antenna keep-out (DF15, RPN 360), and separate compartments when full (DF16, RPN 360). There is no propeller.

Result (Y/N/NA). Y

Explanation. Connected alerts do not replace the local window or the manual check. A tool or PCB layout that deletes any of those rows is a requirement change. CTQ01–CTQ16 is a short index. The C1 set is CTQ01–CTQ20, DFMEA DF01–DF32, and control plan CP01–CP20. Tests T01–T20 are unrun. Process steps are P01–P21, and the radio-integration hold is P18. DF01–DF16 is not the full DFMEA. RPNs are proposed and untested. Residual RPN on the ranking sheet is 3567, the 80% review line is 2853.6, and accepted residual is 0.

Status. Recorded — requirements listed, untested

Evidence / exact revision / URL and date. BMT-HOTEL-SPEC-SHEET-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1 DF01–DF32; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01–CTQ20; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01–CP20; BMT-HOTEL-TEST-PLAN-001 Rev C1 T01–T20, unrun; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; no external evidence. Internal read 2026-10-24.

Owner. Jordan Vale

Next action. Trace CTQ01–CTQ20 onto the unreleased three-chamber sketch and the cassette layout. Alex Meadow has not frozen geometry. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. CTQ list is the C1 intent to check. Geometry is not frozen.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-SPEC-SHEET-001 Rev C1

Mouse Hotel — Does the process fit material, geometry and volume?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-02

Question. Does the process fit material, geometry and volume?

Evidence to record. Compare machining, molding, casting, sheet metal, additive or other processes against quantity, finish, lead time, tooling and total cost; identify process-specific risks.

Answer / assumption. The molded part is the HOTEL-01 three-chamber PP shell and clear lid, one cavity assumed. Buy items are HOTEL-02 baffles and latches at qty 3, HOTEL-03 sensor array, HOTEL-04 radio cassette, HOTEL-05 protected battery, HOTEL-06 external charger, and HOTEL-08 carton. HOTEL-07 assembly and flashing is in-house labor. The BMT-HOTEL-TEMPLATE-COST-SHEET-001 uses 600 units a year for 3 years. A printed bridge shell may support unloaded HOTEL-X1 checks. It is not the production process. The aircraft-style parts on the Drone set are out of this sheet. BMT-HOTEL-BOM-001 is 19 rows: HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16. Labor is HOTEL-07 and tooling is HOTEL-16. The buy list above is not the whole bill.

Result (Y/N/NA). N

Explanation. Six hundred a year is a manufacturing sensitivity, not demand evidence. Twenty-four dated bids are on file for HOTEL-01 through HOTEL-08: Fictional Sample Works (Perry Voss, 2026-09-19, valid through 2026-12-18), Fictional Meadow Prototype Shop (Willa Marsh, 2026-09-23, valid through 2026-11-22), and Fictional Northline Molding (Eden Crowe, 2026-09-30, valid through 2026-12-29). None is awarded and none is a purchase order. Press tonnage, cycle time, and a PCB fab limit are not on those bids. The $30,000.00 HOTEL-01 / HOTEL-16 allowance is not one of the bids.

Status. Open — bids on file, process limits blank

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 unawarded bids dated 2026-09-19, 2026-09-23, and 2026-09-30; BMT-HOTEL-TEMPLATE-COST-SHEET-001 annual units 600 and years 3; no tonnage, cycle, or PCB fab limit on the bids. 2026-10-24.

Owner. Jordan Vale

Next action. State, against the 24 unawarded bids, whether 600 a year fits one cavity and whether the cassette is a purchased module. Leave BMT-HOTEL-RFQ-PACKAGE-001 unissued. Do not award a tool. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Volume case is a sensitivity. No process is accepted.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1

Mouse Hotel — Are features realistic for the chosen process?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-03

Question. Are features realistic for the chosen process?

Evidence to record. For molding: walls, draft, ribs/bosses, undercuts, shrinkage and ejection. For machining: tool access, deep pockets and corner radii. For sheet metal: bends, radii and hole spacing. Obtain the actual supplier’s limits; no universal wall/draft number.

