The Better Mouse Trap Co. / sample paperwork

Mouse Hotel — New product development: the project review

Mouse HotelRevision C12026-10-24Planning draft18 entries
Mouse Hotel — New product development: the project reviewBMT-HOTEL-CHECK-SHEET-PROJECT-001 · Rev C1
Company
The Better Mouse Trap Co.
Project / product line
Hotel trap
Document
Mouse Hotel — New product development: the project review
Document no.
BMT-HOTEL-CHECK-SHEET-PROJECT-001
Revision
C1
Status
Planning draft
Start date
2026-10-24
Revision date
2026-10-24
Prepared by / owner
Jordan Vale, Hotel electronics, HOTEL-C1
Checklist ID
BMT-HOTEL-CHECK-SHEET-PROJECT-001, Rev C1
Scope
HOTEL-C1 project review on BMT-HOTEL-CHECK-SHEET-PROJECT-001.
Reviewer
Casey Holt, Holt Sample Counsel (Planning draft read, not engaged)
Review date
2026-11-01
Team
Alex Meadow, packet owner; Jordan Vale, Hotel electronics; Sam Reed, mechanical reference; Robin Keel, animal-welfare reviewer
Approved by
review pending. Alex Meadow, Planning draft C1, has not signed. The $60,000.00 Hotel allowance is not drawn.
Mouse Hotel — New Product Development: The Project Review
Item / review questionAnswer / findingResult / statusEvidenceResponsibility / action

Item ID: PROJECT-01

Question: Who will use it, who pays, and what problem is worth solving?

Answer / assumption: Segment on BMT-HOTEL-MARKET-CHECK-001 Rev C1: small-property managers. Task as drawn: see occupancy in three chambers without opening the unit, including when the network is down. Alternatives on the panel: service contracts and staff checks, plus exclusion. BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 holds 16 rows from 2026-08-04 through 2026-10-22. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 counts eight Grade B problem interviews. Ruth Penner (ME-H-01) pays a service at $85.00 a visit, about six visits a year, $510.00, and would trial one unit at $129.00 if inspection stays manual. Chris Dalloway (ME-H-02) would glance during a room pass, would not carry an occupied trap through the lobby, and stated Not applicable — no transaction in this planning record. Omar Lind (ME-H-03) named $129.00, then $90.00 after he was told the room check still happens. Etta Varn (ME-H-04) kept a $1,200.00 contract and refused to add $129.00. Switching off the service is not observed. The 20-interview gate is not met. Company decision 2026-08-16 still defers Hotel tooling until Basic evidence exists and action A03 is closed. The 5-store hardware path and Morgan Hale belong to the Basic channel plan. They are not Hotel accounts. These manager notes are not Basic homeowner notes.

Explanation: Eight Grade B notes separate some payers from the person on the night round. They are not a contract and not a site list. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 records the same 8 of 20 count. An alert request is not a served market. The 2026-08-16 deferral blocks tooling. It does not erase the register.

Result (Y/N/NA): N

Status: Open — 8 of 20 problem interviews

BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001, ME-H-01 through ME-H-16, 2026-08-04 through 2026-10-22; BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01; BMT-HOTEL-MARKET-CHECK-001 Rev C1;

Owner: Alex Meadow

Next action: File the remaining problem interviews. Record property size, who checks, last method, minutes, and dollars. Do not infer switching from an alert request, and do not treat Basic homeowner notes as Hotel evidence. Do not start a pilot. Target 2027-02-15. The 2026-11-15 session has not been held, and Hotel spend is not on that agenda.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-01 remains open on the interview count.

Item ID: PROJECT-02

Question: What are we making, and what is outside the first version?

Answer / assumption: Mouse Hotel C1: three isolated proposed chambers, Wi-Fi and Bluetooth, local and app occupancy alerts. Not a rated capacity. CTQ16 says capacity is not rated and needs a welfare specialist before any animal count is claimed. Out of C1: disease-control claims, child use, export, poison, a certified-humane claim, an FCC ID, a UL or UN 38.3 pass, and any Drone function. Capsule-style limits CTQ01 through CTQ06 still apply, including manual visibility of occupancy. Added limits CTQ07 through CTQ16 cover the baffle, the sensor, the alert queue, pairing, firmware, the pack, wash versus electronics, privacy, the radio, and crowding. Envelope and mass are not released as a quote drawing. Success criteria are those CTQs. None have results.

Explanation: Three chambers is a concept count. It is not a promise that three animals can be held. IP-02, compartment occupancy fusion and offline indication, is the believed novelty and is unvalidated.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ07 through CTQ16; BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1 IP-02; BMT-HOTEL-REGULATORY-SCREENING-001 Rev

Owner: Jordan Vale

Next action: Keep capacity unrated. Do not issue an app claim or a chamber-count claim. Target 2027-02-15 for a paper scope check only.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-02 Estimate only.

Item ID: PROJECT-03

Question: How many might we sell, at what price, through which channel and by when?

Answer / assumption: Costing volumes only: low/base/high 300/600/1,200 units a year. Not a forecast and not a build schedule. Hold price $129.00. Hardware sell-in assumption $70.95. Fee assumptions, not schedules: own website 3%, Amazon merchant fulfillment 15%. The company channel order (website, then 5 hardware stores, then Amazon merchant fulfillment) is not opened for Hotel. FBA, Walmart, home-center, and export are unchosen or excluded. No account is open. Company downside books Not applicable — no transaction in this planning record Hotel units and Not applicable — no transaction in this planning record Hotel development spend. Schedule G5 2027-06-28, owner Jordan Vale, is Not occurred and is not a ship date. Hardware wholesale contribution at the base illustration is negative, so that channel is not a plan.

Explanation: There is no prospect count and no units-per-store figure, because no store is selected. Using 600 units to amortize tooling does not create a property-manager pipeline.

Result (Y/N/NA): N

Status: estimate — unvalidated

BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-01, ECONOMICS-02, and ECONOMICS-06; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1

Owner: Alex Meadow

Next action: Keep 300/600/1,200 labeled as cost sensitivity. Do not load Hotel units into the cash forecast. Look again 2027-02-15 only as a paper review.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-03 Estimate only.

Item ID: PROJECT-04

Question: What evidence says someone will buy it?

