The Better Mouse Trap Co. / sample paperwork

Mouse Hotel — Suppliers and production readiness

Mouse HotelRevision C12026-10-24Planning draft18 entries
Mouse Hotel — Suppliers and production readinessBMT-HOTEL-CHECK-SHEET-PRODUCTION-001 · Rev C1
Company
The Better Mouse Trap Co.
Project / product line
Hotel trap
Document
Mouse Hotel — Suppliers and production readiness
Document no.
BMT-HOTEL-CHECK-SHEET-PRODUCTION-001
Revision
C1
Status
Planning draft
Start date
2026-10-24
Revision date
2026-10-24
Prepared by / owner
Jordan Vale, Hotel electronics, with Sam Reed on the shell
Checklist ID
BMT-HOTEL-CHECK-SHEET-PRODUCTION-001, Rev C1
Scope
HOTEL-C1 supplier readiness for the three-chamber shell and the electronics cassette.
Reviewer
Casey Holt
Review date
Planned 2026-11-01. Pending as of 2026-10-28. The review has not been held.
Team
Alex Meadow, packet owner; Jordan Vale, Hotel electronics; Sam Reed, mechanical reference; Robin Keel, animal-welfare reviewer
Approved by
review pending. Alex Meadow, Planning draft C1, unsigned. The $60,000.00 Hotel allowance is not drawn.
Mouse Hotel — Suppliers and Production Readiness
Item / review questionAnswer / findingResult / statusEvidenceResponsibility / action

Item ID: PRODUCTION-01

Question: Are all suppliers quoting the same thing?

Answer / assumption: Twenty-four dated bids are on BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, refs FSW-H-2026-01 through NLM-H-2026-24, parts HOTEL-01 through HOTEL-08, unawarded, no purchase order, cash disbursed Not applicable — no transaction in this planning record. The obsolete two-supplier blank sheet is withdrawn. HOTEL-01 shell bids: FSW-H-2026-01 (Fictional Sample Works, Perry Voss) dated 2026-09-19, valid through 2026-12-18, P20 steel mold, three chambers, 1 cavity, 300,000 shots, tooling $34,500.00, volume piece $7.35, annual qty 600, tool lead 16 weeks, tool owner: The Better Mouse Trap Co. when paid. MPS-H-2026-02 (Fictional Meadow Prototype Shop, Willa Marsh) dated 2026-09-23, valid through 2026-11-22, Aluminum bridge mold, three chambers, 1 cavity, 20,000 shots, tooling $14,800.00, volume piece $12.80, annual qty 200, tool lead 6 weeks, tool owner: Meadow Prototype Shop until buyout. NLM-H-2026-03 (Fictional Northline Molding, Eden Crowe) dated 2026-09-30, valid through 2026-12-29, Pre-hard mold, three chambers, 1 cavity, 150,000 shots, tooling $28,750.00, volume piece $8.45, annual qty 600, tool lead 13 weeks, tool owner: The Better Mouse Trap Co. before kickoff. The internal $30,000.00 shell allowance is outside the $60,000.00 Hotel ceiling and is not one of those bids. Drawings are not released, so the bids are not one common released revision. The company correspondence log has no outbound letter to Perry Voss, Willa Marsh, or Eden Crowe. That gap does not erase the bids. BOM C1 splits HOTEL-09 through HOTEL-15 as included cost inside the $42.00 pre-tool sum. BOM C1 assigns the shell lines to Sam Reed and the sensor, radio, battery, and firmware lines to Jordan Vale. This check sheet owner stays Jordan Vale. BOM C1 records a labor-line name clash on HOTEL-07: the cost sheet still names Fictional Sample Works, and the BOM says that name is not an order. Hotel stays deferred until Basic evidence exists. The 600-a-year column is a cost case, not demand.

Explanation: G1 holds tooling. Twenty-four unawarded bids are not an award and are not one released revision for a three-chamber unit. The labor-line name on the cost sheet is not a shop release. The $30,000.00 allowance is outside the $60,000.00 ceiling.

Result (Y/N/NA): N

Status: Open — bids unawarded, drawing not released

BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-16; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 dated bids, FSW-H-2026-01 through NLM-H-2026-24, unawarded.

Owner: Jordan Vale

Next action: Jordan Vale does not award a bid. Sam Reed does not award the shell package. The three quote contacts stay unawarded. Target 2027-02-15, planned.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Twenty-four bids stay unawarded. There is no common released offer and no purchase order.

Item ID: PRODUCTION-02

Question: Can the supplier actually make and inspect it?

Answer / assumption: No audit or capability study. The twenty-four bids are not an audit and not a pilot qualification. Perry Voss, Willa Marsh, and Eden Crowe are quote contacts for HOTEL-01 through HOTEL-08. They are not shown as a qualified PCB assembler, cell source, or sensor source. CP01 through CP20 are draft. Controlling process steps are P01 through P21. Latch is P05. Radio-integration hold is P18. HOTEL-07, assembly and flashing, is in-house labor for Sam Reed and Jordan Vale and is not engaged. The signed image and the fixture do not exist. No award and no purchase order. Hotel stays deferred until Basic evidence exists.

Explanation: Make-and-inspect readiness for Mouse Hotel is mechanical plus a flash station. Neither exists as a qualified process. A tooling bid does not cover the cassette. Directory names are not qualification.

Result (Y/N/NA): N

Status: Open — no capability evidence

BMT-HOTEL-BOM-001 Rev C1 HOTEL-07 supplier in-house, not engaged; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP20 draft; HOTEL-15 no binary; quote comparison 24 bids,

Owner: Jordan Vale

Next action: Jordan Vale requests no audit. The flash fixture is not built and is not ordered. The bids stay unawarded. Target 2027-02-15, planned.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No audit, process limit, or production address is on file. Directory names are not qualification.

Item ID: PRODUCTION-03

Question: What are the real costs and commitments?

Answer / assumption: No spending committed; tooling allowance $30,000.00; per-unit packed cost $58.67 estimate. Funding worksheet C1 states a $60,000.00 feasibility allowance, status Not funded/committed, and future Hotel/Drone funding not secured. It says stop before production tooling. The unfunded ceiling is prototype and rig $24,000.00, specialist testing and welfare $18,000.00, engineering and market $12,000.00, and reserve $6,000.00. The $30,000.00 shell allowance is outside the $60,000.00 ceiling and is not these bids. The ceiling is not drawn from the Basic cap. BOM C1 puts the shell tool on HOTEL-16 as $30,000.00 NRE, not ordered, already amortized at $16.67. Lines on BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1: HOTEL-01 Three-chamber shell line $24.67; HOTEL-02 Entry baffles/latches line $3.00, BOM qty 3 at $1.00 each; HOTEL-03 Sensor array line $6.00; HOTEL-04 Radio/controller cassette line $10.00; HOTEL-05 Protected battery line $6.00; HOTEL-06 Charger and cable line $4.00; HOTEL-07 Assembly and flashing line $3.00; HOTEL-08 Carton and instructions line $2.00. Running total $58.67. Shell amortization $16.67 on tooling $30,000.00 at 600 units/year for 3 years. BOM pre-tool sum $42.00. Adding the NRE mold row again would count the tool twice. BOM C1 states the piece as $58.67. Ten times $58.67 is $586.67 of estimated packed cost, not a quote and not freight. The 600/year figure is a denominator. The RFQ quantity line records forecast sales as zero. HOTEL-10 says that if the shell resin cannot absorb the $0.75 bait-pocket allowance, Sam Reed re-cuts the cost sheet before any quote. That re-cut has not happened. Owner capital of $80,000.00 is not deposited.