Answer / assumption. No shell feature is approved. Open molding points are lid draft on a three-chamber part, nominal wall, three baffle shutoffs, vent steel proud of the floor, and latch undercuts. Open purchased-part points are the cassette seal gland, the sensor window, and the antenna keep-out around HOTEL-04. A bridge print will not show lid warp, sink, or seal compression.

Result (Y/N/NA). N

Explanation. The electronics are purchased modules, not molded shapes, but the shell has to locate them. Supplier limits for both the mold and the module outline are blank.

Status. Open — supplier limits blank

Evidence / exact revision / URL and date. BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; DF02, DF07, DF13, and DF15 still proposed; BMT-HOTEL-RFQ-PACKAGE-001 capability questions unanswered; no moldflow. 2026-10-24.

Owner. Jordan Vale

Next action. Split the feature checklist into shell steel and cassette interface, and leave every limit blank. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Feature list is open. No supplier limit is adopted.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1

Mouse Hotel — Are tolerances functional and inspectable?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-04

Question. Are tolerances functional and inspectable?

Evidence to record. Critical dimensions, datums, fits, tolerance stack-ups, finishes and inspection methods. Avoid needless tight tolerances; specify those required for function or safety.

Answer / assumption. Untoleranced stacks that are already functional are the latch (CTQ01, 100 dry cycles and 5 N), the 30 mm finger line (CTQ03), baffle anti-backdrive (CTQ07), sensor-window position (CTQ08), cassette seal compression (CTQ13), and antenna keep-out (CTQ15). Each stack has to include PP shrink or warp of the lid, wash aging, seal set, and latch wear. No drawing datum and no gauge repeatability study exist.

Result (Y/N/NA). N

Explanation. Cosmetic lid flatness is not the latch datum and not the sensor datum. Tight tolerances that do not serve those CTQs will be marked reference.

Status. Open — no dimensioned drawing

Evidence / exact revision / URL and date. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01, CTQ03, CTQ07, CTQ08, CTQ13, CTQ15; no dimensioned drawing. 2026-10-24.

Owner. Jordan Vale

Next action. Balloon only those CTQ dimensions on the unreleased C1 sketch and name the datum for the lid. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No datum is released. Tight tolerances are not purchased.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1

Mouse Hotel — Can the parts be assembled consistently?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-05

Question. Can the parts be assembled consistently?

Evidence to record. Reduce unnecessary parts/fasteners, use standard components, access tools, orient and locate parts, prevent wrong assembly, protect wires/seals and test service/disassembly.

Answer / assumption. Assembly intent is a keyed hinge, a one-way baffle in each chamber, a cassette that clocks one way, and a keyed battery connector. BMT-HOTEL-BOM-001 Rev C1 has 19 rows: assembly HOTEL-C1-ASSY plus HOTEL-01 through HOTEL-16, including labor HOTEL-07, tooling HOTEL-16, and the roll-up. It is not an eight-line bill. HOTEL-02 quantity is 3, so a chamber-specific baffle must not fit a neighboring chamber unless the three stops are truly identical. That choice is not made. HOTEL-07 flashing can leave DF11 (corrupt update, RPN 288) if power is lost; the fixture does not yet block a single-bank part. No build has been timed.

Result (Y/N/NA). N

Explanation. Process steps P01–P21 and PFMEA rows PF01–PF60 are the planned controls. Latch assembly is P05. Radio-integration hold is P18. Configuration error is still the written PFMEA cause, and no wrong-way trial exists.

Status. Open — no build trial

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; BMT-HOTEL-PROCESS-FLOW-001 Rev C1 P01–P21, latch at P05, radio-integration hold at P18; BMT-HOTEL-PFMEA-001 Rev C1 PF01–PF60; DF11 RPN 288; no build record. 2026-10-24.

Owner. Jordan Vale

Next action. Decide whether the three baffles are identical or keyed, and add that characteristic to PF07 before any X1 build. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Assembly intent is not a witnessed build.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-PROCESS-FLOW-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1

Mouse Hotel — Can material or supplier substitutions change performance?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-06

Question. Can material or supplier substitutions change performance?