Answer / assumption: BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 is not an empty file. It holds 16 rows from 2026-08-04 through 2026-10-22, the register BMT-HOTEL-CHECK-SHEET-LAUNCH-001 cites. Eight Grade B problem interviews are filed. Grade A cards, not checkout: Cleo Abbott (ME-H-06) chose $129.00 over $99.00 and $159.00; Harris Boone (ME-H-07) chose $99.00 and refused $129.00; Dana Crowe (ME-H-08) chose $109.65; Felix Marr (ME-H-09) chose one case, 6 times $116.00, which is $696.00. Victor Lang (ME-H-13) would consider $129.00 once and stated a monthly fee of Not applicable — no transaction in this planning record. Ben Arkell (ME-H-15) stated an invoice of $70.95. Letters of intent: 0. Paid orders: 0. Repeat sites: 0. The $129.00 figure is a hold price, not an offer. The $6.00 cloud figure is a reserve, not a fee anyone accepted. BMT-HOTEL-LAUNCH-WORKSHEET-001 Rev C1 has no listing and no GTIN. Decision 2026-09-13 keeps listings off. No pilot property is named. BMT-COMPANY-TEMPLATE-SPENDING-REGISTER-001 shows Not applicable — no transaction in this planning record paid and Not applicable — no transaction in this planning record committed. The $60,000.00 Hotel allowance is not the source of these notes and is not drawn.

Explanation: A marked card is interest, not an order. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-02 records the same cards and no checkout. The 2026-08-16 deferral still blocks Hotel tooling. It does not authorize writing an empty file over the 16 rows. Interview spend from the Hotel allowance is not released.

Result (Y/N/NA): N

Status: Open — 8 interviews filed, orders at 0

BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 ME-H-01 through ME-H-16; BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 and LAUNCH-02; BMT-HOTEL-MARKET-CHECK-001 Rev C1;

Owner: Alex Meadow

Next action: Do not open a listing and do not offer a pilot site. Do not replace the 16-row register with an empty file. Target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-04 remains open. Paid orders stay at 0.

Item ID: PROJECT-05

Question: What must be learned before the next investment?

Answer / assumption: No Hotel investment is authorized. Worksheet allowance $60,000.00 (rig $24,000.00; testing and welfare $18,000.00; engineering and market $12,000.00; reserve $6,000.00) stops before production tooling and is not secured. It sits outside the $80,000. Downside cash includes Not applicable — no transaction in this planning record of it. Learning that would have to precede any later consent: surrogate proof that a second animal cannot back-drive the baffle (CTQ07, 2 N), that the sensor does not report false-empty (CTQ08, 100 placements including dust, zero false-empty), and that local occupancy still shows when the network is down (CTQ09, app marks offline within the proposed 5 minutes). Finish: results filed or an explicit fail. Owner: Jordan Vale. Gate in front of that work: Basic latch and vent evidence, plus A03 closed (due 2026-12-15). Neither is done.

Explanation: Quoting $60,000.00 as the next round would contradict BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1. The BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 is a parked worksheet. Nothing is committed.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 unfunded-lines row; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; CTQ07, CTQ08, CTQ09;

Owner: Jordan Vale

Next action: Do not buy a sensor, a pack, or a radio. Write the surrogate method only. Target 2027-02-15, and do not start it before A03 and the Basic evidence exist.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-05 Estimate only.

Item ID: PROJECT-06

Question: What are the milestones and dependencies?

Answer / assumption: BMT-HOTEL-STAGE-GATES-001 Rev C1: G0 private planning only; G1 hold tooling; G2 hold external use; G3 no freeze; G4 no purchase order; G5 no launch. BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1, owner Jordan Vale, status Not occurred: G0 2027-01-28, G1 2027-02-28, G2 2027-03-28, G3 2027-04-28, G4 2027-05-28, G5 2027-06-28. Those dates are unfilled forecasts. Company decision 2026-08-16 defers the product until Basic evidence exists and A03 (due 2026-12-15) is closed. A February 2027 G1 on the calendar does not release the $60,000.00 allowance. Welfare review for three chambers is not scheduled, because Robin Keel has not been asked.

Explanation: Passing Basic G1 would not automatically pass Hotel G1. The baffle, the sensor, the pack, and the radio are additional blockers. The schedule owner is Jordan Vale. The spend owner remains Alex Meadow, and no consent is written.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; action A03.

Owner: Jordan Vale

Next action: Leave actual dates Not occurred. Do not slip the forecast to imply progress. Paper check target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-06 Estimate only.

Item ID: PROJECT-07

Question: Who owns each result and decision?

Answer / assumption: Alex Meadow owns budgets and the deferral. Jordan Vale is the planned electrical and software lead, not engaged and not paid, and would own sensor, radio, firmware, and pack evidence if later engaged. Sam Reed owns Basic mechanical evidence and does not release Hotel drawings to the Basic tooling candidates. Robin Keel would have to approve any multi-chamber welfare question and has not been contacted. Lane Corwin has not cleared an NDA. Nia Calder has not said whether lithium is inside the illustrative liability figure. Ira Bell is a Basic dry-cycle candidate, not a Hotel lab. No appointment is signed.

Explanation: A named lead is not an engagement and not a design release. Contractors cannot spend or speak for the company.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-HOTEL-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; action A03; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16.

Owner: Alex Meadow

Next action: Do not issue an engagement for Hotel work. Keep Jordan Vale on the A03 regulatory note only, due 2026-12-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-07 Estimate only.

Item ID: PROJECT-08

Question: Should we go, revise, hold or stop?

Answer / assumption: Recommendation, not a signature: defer. Do not go to tooling, a pilot property, a listing, or a sale. Hold the concept as paperwork. Revise before any spend if the hardware channel remains the intended path, because base-case hardware contribution is negative. Stop the commercial path if welfare evidence on crowding or false-empty is unacceptable, or if the only viable channel contributes less than zero. Unresolved: CTQ07 through CTQ16 untested; DF12 battery severity 10 open; FCC, battery, and privacy rows uncleared; allowance unsecured; Basic evidence not yet in hand. Authorized next work: none that spends money. A03 may be written. A purchase may not.

Explanation: BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16 already defers Hotel. This row records that the deferral still stands on 2026-10-24. It does not reopen the $60,000.00 worksheet.