Explanation: The $30,000.00 shell allowance is outside the $60,000.00 Hotel ceiling. It does not hide inside the $24,000.00 prototype-and-rig line, and it is not one of the shell bids at $34,500.00, $14,800.00, and $28,750.00. The ceiling itself is not secured. G1 holds tooling.

Result (Y/N/NA): N

Status: Open — allowances uncommitted

BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 running total $58.67; BMT-HOTEL-BOM-001 Rev C1 HOTEL-10 and HOTEL-16; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale leaves the mold and the allowance uncommitted. Sam Reed does not award the shell bids that are already on the comparison sheet. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Allowances are recorded and uncommitted. Nothing in this row is an awarded supplier price. The bids on HOTEL-01 through HOTEL-08 stay unawarded.

Item ID: PRODUCTION-04

Question: Who owns tooling, data and changes?

Answer / assumption: Proposed company ownership of tooling/data; contract and ECN approval before later frozen changes. Tool title is unsigned. The three HOTEL-01 bids do not share one title clause: company when paid, shop until buyout, and company before kickoff. BOM C1 HOTEL-16 names Alex Meadow on the tooling note. No removal, custody, or maintenance clause exists. G3 is No freeze. DFM-06 bars a cell, antenna, or latch-sensor substitute without regression. The radio module is unselected, and CTQ15 says no FCC ID is invented. Lane Corwin has not cleared disclosure. The RFQ records no NDA and no disclosure.

Explanation: Change control cannot start before a baseline. The cassette and the cell are the changes most likely to be substituted, and both are unnamed.

Result (Y/N/NA): N

Status: Open — tool title unsigned

BMT-HOTEL-BOM-001 Rev C1 HOTEL-16; CTQ15; DFM-06; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 NDA field. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Alex Meadow does not sign tool title. Jordan Vale does not select a radio module on this sheet. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Tool title is unsigned. The three bids do not share one title clause. No NDA and no change baseline.

Item ID: PRODUCTION-05

Question: How will we accept incoming parts and production output?

Answer / assumption: Incoming configuration check, linked CP controls, planned FAI; no inspection evidence. Accept would use BOM C1 and draft controls CP01 through CP20, drawing revision Mouse Hotel C1, phase prototype. FAI characteristics are Not measured. Tests T01 through T20 are unrun. CTQ01 through CTQ20 are untested. Stopping ahead of CTQ17 would leave the set incomplete. Planned unit IDs HOTEL-X1-001 onward have no results. The control plan names a fault-injection harness for the beam and the weight channel. It has not been built and it is not a production sample plan. Work instructions are draft. Controlling process steps are P01 through P21. Latch is P05. Radio-integration hold is P18. HOTEL-15, the signed firmware image, does not exist.

Explanation: There is no first article to accept. A flash step with no image is not an incoming test. Controls stay draft.

Result (Y/N/NA): N

Status: Blocked — FAI not measured

BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP20 draft; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-HOTEL-BOM-001 Rev C1 HOTEL-15. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale does not record FAI results. Sam Reed does not accept shell parts against an unreleased drawing. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. FAI characteristics are Not measured. Draft controls are not acceptance.

Item ID: PRODUCTION-06

Question: Can we deliver and recover from interruption?

Answer / assumption: Assume single source initially; qualify backup before scale; no promised delivery. RFQ quantity is 10 prototype units. The 600-a-year figure is a cost case and the amortization denominator, not demand and not a forecast. The year-1 hypothesis is 600 units. Meadow Prototype Shop bids 200 a year, is not an electronics qualification, and is not a qualified backup. HOTEL-03, HOTEL-04, and HOTEL-05 have dated bids, including lead times, and those bids are unawarded. A bid lead time is not a delivery promise. G1 is Hold tooling pending evidence. No inventory and no delivery promise.

Explanation: A commercial trap with a cassette cannot be recovered by a second mold shop alone. The long-lead articles are not a qualified source. No customer date is offered.

Result (Y/N/NA): N

Status: Open — no recovery source

BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 quantities and 8-week window; BMT-HOTEL-BOM-001 Rev C1 HOTEL-03, HOTEL-04, HOTEL-05. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale does not promise delivery and does not treat an unawarded backup bid as qualification. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The volume figure is a cost denominator. No delivery date is promised.

Item ID: PRODUCTION-07

Question: What must be in place after sale?

Answer / assumption: Traceability, complaints, recall containment, returns and safe disposal required before sale. Traceability, complaints, recall, returns, and safe disposal are required before sale and are not written. The same gap covers cell disposal and the CTQ14 path: no precise location, and a 30-day deletion request that has no process behind it. BOM C1 says the draft one-year manufacturing-defect remedy is unprinted, so this sheet is not a warranty. G5 is No launch authorized. Nia Calder has not bound coverage. Robin Keel has yet to approve capacity. CTQ16 says capacity is not rated. HOTEL-08 calls three chambers an unrated target. Nothing has been sold.

Explanation: After-sale scope is wider than a plastic housing. G5 stays closed until insurance, capacity, and the deletion path exist as records. They do not.

Result (Y/N/NA): N

Status: Blocked — after-sale records absent

CTQ14 and CTQ16; BMT-HOTEL-BOM-001 Rev C1 HOTEL-08; BMT-HOTEL-STAGE-GATES-001 Rev C1 G5. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale does not print a warranty or a capacity rating. Robin Keel is not given a new assignment by this row. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. After-sale records are absent. Gate G5 is not a launch.

Item ID: PRODUCTION-08

Question: Is the first production order ready?

Answer / assumption: Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. G3 is No freeze. G4 is No purchase order. Missing drawings, qualification, physical tests, and reviewed controls each block the order. Connected features on the concept do not create a production release. This row is not that release.

Explanation: PRODUCTION-08 is the buy stop. A shell quote, a module datasheet, or this checklist does not replace Alex Meadow recording a decision, and he has not.

Result (Y/N/NA): N

Status: Blocked — release not recorded

BMT-HOTEL-STAGE-GATES-001 Rev C1 G0, G3, G4; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 Not funded/committed. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Nobody places a purchase order for Mouse Hotel. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. This row is the buy stop. It is not a release by Alex Meadow.

Item ID: PRODUCTION-09

Question: Is one released revision ready so the quoted shops would be on the same released part?

Answer / assumption: Not ready. DFM-07 records requirements R01 through R16 at C1 and no released CAD or drawings. DFM-03 and DFM-04 are open. DFM-08 records no manufacturer comments. CTQ15 says the module is chosen only after grant, antenna, and host review, and no FCC ID is invented, so the cassette is not a defined part. HOTEL-14 keeps the antenna layout frozen until that review, and no RF lab date exists. Twenty-four bids are on file for HOTEL-01 through HOTEL-08 and are not one released revision. No drawing has been released.

Explanation: Shell bids and a radio line on the same comparison sheet are not one released package. Until both are defined at one revision, PRODUCTION-01 stays no.