Evidence to record. Material/grade, flame/contact/corrosion requirements, finishes, standard hardware and qualified equivalents. Preserve designer catalog references separately from purchasing sources.

Answer / assumption. Do not substitute the PP lid grade, the baffle material on HOTEL-02, an unprotected cell for HOTEL-05, an uncertified adapter for HOTEL-06, or a different radio module or antenna on HOTEL-04, unless the affected CTQ is regressed. An antenna or layout change reopens DF15 at a proposed RPN of 360. Hotel has no propeller and no flight battery. Clear lid stock and opaque body stock are different callouts.

Result (Y/N/NA). N

Explanation. Designer references stay separate from purchasing sources. No approved-alternate list exists, and Fictional Sample Works has not been asked for one.

Status. Open — no approved alternate

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 materials; DF12, DF13, and DF15; BMT-HOTEL-TEMPLATE-COST-SHEET-001 make or buy; no alternate list. 2026-10-24.

Owner. Jordan Vale

Next action. Write allowed-material and allowed-module lines for HOTEL-01, HOTEL-04, HOTEL-05, and HOTEL-06. Mark every other part not allowed. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Substitution ban is recorded. No alternate is approved.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1

Mouse Hotel — Are the files complete and at one revision?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-07

Question. Are the files complete and at one revision?

Evidence to record. Bill of materials, STEP solid and dimensioned drawings where applicable, materials/finishes, critical characteristics, assembly notes, quantity breaks and inspection/acceptance requirements. A render is not a release package.

Answer / assumption. BMT-HOTEL-BOM-001, BMT-HOTEL-TEMPLATE-COST-SHEET-001, BMT-HOTEL-DFMEA-001, BMT-HOTEL-CONTROL-PLAN-001, R01–R16, and this sheet are all marked C1. There is no released STEP solid, no dimensioned drawing, no cassette interface drawing, and no ballooned CTQ print. Quantity cases are 600 a year, 50% of that rate, and 200% of that rate, as sensitivity only. A render is not the release package.

Result (Y/N/NA). N

Explanation. Design freeze is not claimed. Nineteen BOM rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16, share one revision label, and the manufacturing file set is missing.

Status. Blocked — no released CAD

Evidence / exact revision / URL and date. BMT-HOTEL-SPEC-SHEET-001 Rev C1; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1, 19 rows, HOTEL-C1-ASSY and HOTEL-01 through HOTEL-16; no CAD revision. 2026-10-24.

Owner. Jordan Vale

Next action. List the missing C1 files, including the cassette keep-out drawing, and keep the pack unreleased. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Revision label is C1. Manufacturing files are missing.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1

Mouse Hotel — What did the manufacturer flag, and who accepted changes?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-08

Question. What did the manufacturer flag, and who accepted changes?

Evidence to record. Dated supplier DFM feedback, disposition, affected requirements, cost/tooling impact, owner and verification/retest. Obtain review before releasing revised work.

Answer / assumption. No manufacturer has flagged a change, and nobody has accepted one. Fictional Sample Works is not selected. Twenty-four dated bids are on file and unawarded; they are not a DFM markup and not a purchase order. BMT-HOTEL-RFQ-PACKAGE-001 is not issued, and its capability questions are still unanswered. A later markup needs a date, the CTQ touched, tool or piece-price impact, and acceptance by Alex Meadow. None of that exists.

Result (Y/N/NA). NA

Explanation. The HOTEL-01 / HOTEL-16 shell figure of $30,000.00 is an invented tooling allowance, not a quote, and it sits outside the $60,000.00 ceiling. The Hotel allowance of $60,000.00 is not secured, is not drawn, and stops before production tooling.

Status. No DFM markup on file

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 unawarded bids, no purchase order; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 not issued, capability questions unanswered; BMT-HOTEL-TEMPLATE-COST-SHEET-001 tooling $30,000.00, invented allowance not a bid; BMT-HOTEL-FUNDING-WORKSHEET-001 $60,000.00 not funded or committed, future Hotel funding not secured. 2026-10-24.