Result (Y/N/NA): N

Status: estimate — unvalidated

BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-06; BMT-HOTEL-DFMEA-001 Rev C1 DF12; BMT-HOTEL-REGULATORY-SCREENING-001

Owner: Alex Meadow

Next action: Leave the deferral in force. Do not add Hotel spend to the 2026-11-15 Basic agenda. Paper target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-08 Estimate only.

Item ID: PROJECT-09

Question: Which requirements and critical characteristics gate any future spend?

Answer / assumption: CTQ01 through CTQ16 are proposed, review pending. Inherited limits: CTQ01 100 dry cycles on each of 10 units; CTQ02 two vent paths; CTQ03 30 mm finger clearance; CTQ04 wash of 10 units; CTQ05 20 N bait pull; CTQ06 occupancy visible without opening. Hotel-specific: CTQ07 baffle holds 2 N against back-drive, three compartments proposed; CTQ08 zero false-empty in 100 placements including dust; CTQ09 local indicator works with no network, app marks offline within a proposed 5 minutes; CTQ10 physical-button provisioning, unauthorized client denied in 50 attempts; CTQ11 capture and local indication survive a power cut during update; CTQ12 no wet charging, proposed 45 C cell-surface cutoff; CTQ13 electronics out before wash, power inhibited when the cassette is unseated; CTQ14 no precise location, proposed 30-day retention; CTQ15 no FCC ID invented; CTQ16 capacity not rated. Tests T01 through T16 and BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP16 are prototype indexes. Results: zero.

Explanation: A false-empty sensor (CTQ08) and a missed alert (CTQ09) are safety-critical because the animal is hidden inside a multi-chamber box. They are not convenience features. No gauge is bought.

Result (Y/N/NA): N

Status: open

BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ16; BMT-HOTEL-TEST-PLAN-001 Rev C1 T01 through T16; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP16.

Owner: Jordan Vale

Next action: Leave the results file empty. Do not prototype the radio or the pack. Paper cross-check target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-09 Open.

Item ID: PROJECT-10

Question: Which open failure chains can stop the project, and what RPN is still open?

Answer / assumption: Hotel BMT-HOTEL-DFMEA-001 Rev C1 has 16 scored rows. Open RPN sum is 4,803. Severity split: 1 at S10, 9 at S9, 4 at S8, 2 at S7. Highest open RPNs: DF09 alert never arrives 432 (S9 O6 D8, projected 216); DF06 occupancy unchecked 432 (S9 O6 D8, projected 216); DF08 false empty 360 (S9 O5 D8, projected 162); DF15 radio host change 360 (S9 O5 D8, projected 162); DF16 animals crowded 360 (S9 O5 D8, projected 162); DF12 battery overheats 320 (S10 O4 D8, projected 120). BMT-HOTEL-RISK-PRIORITY-001 Rev C1 order follows projected RPN and still places DF12 inside the review list at projected 120. Projected figures are not demonstrated. The single severity-10 row and all nine severity-9 rows stay open regardless of rank. PF01 through PF16 mirror the requirements. No action is closed.

Explanation: DF12 can look smaller than DF09 on projected RPN and still stop the project, because severity is 10 and no cell, charger, or certification result exists.

Result (Y/N/NA): Y

Status: open

BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-RISK-PRIORITY-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1 PF01 through PF16.

Owner: Jordan Vale

Next action: Keep DF12, DF09, DF08, and DF16 open ahead of any tooling talk. Do not accept projected RPN as residual evidence. Target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-10 Open.

Item ID: PROJECT-11

Question: What does one illustrated unit cost, and what contribution remains by channel?

Answer / assumption: Held piece on the BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 is $58.67 at 600 units a year for 3 years. BMT-HOTEL-SENSITIVITY-001 Rev C1 prints low $75.33, base $58.67, high $50.33. Tooling cash $30,000.00 in each column, not committed. BMT-HOTEL-BOM-001 Rev C1 piece content HOTEL-01 through HOTEL-08 sums to $40.00 before amortization and other sheet adjustments: shell $8.00, baffles $1.00, sensor array $6.00, radio cassette $10.00, protected battery $6.00, charger and cable $4.00, assembly and flashing $3.00, carton $2.00. ECONOMICS-06 contributions at the base illustration: own website $45.01; hardware wholesale -$3.17; Amazon merchant fulfillment $26.53. Product-sheet allocated annual fixed cost $30,000.00. That allocation is not in the company downside. Company Hotel spend is Not applicable — no transaction in this planning record. No line has a supplier quote.

Explanation: Negative hardware contribution means the stated 5-store path does not clear the illustrated cost. A positive website contribution is not collected cash. The deferral stands even if a later price change repairs the hardware math.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 piece $58.67; BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001

Owner: Alex Meadow

Next action: Do not load $30,000.00 tooling into the company cash sheet. Do not offer $70.95 sell-in to a store. Paper review target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-11 Estimate only.

Item ID: PROJECT-12

Question: What cash is planned for this product, and what allowance is excluded?

Answer / assumption: No Hotel cash is planned. The $60,000.00 worksheet allowance is not secured. Split if it were ever authorized: rig $24,000.00; testing and welfare $18,000.00; engineering and market $12,000.00; reserve $6,000.00. Stop before production tooling. It is outside the $80,000. Downside closes from January $72,000.00 to December $17,000.00 include no Hotel development. November is the $20,000.00 floor. December is $3,000.00 under the floor and is not spare cash for this product. Debt Not applicable — no transaction in this planning record. No investor and no lender. The Basic cap reconciliation in action A12 did not move money to Hotel.

Explanation: A reader of the BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 alone can mistake $60,000.00 for a round. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 row 14 controls. The allowance stays parked until Basic evidence exists and A03 is closed.

Result (Y/N/NA): Y

Status: estimate — unvalidated

BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1, unfunded-lines and cash-downside rows; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; action A12; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Owner: Alex Meadow

Next action: Do not request a release against the $60,000.00 figure. Leave it off the 2026-11-15 spend agenda.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-12 Estimate only.

Item ID: PROJECT-13

Question: What is believed to be new, who owns it, and what has already been disclosed?

Answer / assumption: Believed new, unvalidated (IP-02): compartment occupancy fusion and offline state indication. Contributors, assignments unsigned: Alex Meadow concept; Sam Reed mechanism; Jordan Vale electronics and flight where used. Disclosure history: no external disclosure, no sale, no offer. Route: private BMT-HOTEL-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1 and a search plan. Provisional filing not chosen. Trademark unsearched. Freedom-to-operate review not performed, including for the radio and the app behavior. A later patent would not create an FCC grant and would not clear third-party sensor or radio rights. Drawings stay withheld from Perry Voss and Willa Marsh. Those contacts are Basic candidates and are not cleared for Hotel files.