Result (Y/N/NA): N

Status: Blocked — drawing not released

DFM-03, DFM-04, DFM-07, DFM-08; CTQ15; BMT-HOTEL-BOM-001 Rev C1 HOTEL-14. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale writes the open DFM rows and the unselected module as exclusions. The package is not sent. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No released drawing, so the bids on file are not one released part.

Item ID: PRODUCTION-10

Question: Is every CTQ measurable on a first-article record with a defined gauge and sample?

Answer / assumption: Not measurable as a first article. All 16 FAI rows are Not measured, and suitability review is pending. The set is CTQ01 door latch, CTQ02 vents, CTQ03 30 mm release, CTQ04 wash, CTQ05 20 N bait pull, CTQ06 occupancy visible without opening, CTQ07 baffle back-drive at 2 N, CTQ08 sensor with zero false-empty in the concept screen, CTQ09 local indicator with the network down, CTQ10 physical-button provisioning, CTQ11 firmware safe through a power loss, CTQ12 no wet charge and a 45 C cutoff pending battery-engineer review, CTQ13 cassette unseated inhibits power, CTQ14 no precise location, CTQ15 module not chosen, and CTQ16 capacity not rated. CTQ17 through CTQ20 are also untested: offline occupied indication, wash water at the board, cassette wash and the offline lamp, and chamber pitch or vent drift. Stopping ahead of CTQ17 would leave the set incomplete. No battery engineer is named on the people register, so the CTQ12 review has no assignee. The fault-injection harness for the beam and the weight channel has not been built.

Explanation: The open item is not a missing sticker. CTQ12 names a reviewer who is not on the people register, and CTQ16 refuses a capacity number. FAI cannot close those with a gauge.

Result (Y/N/NA): N

Status: Open — CTQ gauges not suitable

BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ20; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 has no battery-engineer

Owner: Jordan Vale

Next action: Jordan Vale does not invent a battery-engineer name. The CTQ12 review stays pending. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Gauge suitability is pending. FAI stays Not measured.

Item ID: PRODUCTION-11

Question: Is pilot cash identified, and is production tooling still stopped?

Answer / assumption: Identified only as an unfunded estimate, and the mold is stopped. The $60,000.00 allowance is not secured. Future Hotel/Drone funding is not secured. The $24,000.00 prototype-and-rig line is unreleased, and ten times $58.67 is $586.67. That amount is not a purchase order. HOTEL-16 at $30,000.00 sits outside the $60,000.00 ceiling and is also larger than the $24,000.00 line. The funding sheet says stop before production tooling. The company is not formed. Ellis Brook at Example Meadow Bank is a depository contact only. Credit is not requested. Owner capital of $80,000.00 is not deposited.

Explanation: The $30,000.00 shell allowance is outside the $60,000.00 ceiling, and the ceiling is not cash. G4 remains No purchase order. G0 through G5 are pending.

Result (Y/N/NA): Y

Status: Recorded — stop holds; cash unfunded

BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 $60,000.00 not secured; BMT-HOTEL-BOM-001 Rev C1 HOTEL-16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Alex Meadow does not release the prototype line or the shell mold. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The tooling stop holds. Pilot cash is an unfunded estimate, not a release.

Item ID: PRODUCTION-12

Question: Are sub-tier parts and special processes identified to a named source?

Answer / assumption: No qualified sub-tier beyond the quote contacts. Fictional Sample Works, Meadow Prototype Shop, and Fictional Northline Molding have unawarded bids on HOTEL-01 through HOTEL-08. Those bids do not name a qualified PCB assembler or cell maker. Included splits excluded from the $42.00 sum: HOTEL-09 dividers qty 2, HOTEL-10 bait pockets qty 3 with allowance $0.75 extended, HOTEL-11 release sliders qty 3, HOTEL-12 occupancy lamp, HOTEL-13 keyed cassette seal, HOTEL-14 antenna keep-out, and HOTEL-15 firmware labor inside HOTEL-07. HOTEL-05 cell and watt-hours are unselected. HOTEL-06 has no certification file. No PCB assembler and no cell maker are named. DFM-06 bars a cell or antenna substitute without regression.

Explanation: The $42.00 sum hides the chamber hardware inside the shell and the cassette. A quote that prices those splits again, or that ignores the $0.75 resin warning on HOTEL-10, is not the same basis as PRODUCTION-01.

Result (Y/N/NA): N

Status: Open — sub-tier sources unnamed

BMT-HOTEL-BOM-001 Rev C1 HOTEL-09 through HOTEL-15 and HOTEL-05; DFM-06. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Sam Reed leaves the shell sub-tier blank. Jordan Vale leaves the cell and the module blank. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Sub-tier sources are unnamed. Included splits must not be priced twice.

Item ID: PRODUCTION-13

Question: Is the carton, the instruction revision, and the shipping trial defined for the packed unit?

Answer / assumption: Not defined. HOTEL-08 is line $2.00 inside the $42.00 sum. The BOM description requires the sheet to say: detach the cassette before wash, gloves, frequent check, offline lamp, three chambers as an unrated target, and no sterilization claim. That text is a BOM note, not an approved print. The RFQ shipping qualification has not been run. The protected pack and the adapter have no transport classification on file, and no shipment is authorized. Freight and duty are excluded on every bid, so there is no landed freight term. Payment terms on the bids are not a signed contract. The $58.67 piece is not a landed cost.

Explanation: Instruction content is part of the packed unit because CTQ13 and CTQ16 are user-visible. An unprinted note is not a revision. Freight is unknown.

Result (Y/N/NA): N

Status: Open — pack and freight undefined

BMT-HOTEL-BOM-001 Rev C1 HOTEL-08 description; CTQ13 and CTQ16; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 packaging field. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Sam Reed does not print the instruction. Jordan Vale marks cell transport and freight as exclusions. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The instruction text is a bill-of-materials note. Freight is excluded on the bids and is not a landed cost.

Item ID: PRODUCTION-14

Question: Can each packed unit be traced to component lots and the assembly record?

Answer / assumption: Not traceable. The control plan says: Planned unit IDs HOTEL-X1-001 onward; no results There is no lot code for the shell, the cell, the PCB, or the sensor, and no firmware hash. CTQ10 requires a unique device identity and that scheme is not defined. HOTEL-15 has no binary on file, so there is no image identity to record. PRODUCTION-07 still requires traceability before sale.

Explanation: A connected unit without a firmware identity cannot be recalled to a bad flash. The traveler is blank, so the requirement is unmet.

Result (Y/N/NA): N

Status: Open — traceability blank

BMT-HOTEL-CONTROL-PLAN-001 Rev C1 HOTEL-X1-001; CTQ10; BMT-HOTEL-BOM-001 Rev C1 HOTEL-15. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale does not assign device identities and does not print serial labels. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Planned serials have no lot code, traveler, or retain.

Item ID: PRODUCTION-15

Question: Which open process failures block acceptance of a pilot lot?