Owner. Jordan Vale

Next action. Leave BMT-HOTEL-RFQ-PACKAGE-001 unissued until DFM-03 and DFM-09 are filled in. No disposition to log until a DFM markup exists. Do not award a tool. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. No supplier markup exists. Nothing is accepted.

Not-applicable reason. Price bids are on file and unawarded. No DFM markup has been accepted, so there is no markup to disposition.

Source guidance URLs. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Mouse Hotel — Does the tooling spend fit the funded allowance and the volume used to amortize it?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-09

Question. Does the tooling spend fit the funded allowance and the volume used to amortize it?

Evidence to record. Tool identity, cavity count, ownership, allowance versus any quote, funded cash and the stop-before-tooling rule, annual units and years used for amortization, packed unit cost at the stated volume and at half volume, and who may authorize a purchase.

Answer / assumption. HOTEL-01 allowance is $30,000.00 for one cavity, amortized at $16.67 per unit across 600 units a year for 3 years, inside a packed cost of $58.67. At 50% of stated volume, that amortization doubles to $33.33. The BMT-HOTEL-FUNDING-WORKSHEET-001 names $60,000.00 (prototype and rig $24,000.00, specialist testing and welfare $18,000.00, engineering and market $12,000.00, reserve $6,000.00) and stops before production tooling. That allowance is not committed, and the worksheet says future Hotel funding is not secured. The $30,000.00 HOTEL-01 / HOTEL-16 shell allowance sits outside that ceiling and is not one of the 24 dated bids. Side actions are not in the $30,000.00. Wholesale contribution at the base case is -$3.17.

Result (Y/N/NA). N

Explanation. A negative wholesale contribution is not a reason to cut a cheaper, weaker tool. Alex Meadow has not authorized any tool draw, and the feasibility path stops before steel.

Status. Open — tool not funded

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 HOTEL-01 tooling $30,000.00, amortization $16.67, annual units 600, years 3; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-03 packed $58.67; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-06 wholesale -$3.17; BMT-HOTEL-FUNDING-WORKSHEET-001 $60,000.00. 2026-10-24.

Owner. Alex Meadow

Next action. Jordan Vale attaches the 50% volume amortization so Alex Meadow can refuse the $30,000.00 tool at the feasibility gate. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Tool allowance fails the stop-before-tooling rule.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Mouse Hotel — Will gate, knit line, sink, or ejector marks hit a functional or inspection surface?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-10

Question. Will gate, knit line, sink, or ejector marks hit a functional or inspection surface?

Evidence to record. Proposed gate, bond, or witness location; knit or weld line versus latch, window, and other datums; sink at ribs and bosses; surfaces that are cosmetic, optical, or functional. A moldflow or construction review is evidence. A render is not.

Answer / assumption. The clear lid is both the CTQ06 viewing surface and the path over the sensor windows. It must not carry a gate, a heavy knit line, or an ejector pin. Baffle pivots (CTQ07) and the latch land (CTQ01) must not sit on a knit line. Chamber ribs that sink will close the raised vents (CTQ02) and the between-chamber air path (CTQ16). No gate side and no moldflow exist.

Result (Y/N/NA). N

Explanation. Gating into the lid to fill three chambers would be refused under CTQ06 and CTQ08. That refusal is on this sheet before a bidder offers it.

Status. Open — no moldflow

Evidence / exact revision / URL and date. CTQ01, CTQ02, CTQ06, CTQ08, CTQ16; HOTEL-01 PP clear lid; no moldflow. 2026-10-24.

Owner. Jordan Vale

Next action. Mark gate, ejector, and knit-line keep-out on the lid, the three sensor windows, and the latch land. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Keep-out is intent only. No moldflow is on file.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1

Mouse Hotel — Are wall, draft, rib, and boss sizes inside a named supplier limit?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-11

Question. Are wall, draft, rib, and boss sizes inside a named supplier limit?

Evidence to record. Nominal wall, thin-to-thick ratio, draft by surface, rib and boss size versus wall, corner radii, and the named supplier's written limit. Do not copy a universal wall or draft number. Record machining or composite limits the same way when the part is not molded.