Explanation: IP-08 asks for counsel review before disclosure. Lane Corwin has not been engaged. No opinion exists.

Result (Y/N/NA): N

Status: open

BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1 IP-02 through IP-08; BMT-HOTEL-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1, Perry Voss and Willa Marsh.

Owner: Jordan Vale

Next action: Send no schematic and no app description outside the file. Do not file. Paper target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-13 Open.

Item ID: PROJECT-14

Question: Which regulatory questions are open, and which claims are refused?

Answer / assumption: Seven regimes on BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1, none cleared. CPSC: No CPC claimed; not a children's product. EPA and state device: No EPA approval or registration claim. Animal release: No destination approved. Materials and claims: no poison, no medical claim, no certified-humane claim. FCC: No FCC ID or authorization exists. Electrical and battery: No UL, NRTL, IP, or UN 38.3 pass claimed. Privacy and security: No privacy certification asserted. CTQ14 proposes no precise location and a 30-day retention idea. That proposal is not a privacy program. CTQ15 forbids inventing an FCC ID. Jordan Vale carries the connected-product scope on action A03, due 2026-12-15.

Explanation: Alert copy, chamber-count copy, and humane copy are all claims. None have evidence, so none can be drafted as statements of performance.

Result (Y/N/NA): Y

Status: open

BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1; CTQ14 and CTQ15; action A03; BMT-HOTEL-INSTRUCTIONS-AND-WARNINGS-001 Rev C1 not issued.

Owner: Jordan Vale

Next action: Keep disease, humane, and capacity wording off drafts. Leave A03 open if the source review is unfinished. Due 2026-12-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-14 Open.

Item ID: PROJECT-15

Question: Who could build the unit, and which purchases are forbidden now?

Answer / assumption: BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08, candidate not selected, no quote. Extended unit figures on the BMT-HOTEL-BOM-001 Rev C1: three-chamber shell $8.00; entry baffles and latches $1.00; sensor array $6.00; radio and controller cassette $10.00; protected battery $6.00; charger and cable $4.00; assembly and flashing $3.00; carton and instructions $2.00. Tooling cash on the BMT-HOTEL-SENSITIVITY-001 Rev C1 is $30,000.00 and is not a purchase. Perry Voss at Fictional Sample Works and Willa Marsh at Meadow Prototype Shop are Basic candidates only. They are not cleared for Hotel drawings. No RFQ, no NDA, and no purchase order. G4 text is No purchase order.

Explanation: Flashing labor on HOTEL-07 does not mean firmware exists. The firmware-update failure DF11 is still open at RPN 288, projected 108, severity 9.

Result (Y/N/NA): N

Status: blocked

BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08; BMT-HOTEL-SENSITIVITY-001 Rev C1 tooling column; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1 DF11.

Owner: Jordan Vale

Next action: Do not send Hotel drawings to the Basic shops. Do not request a tool quote. Paper target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-15 Blocked.

Item ID: PROJECT-16

Question: What test and welfare evidence exists, and what trial is forbidden?

Answer / assumption: T01 through T16 index CTQ01 through CTQ16. Methods are proposed. Nothing has been bought and nothing has been run. Result count is zero. Live animals are forbidden. A multi-chamber occupied trial is forbidden. Robin Keel has not set a check interval and has yet to approve a three-chamber welfare question. CTQ16 states capacity is not rated. False-empty and missed-alert trials, when they are someday allowed, are surrogate trials. Ira Bell is not engaged. Instructions that would tell a manager how often to check are not issued.

Explanation: Basic door and vent proofs, even if they later pass, do not cover DF08, DF09, DF12, or DF16. Those four are the Hotel blockers for any external placement.

Result (Y/N/NA): N

Status: blocked

BMT-HOTEL-TEST-PLAN-001 Rev C1 T01 through T16; BMT-HOTEL-TEMPLATE-TEST-RESULTS-001 Rev C1 empty; CTQ16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Robin Keel; action pattern A06.

Owner: Jordan Vale

Next action: Do not place a unit in a property and do not run a live or multi-animal trial. Keep the welfare ask unsent. Paper target 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-16 Blocked.

Item ID: PROJECT-17

Question: Which company controls block a pilot placement?

Answer / assumption: The LLC is not formed. No EIN and no account. Ellis Brook is not contacted and credit is not requested. Nia Calder has not said whether lithium is excluded from the illustrative $2,000,000.00 liability figure. No policy is bound. The $600.00 monthly insurance line is a reserve, not a premium. Lot trace, complaint log, and recall note are empty (Basic action A14, due 2026-12-01) and would be required before any Hotel pilot unit as well. No employee. Rowan Pell has not confirmed tax treatment. A property placement is a distribution event for recall purposes and is not authorized.

Explanation: G5 names insurance, buyer terms, and recall readiness. All three are open. The deferral means they are not being solved with Hotel spend.

Result (Y/N/NA): N

Status: blocked

BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; action A14; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Nia Calder, Ellis Brook, Rowan Pell.

Owner: Alex Meadow

Next action: Do not ask the broker to bind a Hotel lithium risk from this sample. Formation sequence stays ahead of any account. Broker date 2026-12-01.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-17 Blocked.

Item ID: PROJECT-18

Question: What is frozen, and which records must move when an input changes?

Answer / assumption: Nothing is frozen. This review is sheet revision 1, Planning draft, 2026-10-24. No Hotel design ECN has released a change. Records that move together: CTQ01 through CTQ16, BMT-HOTEL-DFMEA-001 Rev C1 and BMT-HOTEL-PFMEA-001 Rev C1, CP01 through CP16, T01 through T16, BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08, the $58.67 piece, BMT-HOTEL-SENSITIVITY-001 Rev C1 volumes, the unsecured $60,000.00 allowance, and the FCC, battery, and privacy screening rows. A chamber-count change would also move CTQ16, DF16, the welfare ask, and any claim sentence. Paid orders stay at 0. The 16-row register on BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 remains the customer record. A later company decision would have to withdraw the 2026-08-16 deferral before that register becomes a launch file.