Answer / assumption: Do not accept a pilot lot. BMT-HOTEL-PFMEA-001 Rev C1 has 60 data rows, PF01 through PF60. Status is Open, Hold, or Blocked. No row is accepted. Severity 9 or 10 lines number 34. Highest lines, and the lines this sheet had been indexing short: PF12 RPN 320 severity 10 (Charge script missing the overtemperature cutoff; Blocked); PF09 RPN 432 severity 9 (Alert path checked only by a phone notification; Open); PF06 RPN 432 severity 9 (Window line closed with no pane check; Open); PF08 RPN 360 severity 9 (Beam left readable while the weight channel is unwired; Open); PF15 RPN 360 severity 9 (Host keep-out edited after the freeze; Hold); PF16 RPN 360 severity 9 (Divider left out of the kit; Blocked); PF02 RPN 252 severity 9 (Ribs clocked onto the floor of a chamber; Open); PF11 RPN 288 severity 9 (Single-bank image flashed; Open); PF13 RPN 315 severity 9 (Board left in the shell for a wash trial; Open); PF35 RPN 216 severity 9 (Beam and weight connectors swapped; Open); PF37 RPN 216 severity 9 (Lamp wired to the radio supply; Open); PF49 RPN 216 severity 9 (Divider seated in the wrong rib; Open). Those highlighted lines do not stand in for PF01 through PF60. Robin Keel has yet to approve a capacity and is not contacted. Robin Keel does not certify the trap. Controls are CP01 through CP20, draft. Latch is P05. Radio-integration hold is P18. CTQ01 through CTQ20 are untested. Tests T01 through T20 are unrun.

Explanation: The block is the open process FMEA, not a wish for more process steps. A pilot accepted now would skip stop and hold on the control plan. Alex Meadow has not authorized a restart. No build exists.

Result (Y/N/NA): Y

Status: Recorded — pilot lot refused

BMT-HOTEL-PFMEA-001 Rev C1 PF01 through PF60, none accepted; CTQ01 through CTQ20; control plan CP01 through CP20. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale keeps the pilot quantity at zero while PF01 through PF60 stay unaccepted. Target 2027-02-15, planned.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Open PFMEA rows stay unaccepted. A pilot lot is refused. RPN is unchanged.

Item ID: PRODUCTION-16

Question: What has to be signed before an RFQ goes out or tool steel is cut?

Answer / assumption: Nothing is signed. The RFQ says no agreement and no disclosure. Lane Corwin is not engaged. Perry Voss, Willa Marsh, and Eden Crowe have bids on file. No award and no purchase order. A later packet would also have to keep the unselected radio module and the unselected cell out of the supplier's scope until CTQ12 and CTQ15 move. Those sentences are not written. Steel is stopped under PRODUCTION-11.

Explanation: Disclosure risk on this product includes the cassette, not only the shell geometry. The file stays in house.

Result (Y/N/NA): N

Status: Blocked — terms and NDA unsigned

BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 NDA field; CTQ12 and CTQ15; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 Lane Corwin. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Jordan Vale holds the file and does not send the RFQ. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No NDA, tool clause, or payment term is signed. The file stays in house.

Item ID: PRODUCTION-17

Question: Is the three-chamber shell mold defined enough to cut the $30,000.00 tool?

Answer / assumption: No. HOTEL-16 is the internal $30,000.00 shell allowance, outside the $60,000.00 ceiling, not ordered, and not a supplier bid. It is already amortized at $16.67 per unit at 600 units a year for 3 years. HOTEL-01 bids, unawarded: FSW-H-2026-01 (Fictional Sample Works, Perry Voss) dated 2026-09-19, valid through 2026-12-18, P20 steel mold, three chambers, 1 cavity, 300,000 shots, tooling $34,500.00, volume piece $7.35, annual qty 600, tool lead 16 weeks, tool owner: The Better Mouse Trap Co. when paid. MPS-H-2026-02 (Fictional Meadow Prototype Shop, Willa Marsh) dated 2026-09-23, valid through 2026-11-22, Aluminum bridge mold, three chambers, 1 cavity, 20,000 shots, tooling $14,800.00, volume piece $12.80, annual qty 200, tool lead 6 weeks, tool owner: Meadow Prototype Shop until buyout. NLM-H-2026-03 (Fictional Northline Molding, Eden Crowe) dated 2026-09-30, valid through 2026-12-29, Pre-hard mold, three chambers, 1 cavity, 150,000 shots, tooling $28,750.00, volume piece $8.45, annual qty 600, tool lead 13 weeks, tool owner: The Better Mouse Trap Co. before kickoff. DFM-02 says bridge process before a production tool at the 600-a-year cost case. DFM-03 has not had a mold-shop review accepted as a change. Three baffles, HOTEL-02 qty 3, extended line $3.00, are a separate fit. Dividers HOTEL-09 qty 2 are molded in the shell and are not a second tool. There is no accepted T0 or T1 plan. Alex Meadow is named on the BOM tooling note and has not released it. Sam Reed holds the shell lines on BOM C1. The 600 figure is a cost case, not demand.

Explanation: Cutting steel would spend an allowance that is already inside the $58.67 piece and outside the $60,000.00 ceiling, and it would breach the stop-before-tooling rule. The supplier tools are different dollars and are unawarded. G1 has not moved.

Result (Y/N/NA): N

Status: Blocked — mold not released to cut

BMT-HOTEL-BOM-001 Rev C1 HOTEL-16 allowance $30,000.00 outside the ceiling; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 FSW-H-2026-01, MPS-H-2026-02, and NLM-H-2026-03,

Owner: Jordan Vale

Next action: Do not cut steel. Sam Reed keeps HOTEL-16 as an allowance. Jordan Vale records that stop here. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The mold is an allowance. Steel is not released.

Item ID: PRODUCTION-18

Question: What blocks a first production order even with shell bids on file?

Answer / assumption: Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. A shell quote is not an order for a connected unit. Independent blocks: G4 No purchase order, G3 No freeze, Hotel funding not secured, HOTEL-16 stopped, FAI Not measured, CP01 through CP20 draft on process steps P01 through P21, radio-integration hold at P18, CTQ12 pending with no named battery engineer, CTQ15 module unselected and no FCC ID invented, CTQ16 capacity not rated, PF09 RPN 432 and PF12 RPN 320 remain unaccepted, HOTEL-15 firmware image absent, Robin Keel has yet to approve multi-chamber use, no formed company, and no bank account.

Explanation: The feasibility gate can be prepared with this sheet and still not buy. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. This row is the record that the order was not placed.

Result (Y/N/NA): Y

Status: Recorded — order stays unplaced

BMT-HOTEL-STAGE-GATES-001 Rev C1 G0, G3, G4; CTQ12, CTQ15, CTQ16; PF09 and PF12; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.

Owner: Jordan Vale

Next action: Leave the order unplaced. A shell quote does not authorize a connected build. Target 2027-02-15.

Reviewer / review date: Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The blocks are independent. A later quote does not place the order.

Mouse Hotel — Suppliers and Production Readiness — supporting detail

Mouse Hotel — Are all suppliers quoting the same thing?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-01

Question. Are all suppliers quoting the same thing?

Evidence to record. Exact revision/material/finish/quantities, inspection, packaging and acceptance requirements; assumptions and exclusions alongside each quote.

Result (Y/N/NA). N

Explanation. G1 holds tooling. Twenty-four unawarded bids are not an award and are not one released revision for a three-chamber unit. The labor-line name on the cost sheet is not a shop release. The $30,000.00 allowance is outside the $60,000.00 ceiling.

Status. Open — bids unawarded, drawing not released

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-16; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1, 24 dated bids, FSW-H-2026-01 through NLM-H-2026-24, unawarded. Recorded 2026-10-24. The Casey Holt read is planned for 2026-11-01 and has not been held.