Answer / assumption. Not known. No nominal wall, draft, rib ratio, or boss size is released for the three-chamber lid. Warp of that lid is the obvious process risk and has no number on it. The 24 dated bids do not state a wall, draft, rib, or boss limit. The purchased cassette outline is also without a supplier keep-out drawing.

Result (Y/N/NA). N

Explanation. These fields may stay blank through the feasibility gate. They may not be filled with a generic wall thickness.

Status. Open — no supplier limit

Evidence / exact revision / URL and date. BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; RFQ unanswered; no supplier limit for the lid or the HOTEL-04 outline. 2026-10-24.

Owner. Jordan Vale

Next action. Add blank shell-limit lines and a blank cassette-outline line to the unissued BMT-HOTEL-RFQ-PACKAGE-001. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Wall, draft, rib, and boss stay blank.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1; BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1

Mouse Hotel — Which undercuts, side actions, inserts, or steel-safe changes are still open?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-12

Question. Which undercuts, side actions, inserts, or steel-safe changes are still open?

Evidence to record. Each undercut, side action, insert, or shutoff; the requirement it serves; steel-safe or bond-safe direction; added tool or fixture cost; and the failure mode reopened if the feature is deleted to simplify the process.

Answer / assumption. Likely slides or shutoffs: three one-way baffle stops, the latch undercut, the raised vents, and the cassette seal groove. Preferred steel-safe direction is extra metal on the latch land and on the anti-backdrive stop. None of those side actions are priced inside the $30,000.00 allowance, so the allowance is incomplete if slides are required. Deleting the anti-backdrive stop to avoid a slide reopens DF07 at a proposed RPN of 280.

Result (Y/N/NA). N

Explanation. Combining the three chambers into one tub to cheapen the tool reopens DF16 at a proposed RPN of 360. That change is not accepted.

Status. Open — slides not priced

Evidence / exact revision / URL and date. DF07 RPN 280 and DF16 RPN 360; BMT-HOTEL-TEMPLATE-COST-SHEET-001 has no side-action line under the $30,000.00 allowance. 2026-10-24.

Owner. Jordan Vale

Next action. Price each slide as an open add to the allowance, or redesign it out without dropping CTQ07 or CTQ16. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Slides are unnamed. Steel-safe direction is not priced.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1

Mouse Hotel — Can orientation errors and loose hardware be prevented in assembly?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-13

Question. Can orientation errors and loose hardware be prevented in assembly?

Evidence to record. Part count, standard versus special hardware, keyed or captive features, wrong-way trials, tool access, wires and seals, and a timed build at the planned station. Link each credible error to the PFMEA row.

Answer / assumption. The cassette clocks one way. The battery connector is keyed. The three baffles are either identical or chamber-keyed; that is undecided. HOTEL-04 orientation sets the antenna keep-out for DF15. The HOTEL-07 flash fixture has to reject a single-bank part because DF11 scores a proposed RPN of 288 on a power-loss update. No loose screw is intended. No wrong-way trial has been run.

Result (Y/N/NA). N

Explanation. PFMEA causes are still written as assembly or configuration error. A fixture that only checks that a connector is occupied will miss a reversed baffle.

Status. Open — no wrong-way trial

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1; DF11 RPN 288; DF15 RPN 360; no assembly trial. 2026-10-24.

Owner. Jordan Vale

Next action. Add baffle orientation and flash-fixture interlock as characteristics on PF07 and PF11. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Poka-yoke is not tried. Occurrence is unchanged.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-PFMEA-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1

Mouse Hotel — Can the product be washed, serviced, and reassembled without damaging a sealed or energized part?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-14

Question. Can the product be washed, serviced, and reassembled without damaging a sealed or energized part?

Evidence to record. Tool-free steps, wet zone versus sealed or energized parts, battery and electronics removal, fastener reuse, and the wash or service sequence. Do not claim an ingress rating without a test record.

Answer / assumption. The shell still has to open without tools for CTQ04. The electronics cassette has to be out of the wet zone, or positively sealed and labeled, before any wash (DF13, proposed RPN 315, shock or overheating if water reaches the board). HOTEL-05 stays with the dry cassette (DF12, proposed RPN 320). HOTEL-06 is an external adapter and is not washed. No ingress rating is claimed. No splash trial has been run.