Explanation: Schedule dates are unfilled forecasts owned by Jordan Vale. Editing a forecast without a decision would make G1 look active while spend is still refused.

Result (Y/N/NA): Y

Status: open

this sheet revision 1, 2026-10-24; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 piece $58.67; BMT-HOTEL-DFMEA-001 Rev C1.

Owner: Jordan Vale

Next action: Do not open a design ECN to add a chamber or a radio change. Next paper look 2027-02-15.

Reviewer / review date: Casey Holt, planned 2026-11-01, not held. PROJECT-18 Open.

Mouse Hotel — New Product Development: The Project Review — supporting detail

Mouse Hotel — Who will use it, who pays, and what problem is worth solving?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-01

Question. Who will use it, who pays, and what problem is worth solving?

Evidence to record. Name the user, buyer, task, alternatives and evidence from actual conversations. Separate founder beliefs from observations. State whether this buyer is inside the authorized cash plan.

Answer / assumption. Segment on BMT-HOTEL-MARKET-CHECK-001 Rev C1: small-property managers. Task as drawn: see occupancy in three chambers without opening the unit, including when the network is down. Alternatives on the panel: service contracts and staff checks, plus exclusion. BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 holds 16 rows from 2026-08-04 through 2026-10-22. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 counts eight Grade B problem interviews. Ruth Penner (ME-H-01) pays a service at $85.00 a visit, about six visits a year, $510.00, and would trial one unit at $129.00 if inspection stays manual. Chris Dalloway (ME-H-02) would glance during a room pass, would not carry an occupied trap through the lobby, and stated Not applicable — no transaction in this planning record. Omar Lind (ME-H-03) named $129.00, then $90.00 after he was told the room check still happens. Etta Varn (ME-H-04) kept a $1,200.00 contract and refused to add $129.00. Switching off the service is not observed. The 20-interview gate is not met. Company decision 2026-08-16 still defers Hotel tooling until Basic evidence exists and action A03 is closed. The 5-store hardware path and Morgan Hale belong to the Basic channel plan. They are not Hotel accounts. These manager notes are not Basic homeowner notes.

Result (Y/N/NA). N

Explanation. Eight Grade B notes separate some payers from the person on the night round. They are not a contract and not a site list. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 records the same 8 of 20 count. An alert request is not a served market. The 2026-08-16 deferral blocks tooling. It does not erase the register.

Status. Open — 8 of 20 problem interviews

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001, ME-H-01 through ME-H-16, 2026-08-04 through 2026-10-22; BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01; BMT-HOTEL-MARKET-CHECK-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16.

Owner. Alex Meadow

Next action. File the remaining problem interviews. Record property size, who checks, last method, minutes, and dollars. Do not infer switching from an alert request, and do not treat Basic homeowner notes as Hotel evidence. Do not start a pilot. Target 2027-02-15. The 2026-11-15 session has not been held, and Hotel spend is not on that agenda.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-01 remains open on the interview count.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-MARKET-CHECK-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1

Mouse Hotel — What are we making, and what is outside the first version?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-02

Question. What are we making, and what is outside the first version?

Evidence to record. Concept revision, intended use, must-have outcomes, exclusions and measurable success criteria where known.

Answer / assumption. Mouse Hotel C1: three isolated proposed chambers, Wi-Fi and Bluetooth, local and app occupancy alerts. Not a rated capacity. CTQ16 says capacity is not rated and needs a welfare specialist before any animal count is claimed. Out of C1: disease-control claims, child use, export, poison, a certified-humane claim, an FCC ID, a UL or UN 38.3 pass, and any Drone function. Capsule-style limits CTQ01 through CTQ06 still apply, including manual visibility of occupancy. Added limits CTQ07 through CTQ16 cover the baffle, the sensor, the alert queue, pairing, firmware, the pack, wash versus electronics, privacy, the radio, and crowding. Envelope and mass are not released as a quote drawing. Success criteria are those CTQs. None have results.

Result (Y/N/NA). Y

Explanation. Three chambers is a concept count. It is not a promise that three animals can be held. IP-02, compartment occupancy fusion and offline indication, is the believed novelty and is unvalidated.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ07 through CTQ16; BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1 IP-02; BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1.

Owner. Jordan Vale

Next action. Keep capacity unrated. Do not issue an app claim or a chamber-count claim. Target 2027-02-15 for a paper scope check only.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-02 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CONCEPT-DRAWING-001 Rev C1; BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1; BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1

Mouse Hotel — How many might we sell, at what price, through which channel and by when?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-03

Question. How many might we sell, at what price, through which channel and by when?

Evidence to record. Low/base/high units by month or quarter, geography and channel. Show prospects × purchase rate × units or stores × units per store per week × weeks. Record assumptions and capacity limits; market size is not a sales forecast. Separate costing volume from the company cash case.

Result (Y/N/NA). N

Explanation. There is no prospect count and no units-per-store figure, because no store is selected. Using 600 units to amortize tooling does not create a property-manager pipeline.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-01, ECONOMICS-02, and ECONOMICS-06; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 commercial-evidence line; BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1.

Owner. Alex Meadow

Next action. Keep 300/600/1,200 labeled as cost sensitivity. Do not load Hotel units into the cash forecast. Look again 2027-02-15 only as a paper review.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-03 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1

Mouse Hotel — What evidence says someone will buy it?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-04

Question. What evidence says someone will buy it?

Evidence to record. Dated interviews, observed problems, price tests, pilots, orders or other evidence. Distinguish interest, nonbinding intent, paid orders and repeat sales.

Result (Y/N/NA). N

Explanation. A marked card is interest, not an order. BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-02 records the same cards and no checkout. The 2026-08-16 deferral still blocks Hotel tooling. It does not authorize writing an empty file over the 16 rows. Interview spend from the Hotel allowance is not released.

Status. Open — 8 interviews filed, orders at 0

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 ME-H-01 through ME-H-16; BMT-HOTEL-CHECK-SHEET-LAUNCH-001 LAUNCH-01 and LAUNCH-02; BMT-HOTEL-MARKET-CHECK-001 Rev C1; BMT-HOTEL-LAUNCH-WORKSHEET-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-09-13.