Owner. Jordan Vale

Next action. Jordan Vale does not award a bid. Sam Reed does not award the shell package. The three quote contacts stay unawarded. Target 2027-02-15, planned.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Twenty-four bids stay unawarded. There is no common released offer and no purchase order.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1

Mouse Hotel — Can the supplier actually make and inspect it?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-02

Question. Can the supplier actually make and inspect it?

Evidence to record. Relevant capabilities, process limits, capacity, sample evidence, documented process scope, references, subcontractors and production location. Directory membership alone is not qualification.

Answer / assumption. No audit or capability study. The twenty-four bids are not an audit and not a pilot qualification. Perry Voss, Willa Marsh, and Eden Crowe are quote contacts for HOTEL-01 through HOTEL-08. They are not shown as a qualified PCB assembler, cell source, or sensor source. CP01 through CP20 are draft. Controlling process steps are P01 through P21. Latch is P05. Radio-integration hold is P18. HOTEL-07, assembly and flashing, is in-house labor for Sam Reed and Jordan Vale and is not engaged. The signed image and the fixture do not exist. No award and no purchase order. Hotel stays deferred until Basic evidence exists.

Result (Y/N/NA). N

Explanation. Make-and-inspect readiness for Mouse Hotel is mechanical plus a flash station. Neither exists as a qualified process. A tooling bid does not cover the cassette. Directory names are not qualification.

Status. Open — no capability evidence

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-07 supplier in-house, not engaged; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP20 draft; HOTEL-15 no binary; quote comparison 24 bids, unawarded. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale requests no audit. The flash fixture is not built and is not ordered. The bids stay unawarded. Target 2027-02-15, planned.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No audit, process limit, or production address is on file. Directory names are not qualification.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — What are the real costs and commitments?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-03

Question. What are the real costs and commitments?

Evidence to record. Unit prices at realistic volumes, tooling/NRE, MOQ, lead times, payment/deposit terms, currency, freight/trade terms, duties, scrap, quote expiry and cancellation/change terms.

Answer / assumption. No spending committed; tooling allowance $30,000.00; per-unit packed cost $58.67 estimate. Funding worksheet C1 states a $60,000.00 feasibility allowance, status Not funded/committed, and future Hotel/Drone funding not secured. It says stop before production tooling. The unfunded ceiling is prototype and rig $24,000.00, specialist testing and welfare $18,000.00, engineering and market $12,000.00, and reserve $6,000.00. The $30,000.00 shell allowance is outside the $60,000.00 ceiling and is not these bids. The ceiling is not drawn from the Basic cap. BOM C1 puts the shell tool on HOTEL-16 as $30,000.00 NRE, not ordered, already amortized at $16.67. Lines on BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1: HOTEL-01 Three-chamber shell line $24.67; HOTEL-02 Entry baffles/latches line $3.00, BOM qty 3 at $1.00 each; HOTEL-03 Sensor array line $6.00; HOTEL-04 Radio/controller cassette line $10.00; HOTEL-05 Protected battery line $6.00; HOTEL-06 Charger and cable line $4.00; HOTEL-07 Assembly and flashing line $3.00; HOTEL-08 Carton and instructions line $2.00. Running total $58.67. Shell amortization $16.67 on tooling $30,000.00 at 600 units/year for 3 years. BOM pre-tool sum $42.00. Adding the NRE mold row again would count the tool twice. BOM C1 states the piece as $58.67. Ten times $58.67 is $586.67 of estimated packed cost, not a quote and not freight. The 600/year figure is a denominator. The RFQ quantity line records forecast sales as zero. HOTEL-10 says that if the shell resin cannot absorb the $0.75 bait-pocket allowance, Sam Reed re-cuts the cost sheet before any quote. That re-cut has not happened. Owner capital of $80,000.00 is not deposited.

Result (Y/N/NA). N

Explanation. The $30,000.00 shell allowance is outside the $60,000.00 Hotel ceiling. It does not hide inside the $24,000.00 prototype-and-rig line, and it is not one of the shell bids at $34,500.00, $14,800.00, and $28,750.00. The ceiling itself is not secured. G1 holds tooling.

Status. Open — allowances uncommitted

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 running total $58.67; BMT-HOTEL-BOM-001 Rev C1 HOTEL-10 and HOTEL-16; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale leaves the mold and the allowance uncommitted. Sam Reed does not award the shell bids that are already on the comparison sheet. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Allowances are recorded and uncommitted. Nothing in this row is an awarded supplier price. The bids on HOTEL-01 through HOTEL-08 stay unawarded.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Mouse Hotel — Who owns tooling, data and changes?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-04

Question. Who owns tooling, data and changes?

Evidence to record. Tool ownership, custody, maintenance and transfer access; drawings and IP, approved substitutions and who can authorize changes.

Answer / assumption. Proposed company ownership of tooling/data; contract and ECN approval before later frozen changes. Tool title is unsigned. The three HOTEL-01 bids do not share one title clause: company when paid, shop until buyout, and company before kickoff. BOM C1 HOTEL-16 names Alex Meadow on the tooling note. No removal, custody, or maintenance clause exists. G3 is No freeze. DFM-06 bars a cell, antenna, or latch-sensor substitute without regression. The radio module is unselected, and CTQ15 says no FCC ID is invented. Lane Corwin has not cleared disclosure. The RFQ records no NDA and no disclosure.

Result (Y/N/NA). N

Explanation. Change control cannot start before a baseline. The cassette and the cell are the changes most likely to be substituted, and both are unnamed.

Status. Open — tool title unsigned

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-16; CTQ15; DFM-06; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 NDA field. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Alex Meadow does not sign tool title. Jordan Vale does not select a radio module on this sheet. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Tool title is unsigned. The three bids do not share one title clause. No NDA and no change baseline.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1

Mouse Hotel — How will we accept incoming parts and production output?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-05

Question. How will we accept incoming parts and production output?

Evidence to record. First-article/pilot evidence, critical characteristics, sampling rationale, measurement methods, traceability, nonconformance/rework and corrective actions.

Answer / assumption. Incoming configuration check, linked CP controls, planned FAI; no inspection evidence. Accept would use BOM C1 and draft controls CP01 through CP20, drawing revision Mouse Hotel C1, phase prototype. FAI characteristics are Not measured. Tests T01 through T20 are unrun. CTQ01 through CTQ20 are untested. Stopping ahead of CTQ17 would leave the set incomplete. Planned unit IDs HOTEL-X1-001 onward have no results. The control plan names a fault-injection harness for the beam and the weight channel. It has not been built and it is not a production sample plan. Work instructions are draft. Controlling process steps are P01 through P21. Latch is P05. Radio-integration hold is P18. HOTEL-15, the signed firmware image, does not exist.

Result (Y/N/NA). N

Explanation. There is no first article to accept. A flash step with no image is not an incoming test. Controls stay draft.

Status. Blocked — FAI not measured

Evidence / exact revision / URL and date. BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP20 draft; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-HOTEL-BOM-001 Rev C1 HOTEL-15. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale does not record FAI results. Sam Reed does not accept shell parts against an unreleased drawing. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. FAI characteristics are Not measured. Draft controls are not acceptance.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1; BMT-HOTEL-WORK-INSTRUCTIONS-001 Rev C1

Mouse Hotel — Can we deliver and recover from interruption?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-06

Question. Can we deliver and recover from interruption?