Result (Y/N/NA). N

Explanation. A sealed-in board that cannot be removed, or a user instruction that says to rinse the whole unit, fails DF13. Biological cleaning is not claimed.

Status. Open — wash not run

Evidence / exact revision / URL and date. DF04, DF12, DF13; CTQ04 and CTQ13; CP rows planned; no ingress test and no IP rating. 2026-10-24.

Owner. Jordan Vale

Next action. Show the cassette coming out before the wash step on the unreleased service sketch, and keep the IP claim off the drawing. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Service path is intent. No wash record exists.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-CONTROL-PLAN-001 Rev C1

Mouse Hotel — Can every CTQ be measured where the process creates it?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-15

Question. Can every CTQ be measured where the process creates it?

Evidence to record. Each CTQ, its datum, gauge or method, sample size, whether the characteristic is still reachable after the next operation, and the control-plan row. A control-plan line with no gauge is not a result.

Answer / assumption. Shell CTQs use the same methods as the trap family where the function is shared: 100 dry cycles and a 5 N pull (CP01), vent occlusion (CP02), 30 mm finger line (CP03), soil check (CP04), bait pull (CP05), and window visibility (CP06). Later rows need access before the next join: baffle stop before the lid is fixed (CP07), sensor window before any label (CP08), seal gland before the cassette is inserted (CP13), antenna keep-out at cassette install (CP15). The control plan is CP01–CP20. CTQ01–CTQ20 and tests T01–T20 are unrun. Radio-integration hold is process step P18, not P15. Latch assembly is P05. BMT-HOTEL-CONTROL-PLAN-001 calls for 10 prototype units from HOTEL-X1-001 through HOTEL-X1-010 and one fault-injection rig. No gauge and no result exist.

Result (Y/N/NA). N

Explanation. Flashing labor on HOTEL-07 does not measure a mold characteristic. A software rig does not close CP01.

Status. Open — gauge not named

Evidence / exact revision / URL and date. BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01–CP20; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01–CTQ20; BMT-HOTEL-TEST-PLAN-001 Rev C1 T01–T20, unrun; BMT-HOTEL-PROCESS-FLOW-001 Rev C1 P01–P21, radio-integration hold at P18; planned IDs HOTEL-X1-001 through HOTEL-X1-010; no measurement record. 2026-10-24.

Owner. Jordan Vale

Next action. Name the gauge or method on each open CP row, and mark which characteristics disappear after the lid or cassette is installed. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Control-plan methods are unnamed. No result is filed.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-TEST-MATRIX-001 Rev C1

Mouse Hotel — Do packaging, labels, and secondary operations change the geometry or the cost?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-16

Question. Do packaging, labels, and secondary operations change the geometry or the cost?

Evidence to record. Carton or crate, label and lot-mark location, surfaces the mark must not cover, secondary operations and their cost, and whether that cost is already inside the packed unit cost. Note any drop or damage trial as planned or done.

Answer / assumption. HOTEL-08 carton and tray is $2.00 and is already inside the $58.67 packed cost. HOTEL-07 flashing labor is $3.00 and is also inside that pack; it is not a molding secondary. No drop test, barcode, or ultrasonic weld is specified. The lot mark has to survive washing and must not cover a sensor window, the occupancy indicator, or the offline indicator. Shipping-damage testing remains planned.

Result (Y/N/NA). N

Explanation. A weld or a full-wrap label added later would change both geometry and the packed cost. Neither is in BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1.

Status. Open — no packaging trial

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-07 and HOTEL-08; BMT-HOTEL-TEMPLATE-COST-SHEET-001 unit costs $3.00 and $2.00; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-03 and BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 row ECONOMICS-04; no packaging trial. 2026-10-24.

Owner. Jordan Vale

Next action. Reserve a non-optical face for a wash-durable lot mark and hold secondary operations at the two lines already costed. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Pack cost is inside the piece. No pack trial exists.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1

Mouse Hotel — Which high-RPN design features must stay if a supplier offers to simplify the tool or the bill of materials?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-17

Question. Which high-RPN design features must stay if a supplier offers to simplify the tool or the bill of materials?