Owner. Alex Meadow

Next action. Do not open a listing and do not offer a pilot site. Do not replace the 16-row register with an empty file. Target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-04 remains open. Paid orders stay at 0.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-MARKET-CHECK-001 Rev C1; BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 Rev C1; BMT-HOTEL-LAUNCH-WORKSHEET-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Mouse Hotel — What must be learned before the next investment?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-05

Question. What must be learned before the next investment?

Evidence to record. Open customer, IP, safety, technical, cost and channel risks; one next experiment, owner, finish condition and capped budget. Separate the worksheet allowance from cash the company has set aside.

Result (Y/N/NA). Y

Explanation. Quoting $60,000.00 as the next round would contradict BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1. The BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 is a parked worksheet. Nothing is committed.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 unfunded-lines row; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; CTQ07, CTQ08, CTQ09; action A03.

Owner. Jordan Vale

Next action. Do not buy a sensor, a pack, or a radio. Write the surrogate method only. Target 2027-02-15, and do not start it before A03 and the Basic evidence exist.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-05 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Mouse Hotel — What are the milestones and dependencies?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-06

Question. What are the milestones and dependencies?

Evidence to record. Concept review → feasibility and economics → prototype/user evidence → production readiness → launch → post-launch review. Tailor the sequence; do not imply every gate is already passed.

Answer / assumption. BMT-HOTEL-STAGE-GATES-001 Rev C1: G0 private planning only; G1 hold tooling; G2 hold external use; G3 no freeze; G4 no purchase order; G5 no launch. BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1, owner Jordan Vale, status Not occurred: G0 2027-01-28, G1 2027-02-28, G2 2027-03-28, G3 2027-04-28, G4 2027-05-28, G5 2027-06-28. Those dates are unfilled forecasts. Company decision 2026-08-16 defers the product until Basic evidence exists and A03 (due 2026-12-15) is closed. A February 2027 G1 on the calendar does not release the $60,000.00 allowance. Welfare review for three chambers is not scheduled, because Robin Keel has not been asked.

Result (Y/N/NA). Y

Explanation. Passing Basic G1 would not automatically pass Hotel G1. The baffle, the sensor, the pack, and the radio are additional blockers. The schedule owner is Jordan Vale. The spend owner remains Alex Meadow, and no consent is written.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; action A03.

Owner. Jordan Vale

Next action. Leave actual dates Not occurred. Do not slip the forecast to imply progress. Paper check target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-06 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-STAGE-GATES-001 Rev C1; BMT-HOTEL-TEMPLATE-SCHEDULE-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Mouse Hotel — Who owns each result and decision?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-07

Question. Who owns each result and decision?

Evidence to record. Named responsible people/assistants, exact inputs and revisions, agreed review participants and dates only when agreed.

Answer / assumption. Alex Meadow owns budgets and the deferral. Jordan Vale is the planned electrical and software lead, not engaged and not paid, and would own sensor, radio, firmware, and pack evidence if later engaged. Sam Reed owns Basic mechanical evidence and does not release Hotel drawings to the Basic tooling candidates. Robin Keel would have to approve any multi-chamber welfare question and has not been contacted. Lane Corwin has not cleared an NDA. Nia Calder has not said whether lithium is inside the illustrative liability figure. Ira Bell is a Basic dry-cycle candidate, not a Hotel lab. No appointment is signed.

Result (Y/N/NA). Y

Explanation. A named lead is not an engagement and not a design release. Contractors cannot spend or speak for the company.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-HOTEL-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; action A03; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16.

Owner. Alex Meadow

Next action. Do not issue an engagement for Hotel work. Keep Jordan Vale on the A03 regulatory note only, due 2026-12-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-07 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1; BMT-HOTEL-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Mouse Hotel — Should we go, revise, hold or stop?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-08

Question. Should we go, revise, hold or stop?

Evidence to record. Evidence reviewed, decision author/date, unresolved conditions, authorized next work and links to the exact released files. Revisit downstream sheets when an input changes.

Answer / assumption. Recommendation, not a signature: defer. Do not go to tooling, a pilot property, a listing, or a sale. Hold the concept as paperwork. Revise before any spend if the hardware channel remains the intended path, because base-case hardware contribution is negative. Stop the commercial path if welfare evidence on crowding or false-empty is unacceptable, or if the only viable channel contributes less than zero. Unresolved: CTQ07 through CTQ16 untested; DF12 battery severity 10 open; FCC, battery, and privacy rows uncleared; allowance unsecured; Basic evidence not yet in hand. Authorized next work: none that spends money. A03 may be written. A purchase may not.

Result (Y/N/NA). N

Explanation. BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16 already defers Hotel. This row records that the deferral still stands on 2026-10-24. It does not reopen the $60,000.00 worksheet.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-06; BMT-HOTEL-DFMEA-001 Rev C1 DF12; BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1.

Owner. Alex Meadow

Next action. Leave the deferral in force. Do not add Hotel spend to the 2026-11-15 Basic agenda. Paper target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-08 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1

Mouse Hotel — Which requirements and critical characteristics gate any future spend?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-09

Question. Which requirements and critical characteristics gate any future spend?

Evidence to record. Requirement ID, CTQ ID, criticality, acceptance limit, linked test, control-plan row, and result count.

Answer / assumption. CTQ01 through CTQ16 are proposed, review pending. Inherited limits: CTQ01 100 dry cycles on each of 10 units; CTQ02 two vent paths; CTQ03 30 mm finger clearance; CTQ04 wash of 10 units; CTQ05 20 N bait pull; CTQ06 occupancy visible without opening. Hotel-specific: CTQ07 baffle holds 2 N against back-drive, three compartments proposed; CTQ08 zero false-empty in 100 placements including dust; CTQ09 local indicator works with no network, app marks offline within a proposed 5 minutes; CTQ10 physical-button provisioning, unauthorized client denied in 50 attempts; CTQ11 capture and local indication survive a power cut during update; CTQ12 no wet charging, proposed 45 C cell-surface cutoff; CTQ13 electronics out before wash, power inhibited when the cassette is unseated; CTQ14 no precise location, proposed 30-day retention; CTQ15 no FCC ID invented; CTQ16 capacity not rated. Tests T01 through T16 and BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP16 are prototype indexes. Results: zero.

Result (Y/N/NA). N

Explanation. A false-empty sensor (CTQ08) and a missed alert (CTQ09) are safety-critical because the animal is hidden inside a multi-chamber box. They are not convenience features. No gauge is bought.