Evidence to record. Pilot quantity, ramp/capacity plan, long-lead parts, approved alternate sources, packaging/shipping trials, inventory and reorder points.

Answer / assumption. Assume single source initially; qualify backup before scale; no promised delivery. RFQ quantity is 10 prototype units. The 600-a-year figure is a cost case and the amortization denominator, not demand and not a forecast. The year-1 hypothesis is 600 units. Meadow Prototype Shop bids 200 a year, is not an electronics qualification, and is not a qualified backup. HOTEL-03, HOTEL-04, and HOTEL-05 have dated bids, including lead times, and those bids are unawarded. A bid lead time is not a delivery promise. G1 is Hold tooling pending evidence. No inventory and no delivery promise.

Result (Y/N/NA). N

Explanation. A commercial trap with a cassette cannot be recovered by a second mold shop alone. The long-lead articles are not a qualified source. No customer date is offered.

Status. Open — no recovery source

Evidence / exact revision / URL and date. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 quantities and 8-week window; BMT-HOTEL-BOM-001 Rev C1 HOTEL-03, HOTEL-04, HOTEL-05. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale does not promise delivery and does not treat an unawarded backup bid as qualification. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The volume figure is a cost denominator. No delivery date is promised.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — What must be in place after sale?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-07

Question. What must be in place after sale?

Evidence to record. Warranty, spare parts, service, complaints, traceability and recall/incident process appropriate to product/market.

Answer / assumption. Traceability, complaints, recall containment, returns and safe disposal required before sale. Traceability, complaints, recall, returns, and safe disposal are required before sale and are not written. The same gap covers cell disposal and the CTQ14 path: no precise location, and a 30-day deletion request that has no process behind it. BOM C1 says the draft one-year manufacturing-defect remedy is unprinted, so this sheet is not a warranty. G5 is No launch authorized. Nia Calder has not bound coverage. Robin Keel has yet to approve capacity. CTQ16 says capacity is not rated. HOTEL-08 calls three chambers an unrated target. Nothing has been sold.

Result (Y/N/NA). N

Explanation. After-sale scope is wider than a plastic housing. G5 stays closed until insurance, capacity, and the deletion path exist as records. They do not.

Status. Blocked — after-sale records absent

Evidence / exact revision / URL and date. CTQ14 and CTQ16; BMT-HOTEL-BOM-001 Rev C1 HOTEL-08; BMT-HOTEL-STAGE-GATES-001 Rev C1 G5. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale does not print a warranty or a capacity rating. Robin Keel is not given a new assignment by this row. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. After-sale records are absent. Gate G5 is not a launch.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1

Mouse Hotel — Is the first production order ready?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-08

Question. Is the first production order ready?

Evidence to record. Close or explicitly disposition DFM/test gaps, confirm current file package and cash need with the funding role. Record the person’s release decision; never infer authorization to place an order.

Answer / assumption. Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. G3 is No freeze. G4 is No purchase order. Missing drawings, qualification, physical tests, and reviewed controls each block the order. Connected features on the concept do not create a production release. This row is not that release.

Result (Y/N/NA). N

Explanation. PRODUCTION-08 is the buy stop. A shell quote, a module datasheet, or this checklist does not replace Alex Meadow recording a decision, and he has not.

Status. Blocked — release not recorded

Evidence / exact revision / URL and date. BMT-HOTEL-STAGE-GATES-001 Rev C1 G0, G3, G4; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 Not funded/committed. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Nobody places a purchase order for Mouse Hotel. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. This row is the buy stop. It is not a release by Alex Meadow.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-CHECK-SHEET-DFM-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Mouse Hotel — Is one released revision ready so the quoted shops would be on the same released part?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-09

Question. Is one released revision ready so the quoted shops would be on the same released part?

Evidence to record. Released drawing, BOM revision, chamber count, cassette definition, quantities, inspection, packaging, exclusions, and a DFM disposition, as one package.

Answer / assumption. Not ready. DFM-07 records requirements R01 through R16 at C1 and no released CAD or drawings. DFM-03 and DFM-04 are open. DFM-08 records no manufacturer comments. CTQ15 says the module is chosen only after grant, antenna, and host review, and no FCC ID is invented, so the cassette is not a defined part. HOTEL-14 keeps the antenna layout frozen until that review, and no RF lab date exists. Twenty-four bids are on file for HOTEL-01 through HOTEL-08 and are not one released revision. No drawing has been released.

Result (Y/N/NA). N

Explanation. Shell bids and a radio line on the same comparison sheet are not one released package. Until both are defined at one revision, PRODUCTION-01 stays no.

Status. Blocked — drawing not released

Evidence / exact revision / URL and date. DFM-03, DFM-04, DFM-07, DFM-08; CTQ15; BMT-HOTEL-BOM-001 Rev C1 HOTEL-14. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale writes the open DFM rows and the unselected module as exclusions. The package is not sent. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No released drawing, so the bids on file are not one released part.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CHECK-SHEET-DFM-001 Rev C1; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1

Mouse Hotel — Is every CTQ measurable on a first-article record with a defined gauge and sample?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-10

Question. Is every CTQ measurable on a first-article record with a defined gauge and sample?

Evidence to record. For CTQ01 through CTQ20: method, gauge or fixture, sample, calibration or configuration date, and the FAI row. Name any limit that still has no assignee.

Answer / assumption. Not measurable as a first article. All 16 FAI rows are Not measured, and suitability review is pending. The set is CTQ01 door latch, CTQ02 vents, CTQ03 30 mm release, CTQ04 wash, CTQ05 20 N bait pull, CTQ06 occupancy visible without opening, CTQ07 baffle back-drive at 2 N, CTQ08 sensor with zero false-empty in the concept screen, CTQ09 local indicator with the network down, CTQ10 physical-button provisioning, CTQ11 firmware safe through a power loss, CTQ12 no wet charge and a 45 C cutoff pending battery-engineer review, CTQ13 cassette unseated inhibits power, CTQ14 no precise location, CTQ15 module not chosen, and CTQ16 capacity not rated. CTQ17 through CTQ20 are also untested: offline occupied indication, wash water at the board, cassette wash and the offline lamp, and chamber pitch or vent drift. Stopping ahead of CTQ17 would leave the set incomplete. No battery engineer is named on the people register, so the CTQ12 review has no assignee. The fault-injection harness for the beam and the weight channel has not been built.

Result (Y/N/NA). N

Explanation. The open item is not a missing sticker. CTQ12 names a reviewer who is not on the people register, and CTQ16 refuses a capacity number. FAI cannot close those with a gauge.

Status. Open — CTQ gauges not suitable

Evidence / exact revision / URL and date. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ20; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1 Not measured; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 has no battery-engineer seat. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale does not invent a battery-engineer name. The CTQ12 review stays pending. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Gauge suitability is pending. FAI stays Not measured.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-TEMPLATE-FAI-REPORT-001 Rev C1; BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Mouse Hotel — Is pilot cash identified, and is production tooling still stopped?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-11

Question. Is pilot cash identified, and is production tooling still stopped?

Evidence to record. Funded amount, prototype line, mold excluded from that line, signer, and the hold gate.