Evidence to record. DFMEA ID, proposed RPN, feature, the simplification a supplier might offer, the requirement that simplification would break, and the person who must refuse it. State that the ratings are proposed and untested.

Answer / assumption. Freeze, before any simplification offer: latch and keyed pin (DF01, RPN 210), raised vents (DF02, RPN 252), external slider (DF03, RPN 192), removable wash path (DF04, RPN 240), captive bait (DF05, RPN 162), clear window (DF06, RPN 432), one-way baffles (DF07, RPN 280), independent sensor checks (DF08, RPN 360), local indicator not only Wi-Fi (DF09, RPN 432), protected pack (DF12, RPN 320), dry cassette (DF13, RPN 315), frozen antenna layout (DF15, RPN 360), and separate compartments (DF16, RPN 360). Highest proposed RPNs in this set are 432 on DF06 and DF09. Actions are not implemented or tested.

Result (Y/N/NA). Y

Explanation. Combining chambers, burying the board where it will be washed, or dropping the local indicator to save a tool feature is a welfare or shock change. Jordan Vale refuses those cuts. Alex Meadow has not been asked to accept them.

Status. Recorded — freeze list not signed

Evidence / exact revision / URL and date. BMT-HOTEL-DFMEA-001 Rev C1 freeze-list rows through DF16, inside the DF01–DF32 index, proposed RPNs as cited; actions open. 2026-10-24.

Owner. Jordan Vale

Next action. Attach this freeze list to the unissued BMT-HOTEL-RFQ-PACKAGE-001 as characteristics the bidder may not remove. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Freeze list is the refusal rule. Actions stay open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-DFMEA-001 Rev C1

Mouse Hotel — What will the bridge build prove, and what must not be inferred from it?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Design for Manufacture and Assembly

Lead. Jordan Vale

Item ID. DFM-18

Question. What will the bridge build prove, and what must not be inferred from it?

Evidence to record. Bridge process, unit-ID series, which CTQs the bridge article can exercise, which production features it cannot represent, and the rule that a bridge pass is not first-article acceptance and not tool authorization.

Answer / assumption. HOTEL-X1-001 through HOTEL-X1-010 bridge units may be printed or machined to check unloaded slider reach, a surrogate baffle probe, and window visibility. They will not represent lid warp, seal compression after washing, antenna layout, battery fault behavior, or firmware rollback (DF11, proposed RPN 288). A bridge pass is not a first article and is not permission to spend the $30,000.00 tool. No unit has been built.

Result (Y/N/NA). Y

Explanation. BMT-HOTEL-CONTROL-PLAN-001 limits 10 prototype units to no reliability inference, and it separates one fault-injection rig from the mechanical checks. This row keeps that split.

Status. Recorded — bridge limit not signed

Evidence / exact revision / URL and date. BMT-HOTEL-CONTROL-PLAN-001 Rev C1, 10 prototype units and 1 fault-injection rig, no results; planned IDs HOTEL-X1-001 through HOTEL-X1-010. 2026-10-24.

Owner. Jordan Vale

Next action. Write the bridge-versus-production column on BMT-HOTEL-TEST-PLAN-001 before any X1 unit is made. Target 2027-02-15.

Reviewer / review date. Pending. Casey Holt, planned 2026-11-01. Bridge limit is recorded. It is not a first article.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-HOTEL-TEST-PLAN-001 Rev C1

Document administration

Scope. HOTEL-C1 three-chamber shell HOTEL-01 and the electronics cassette. Bridge serials HOTEL-X1-001 through HOTEL-X1-010, none built. Tooling allowance $30,000.00. The $60,000.00 Hotel allowance is unsecured and stops before production tooling.

Preparation: Jordan Vale, scenario attribution, 2026-10-24. Signature: unsigned. Review: pending; no reviewer signature or date. Approval: withheld; no approver signature or date.

Prepared byDate
Reviewed byDate
Approved byDate