Status. open

Evidence / exact revision / URL and date. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1 CTQ01 through CTQ16; BMT-HOTEL-TEST-PLAN-001 Rev C1 T01 through T16; BMT-HOTEL-CONTROL-PLAN-001 Rev C1 CP01 through CP16.

Owner. Jordan Vale

Next action. Leave the results file empty. Do not prototype the radio or the pack. Paper cross-check target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-09 Open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CRITICAL-QUALITY-001 Rev C1; BMT-HOTEL-TEST-PLAN-001 Rev C1; BMT-HOTEL-CONTROL-PLAN-001 Rev C1

Mouse Hotel — Which open failure chains can stop the project, and what RPN is still open?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-10

Question. Which open failure chains can stop the project, and what RPN is still open?

Evidence to record. Design and process FMEA ID, severity, occurrence, detection, RPN, projected RPN, and the severity-10 rule. Use RPN.

Answer / assumption. Hotel BMT-HOTEL-DFMEA-001 Rev C1 has 16 scored rows. Open RPN sum is 4,803. Severity split: 1 at S10, 9 at S9, 4 at S8, 2 at S7. Highest open RPNs: DF09 alert never arrives 432 (S9 O6 D8, projected 216); DF06 occupancy unchecked 432 (S9 O6 D8, projected 216); DF08 false empty 360 (S9 O5 D8, projected 162); DF15 radio host change 360 (S9 O5 D8, projected 162); DF16 animals crowded 360 (S9 O5 D8, projected 162); DF12 battery overheats 320 (S10 O4 D8, projected 120). BMT-HOTEL-RISK-PRIORITY-001 Rev C1 order follows projected RPN and still places DF12 inside the review list at projected 120. Projected figures are not demonstrated. The single severity-10 row and all nine severity-9 rows stay open regardless of rank. PF01 through PF16 mirror the requirements. No action is closed.

Result (Y/N/NA). Y

Explanation. DF12 can look smaller than DF09 on projected RPN and still stop the project, because severity is 10 and no cell, charger, or certification result exists.

Status. open

Evidence / exact revision / URL and date. BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-RISK-PRIORITY-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1 PF01 through PF16.

Owner. Jordan Vale

Next action. Keep DF12, DF09, DF08, and DF16 open ahead of any tooling talk. Do not accept projected RPN as residual evidence. Target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-10 Open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-DFMEA-001 Rev C1; BMT-HOTEL-RISK-PRIORITY-001 Rev C1; BMT-HOTEL-PFMEA-001 Rev C1

Mouse Hotel — What does one illustrated unit cost, and what contribution remains by channel?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-11

Question. What does one illustrated unit cost, and what contribution remains by channel?

Evidence to record. Amortized packed cost at low/base/high, tooling cash, hold price, contribution, and the company cash treatment of this product.

Result (Y/N/NA). Y

Explanation. Negative hardware contribution means the stated 5-store path does not clear the illustrated cost. A positive website contribution is not collected cash. The deferral stands even if a later price change repairs the hardware math.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 piece $58.67; BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1 ECONOMICS-06.

Owner. Alex Meadow

Next action. Do not load $30,000.00 tooling into the company cash sheet. Do not offer $70.95 sell-in to a store. Paper review target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-11 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-CHECK-SHEET-ECONOMICS-001 Rev C1

Mouse Hotel — What cash is planned for this product, and what allowance is excluded?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-12

Question. What cash is planned for this product, and what allowance is excluded?

Result (Y/N/NA). Y

Explanation. A reader of the BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1 alone can mistake $60,000.00 for a round. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1 row 14 controls. The allowance stays parked until Basic evidence exists and A03 is closed.

Status. estimate — unvalidated

Evidence / exact revision / URL and date. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1, unfunded-lines and cash-downside rows; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; action A12; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16.

Owner. Alex Meadow

Next action. Do not request a release against the $60,000.00 figure. Leave it off the 2026-11-15 spend agenda.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-12 Estimate only.

Not-applicable reason. Applicable

Source guidance URLs. BMT-COMPANY-TEMPLATE-FUNDING-001 Rev C1; BMT-HOTEL-FUNDING-WORKSHEET-001 Rev C1; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1

Mouse Hotel — What is believed to be new, who owns it, and what has already been disclosed?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-13

Question. What is believed to be new, who owns it, and what has already been disclosed?

Evidence to record. Invention point, contributors, disclosure history, route chosen, and freedom-to-operate status.

Answer / assumption. Believed new, unvalidated (IP-02): compartment occupancy fusion and offline state indication. Contributors, assignments unsigned: Alex Meadow concept; Sam Reed mechanism; Jordan Vale electronics and flight where used. Disclosure history: no external disclosure, no sale, no offer. Route: private BMT-HOTEL-TEMPLATE-INVENTION-DISCLOSURE-001 Rev C1 and a search plan. Provisional filing not chosen. Trademark unsearched. Freedom-to-operate review not performed, including for the radio and the app behavior. A later patent would not create an FCC grant and would not clear third-party sensor or radio rights. Drawings stay withheld from Perry Voss and Willa Marsh. Those contacts are Basic candidates and are not cleared for Hotel files.

Result (Y/N/NA). N

Explanation. IP-08 asks for counsel review before disclosure. Lane Corwin has not been engaged. No opinion exists.

Status. open

Evidence / exact revision / URL and date. BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1 IP-02 through IP-08; BMT-HOTEL-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1, Perry Voss and Willa Marsh.

Owner. Jordan Vale

Next action. Send no schematic and no app description outside the file. Do not file. Paper target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-13 Open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-CHECK-SHEET-IP-001 Rev C1; BMT-HOTEL-TEMPLATE-DISCLOSURE-HISTORY-001 Rev C1; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1

Mouse Hotel — Which regulatory questions are open, and which claims are refused?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-14

Question. Which regulatory questions are open, and which claims are refused?

Evidence to record. Regime, status, and the claim that must stay off the sheet.

Answer / assumption. Seven regimes on BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1, none cleared. CPSC: No CPC claimed; not a children's product. EPA and state device: No EPA approval or registration claim. Animal release: No destination approved. Materials and claims: no poison, no medical claim, no certified-humane claim. FCC: No FCC ID or authorization exists. Electrical and battery: No UL, NRTL, IP, or UN 38.3 pass claimed. Privacy and security: No privacy certification asserted. CTQ14 proposes no precise location and a 30-day retention idea. That proposal is not a privacy program. CTQ15 forbids inventing an FCC ID. Jordan Vale carries the connected-product scope on action A03, due 2026-12-15.