Answer / assumption. Identified only as an unfunded estimate, and the mold is stopped. The $60,000.00 allowance is not secured. Future Hotel/Drone funding is not secured. The $24,000.00 prototype-and-rig line is unreleased, and ten times $58.67 is $586.67. That amount is not a purchase order. HOTEL-16 at $30,000.00 sits outside the $60,000.00 ceiling and is also larger than the $24,000.00 line. The funding sheet says stop before production tooling. The company is not formed. Ellis Brook at Example Meadow Bank is a depository contact only. Credit is not requested. Owner capital of $80,000.00 is not deposited.

Result (Y/N/NA). Y

Explanation. The $30,000.00 shell allowance is outside the $60,000.00 ceiling, and the ceiling is not cash. G4 remains No purchase order. G0 through G5 are pending.

Status. Recorded — stop holds; cash unfunded

Evidence / exact revision / URL and date. BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 $60,000.00 not secured; BMT-HOTEL-BOM-001 Rev C1 HOTEL-16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Alex Meadow does not release the prototype line or the shell mold. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The tooling stop holds. Pilot cash is an unfunded estimate, not a release.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — Are sub-tier parts and special processes identified to a named source?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-12

Question. Are sub-tier parts and special processes identified to a named source?

Evidence to record. For the lid, baffles, dividers, sensor, PCB, cell, adapter, and carton printer: source, spec, and whether the cost is already inside a parent line.

Answer / assumption. No qualified sub-tier beyond the quote contacts. Fictional Sample Works, Meadow Prototype Shop, and Fictional Northline Molding have unawarded bids on HOTEL-01 through HOTEL-08. Those bids do not name a qualified PCB assembler or cell maker. Included splits excluded from the $42.00 sum: HOTEL-09 dividers qty 2, HOTEL-10 bait pockets qty 3 with allowance $0.75 extended, HOTEL-11 release sliders qty 3, HOTEL-12 occupancy lamp, HOTEL-13 keyed cassette seal, HOTEL-14 antenna keep-out, and HOTEL-15 firmware labor inside HOTEL-07. HOTEL-05 cell and watt-hours are unselected. HOTEL-06 has no certification file. No PCB assembler and no cell maker are named. DFM-06 bars a cell or antenna substitute without regression.

Result (Y/N/NA). N

Explanation. The $42.00 sum hides the chamber hardware inside the shell and the cassette. A quote that prices those splits again, or that ignores the $0.75 resin warning on HOTEL-10, is not the same basis as PRODUCTION-01.

Status. Open — sub-tier sources unnamed

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-09 through HOTEL-15 and HOTEL-05; DFM-06. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Sam Reed leaves the shell sub-tier blank. Jordan Vale leaves the cell and the module blank. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Sub-tier sources are unnamed. Included splits must not be priced twice.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-CHECK-SHEET-DFM-001 Rev C1

Mouse Hotel — Is the carton, the instruction revision, and the shipping trial defined for the packed unit?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-13

Question. Is the carton, the instruction revision, and the shipping trial defined for the packed unit?

Evidence to record. Carton and tray spec, instruction revision, transit trial, freight term, and a note that cell transport classification is unresolved.

Answer / assumption. Not defined. HOTEL-08 is line $2.00 inside the $42.00 sum. The BOM description requires the sheet to say: detach the cassette before wash, gloves, frequent check, offline lamp, three chambers as an unrated target, and no sterilization claim. That text is a BOM note, not an approved print. The RFQ shipping qualification has not been run. The protected pack and the adapter have no transport classification on file, and no shipment is authorized. Freight and duty are excluded on every bid, so there is no landed freight term. Payment terms on the bids are not a signed contract. The $58.67 piece is not a landed cost.

Result (Y/N/NA). N

Explanation. Instruction content is part of the packed unit because CTQ13 and CTQ16 are user-visible. An unprinted note is not a revision. Freight is unknown.

Status. Open — pack and freight undefined

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-08 description; CTQ13 and CTQ16; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 packaging field. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Sam Reed does not print the instruction. Jordan Vale marks cell transport and freight as exclusions. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The instruction text is a bill-of-materials note. Freight is excluded on the bids and is not a landed cost.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-RFQ-PACKAGE-001 Rev C1; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1

Mouse Hotel — Can each packed unit be traced to component lots and the assembly record?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-14

Question. Can each packed unit be traced to component lots and the assembly record?

Evidence to record. Shell lot, cell lot, PCB lot, sensor lot, firmware identity, device identity, traveler, and retain rule.

Answer / assumption. Not traceable. The control plan says: Planned unit IDs HOTEL-X1-001 onward; no results There is no lot code for the shell, the cell, the PCB, or the sensor, and no firmware hash. CTQ10 requires a unique device identity and that scheme is not defined. HOTEL-15 has no binary on file, so there is no image identity to record. PRODUCTION-07 still requires traceability before sale.

Result (Y/N/NA). N

Explanation. A connected unit without a firmware identity cannot be recalled to a bad flash. The traveler is blank, so the requirement is unmet.

Status. Open — traceability blank

Evidence / exact revision / URL and date. BMT-HOTEL-CONTROL-PLAN-001 Rev C1 HOTEL-X1-001; CTQ10; BMT-HOTEL-BOM-001 Rev C1 HOTEL-15. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale does not assign device identities and does not print serial labels. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Planned serials have no lot code, traveler, or retain.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONTROL-PLAN-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1

Mouse Hotel — Which open process failures block acceptance of a pilot lot?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-15

Question. Which open process failures block acceptance of a pilot lot?

Evidence to record. Each of PF01 through PF60, its RPN and severity, and the control that would have to catch it. None is accepted.

Answer / assumption. Do not accept a pilot lot. BMT-HOTEL-PFMEA-001 Rev C1 has 60 data rows, PF01 through PF60. Status is Open, Hold, or Blocked. No row is accepted. Severity 9 or 10 lines number 34. Highest lines, and the lines this sheet had been indexing short: PF12 RPN 320 severity 10 (Charge script missing the overtemperature cutoff; Blocked); PF09 RPN 432 severity 9 (Alert path checked only by a phone notification; Open); PF06 RPN 432 severity 9 (Window line closed with no pane check; Open); PF08 RPN 360 severity 9 (Beam left readable while the weight channel is unwired; Open); PF15 RPN 360 severity 9 (Host keep-out edited after the freeze; Hold); PF16 RPN 360 severity 9 (Divider left out of the kit; Blocked); PF02 RPN 252 severity 9 (Ribs clocked onto the floor of a chamber; Open); PF11 RPN 288 severity 9 (Single-bank image flashed; Open); PF13 RPN 315 severity 9 (Board left in the shell for a wash trial; Open); PF35 RPN 216 severity 9 (Beam and weight connectors swapped; Open); PF37 RPN 216 severity 9 (Lamp wired to the radio supply; Open); PF49 RPN 216 severity 9 (Divider seated in the wrong rib; Open). Those highlighted lines do not stand in for PF01 through PF60. Robin Keel has yet to approve a capacity and is not contacted. Robin Keel does not certify the trap. Controls are CP01 through CP20, draft. Latch is P05. Radio-integration hold is P18. CTQ01 through CTQ20 are untested. Tests T01 through T20 are unrun.

Result (Y/N/NA). Y

Explanation. The block is the open process FMEA, not a wish for more process steps. A pilot accepted now would skip stop and hold on the control plan. Alex Meadow has not authorized a restart. No build exists.

Status. Recorded — pilot lot refused

Evidence / exact revision / URL and date. BMT-HOTEL-PFMEA-001 Rev C1 PF01 through PF60, none accepted; CTQ01 through CTQ20; control plan CP01 through CP20. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale keeps the pilot quantity at zero while PF01 through PF60 stay unaccepted. Target 2027-02-15, planned.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. Open PFMEA rows stay unaccepted. A pilot lot is refused. RPN is unchanged.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-PFMEA-001 Rev C1; BMT-HOTEL-CONTROL-PLAN-001 Rev C1

Mouse Hotel — What has to be signed before an RFQ goes out or tool steel is cut?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-16

Question. What has to be signed before an RFQ goes out or tool steel is cut?

Evidence to record. NDA covering the shell and the radio concept, tool title and removal, change notice, payment, cancellation, expiry, gauge and FAI inclusions, warranty, scrap, and a line that a named shop is not qualified.

Answer / assumption. Nothing is signed. The RFQ says no agreement and no disclosure. Lane Corwin is not engaged. Perry Voss, Willa Marsh, and Eden Crowe have bids on file. No award and no purchase order. A later packet would also have to keep the unselected radio module and the unselected cell out of the supplier's scope until CTQ12 and CTQ15 move. Those sentences are not written. Steel is stopped under PRODUCTION-11.

Result (Y/N/NA). N

Explanation. Disclosure risk on this product includes the cassette, not only the shell geometry. The file stays in house.

Status. Blocked — terms and NDA unsigned

Evidence / exact revision / URL and date. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1 NDA field; CTQ12 and CTQ15; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1 Lane Corwin. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Jordan Vale holds the file and does not send the RFQ. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. No NDA, tool clause, or payment term is signed. The file stays in house.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-RFQ-PACKAGE-001 Rev C1; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — Is the three-chamber shell mold defined enough to cut the $30,000.00 tool?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-17

Question. Is the three-chamber shell mold defined enough to cut the $30,000.00 tool?

Evidence to record. Cavity count, tool life, T0 and T1, divider and baffle fit, who may release steel, and confirmation the allowance is already in the piece.

Answer / assumption. No. HOTEL-16 is the internal $30,000.00 shell allowance, outside the $60,000.00 ceiling, not ordered, and not a supplier bid. It is already amortized at $16.67 per unit at 600 units a year for 3 years. HOTEL-01 bids, unawarded: FSW-H-2026-01 (Fictional Sample Works, Perry Voss) dated 2026-09-19, valid through 2026-12-18, P20 steel mold, three chambers, 1 cavity, 300,000 shots, tooling $34,500.00, volume piece $7.35, annual qty 600, tool lead 16 weeks, tool owner: The Better Mouse Trap Co. when paid. MPS-H-2026-02 (Fictional Meadow Prototype Shop, Willa Marsh) dated 2026-09-23, valid through 2026-11-22, Aluminum bridge mold, three chambers, 1 cavity, 20,000 shots, tooling $14,800.00, volume piece $12.80, annual qty 200, tool lead 6 weeks, tool owner: Meadow Prototype Shop until buyout. NLM-H-2026-03 (Fictional Northline Molding, Eden Crowe) dated 2026-09-30, valid through 2026-12-29, Pre-hard mold, three chambers, 1 cavity, 150,000 shots, tooling $28,750.00, volume piece $8.45, annual qty 600, tool lead 13 weeks, tool owner: The Better Mouse Trap Co. before kickoff. DFM-02 says bridge process before a production tool at the 600-a-year cost case. DFM-03 has not had a mold-shop review accepted as a change. Three baffles, HOTEL-02 qty 3, extended line $3.00, are a separate fit. Dividers HOTEL-09 qty 2 are molded in the shell and are not a second tool. There is no accepted T0 or T1 plan. Alex Meadow is named on the BOM tooling note and has not released it. Sam Reed holds the shell lines on BOM C1. The 600 figure is a cost case, not demand.

Result (Y/N/NA). N

Explanation. Cutting steel would spend an allowance that is already inside the $58.67 piece and outside the $60,000.00 ceiling, and it would breach the stop-before-tooling rule. The supplier tools are different dollars and are unawarded. G1 has not moved.

Status. Blocked — mold not released to cut

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-16 allowance $30,000.00 outside the ceiling; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1 FSW-H-2026-01, MPS-H-2026-02, and NLM-H-2026-03, unawarded; DFM-02. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Do not cut steel. Sam Reed keeps HOTEL-16 as an allowance. Jordan Vale records that stop here. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The mold is an allowance. Steel is not released.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-CHECK-SHEET-DFM-001 Rev C1; BMT-HOTEL-TEMPLATE-QUOTE-COMPARISON-001 Rev C1

Mouse Hotel — What blocks a first production order even with shell bids on file?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. Suppliers and Production Readiness

Lead. Jordan Vale

Item ID. PRODUCTION-18

Question. What blocks a first production order even with shell bids on file?

Evidence to record. The PRODUCTION-08 release, the unsecured Hotel allowance, the open battery and radio limits, and the unrated capacity.

Answer / assumption. Not ready: no released drawings, supplier qualification, physical tests or reviewed controls. A shell quote is not an order for a connected unit. Independent blocks: G4 No purchase order, G3 No freeze, Hotel funding not secured, HOTEL-16 stopped, FAI Not measured, CP01 through CP20 draft on process steps P01 through P21, radio-integration hold at P18, CTQ12 pending with no named battery engineer, CTQ15 module unselected and no FCC ID invented, CTQ16 capacity not rated, PF09 RPN 432 and PF12 RPN 320 remain unaccepted, HOTEL-15 firmware image absent, Robin Keel has yet to approve multi-chamber use, no formed company, and no bank account.

Result (Y/N/NA). Y

Explanation. The feasibility gate can be prepared with this sheet and still not buy. G0 through G5 are pending. None has occurred. G0 is planned for 2027-01-28. This row is the record that the order was not placed.

Status. Recorded — order stays unplaced

Evidence / exact revision / URL and date. BMT-HOTEL-STAGE-GATES-001 Rev C1 G0, G3, G4; CTQ12, CTQ15, CTQ16; PF09 and PF12; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1. Dated 2026-10-24.

Owner. Jordan Vale

Next action. Leave the order unplaced. A shell quote does not authorize a connected build. Target 2027-02-15.

Reviewer / review date. Casey Holt review planned 2026-11-01, pending as of 2026-10-28, and not held. The blocks are independent. A later quote does not place the order.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1

Document administration

Scope. HOTEL-C1 supplier readiness for the three-chamber shell and the electronics cassette. Planned serials HOTEL-X1-001 through HOTEL-X1-010 are not built. Twenty-four dated bids, FSW-H-2026-01 through NLM-H-2026-24, are unawarded. No purchase order. The $30,000.00 shell allowance sits outside the $60,000.00 Hotel ceiling. The ceiling is unsecured. Packed estimate $58.67. Stop before production tooling. First production order is not placed. Hotel stays deferred until Basic evidence exists.

Preparation: Jordan Vale, scenario attribution, 2026-10-24. Signature: unsigned. Review: pending; no reviewer signature or date. Approval: withheld; no approver signature or date.

Prepared byDate
Reviewed byDate
Approved byDate