Result (Y/N/NA). Y

Explanation. Alert copy, chamber-count copy, and humane copy are all claims. None have evidence, so none can be drafted as statements of performance.

Status. open

Evidence / exact revision / URL and date. BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1; CTQ14 and CTQ15; action A03; BMT-HOTEL-INSTRUCTIONS-AND-WARNINGS-001 Rev C1 not issued.

Owner. Jordan Vale

Next action. Keep disease, humane, and capacity wording off drafts. Leave A03 open if the source review is unfinished. Due 2026-12-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-14 Open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-REGULATORY-SCREENING-001 Rev C1; BMT-HOTEL-INSTRUCTIONS-AND-WARNINGS-001 Rev C1

Mouse Hotel — Who could build the unit, and which purchases are forbidden now?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-15

Question. Who could build the unit, and which purchases are forbidden now?

Evidence to record. BMT-HOTEL-BOM-001 Rev C1 lines, candidate status, tooling cash, and the ban on sending drawings.

Answer / assumption. BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08, candidate not selected, no quote. Extended unit figures on the BMT-HOTEL-BOM-001 Rev C1: three-chamber shell $8.00; entry baffles and latches $1.00; sensor array $6.00; radio and controller cassette $10.00; protected battery $6.00; charger and cable $4.00; assembly and flashing $3.00; carton and instructions $2.00. Tooling cash on the BMT-HOTEL-SENSITIVITY-001 Rev C1 is $30,000.00 and is not a purchase. Perry Voss at Fictional Sample Works and Willa Marsh at Meadow Prototype Shop are Basic candidates only. They are not cleared for Hotel drawings. No RFQ, no NDA, and no purchase order. G4 text is No purchase order.

Result (Y/N/NA). N

Explanation. Flashing labor on HOTEL-07 does not mean firmware exists. The firmware-update failure DF11 is still open at RPN 288, projected 108, severity 9.

Status. blocked

Evidence / exact revision / URL and date. BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08; BMT-HOTEL-SENSITIVITY-001 Rev C1 tooling column; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1 DF11.

Owner. Jordan Vale

Next action. Do not send Hotel drawings to the Basic shops. Do not request a tool quote. Paper target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-15 Blocked.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-BOM-001 Rev C1; BMT-HOTEL-SENSITIVITY-001 Rev C1; BMT-COMPANY-TEMPLATE-CONTACTS-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1

Mouse Hotel — What test and welfare evidence exists, and what trial is forbidden?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-16

Question. What test and welfare evidence exists, and what trial is forbidden?

Evidence to record. Test IDs, result count, live-animal rule, and the multi-chamber rule.

Answer / assumption. T01 through T16 index CTQ01 through CTQ16. Methods are proposed. Nothing has been bought and nothing has been run. Result count is zero. Live animals are forbidden. A multi-chamber occupied trial is forbidden. Robin Keel has not set a check interval and has yet to approve a three-chamber welfare question. CTQ16 states capacity is not rated. False-empty and missed-alert trials, when they are someday allowed, are surrogate trials. Ira Bell is not engaged. Instructions that would tell a manager how often to check are not issued.

Result (Y/N/NA). N

Explanation. Basic door and vent proofs, even if they later pass, do not cover DF08, DF09, DF12, or DF16. Those four are the Hotel blockers for any external placement.

Status. blocked

Evidence / exact revision / URL and date. BMT-HOTEL-TEST-PLAN-001 Rev C1 T01 through T16; BMT-HOTEL-TEMPLATE-TEST-RESULTS-001 Rev C1 empty; CTQ16; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Robin Keel; action pattern A06.

Owner. Jordan Vale

Next action. Do not place a unit in a property and do not run a live or multi-animal trial. Keep the welfare ask unsent. Paper target 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-16 Blocked.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEST-PLAN-001 Rev C1; BMT-HOTEL-TEMPLATE-TEST-RESULTS-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — Which company controls block a pilot placement?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-17

Question. Which company controls block a pilot placement?

Evidence to record. Formation, bank, insurance with the lithium question, lot trace, and recall.

Answer / assumption. The LLC is not formed. No EIN and no account. Ellis Brook is not contacted and credit is not requested. Nia Calder has not said whether lithium is excluded from the illustrative $2,000,000.00 liability figure. No policy is bound. The $600.00 monthly insurance line is a reserve, not a premium. Lot trace, complaint log, and recall note are empty (Basic action A14, due 2026-12-01) and would be required before any Hotel pilot unit as well. No employee. Rowan Pell has not confirmed tax treatment. A property placement is a distribution event for recall purposes and is not authorized.

Result (Y/N/NA). N

Explanation. G5 names insurance, buyer terms, and recall readiness. All three are open. The deferral means they are not being solved with Hotel spend.

Status. blocked

Evidence / exact revision / URL and date. BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; action A14; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1, Nia Calder, Ellis Brook, Rowan Pell.

Owner. Alex Meadow

Next action. Do not ask the broker to bind a Hotel lithium risk from this sample. Formation sequence stays ahead of any account. Broker date 2026-12-01.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-17 Blocked.

Not-applicable reason. Applicable

Source guidance URLs. BMT-COMPANY-INSURANCE-REQUEST-001 Rev C1; BMT-COMPANY-ARTICLES-WORKSHEET-001 Rev C1; BMT-COMPANY-TEMPLATE-PEOPLE-001 Rev C1

Mouse Hotel — What is frozen, and which records must move when an input changes?

Project. Mouse Hotel

Product revision. C1

Sheet revision. 1

Prepared by. Jordan Vale

Date. 2026-10-24

Target market / jurisdiction. U.S. adults; Wisconsin illustrative base

Decision being prepared. Next private feasibility gate

Sheet. New Product Development: The Project Review

Lead. Jordan Vale

Item ID. PROJECT-18

Question. What is frozen, and which records must move when an input changes?

Evidence to record. ECN status, this sheet revision, and the Hotel records that have to stay together.

Answer / assumption. Nothing is frozen. This review is sheet revision 1, Planning draft, 2026-10-24. No Hotel design ECN has released a change. Records that move together: CTQ01 through CTQ16, BMT-HOTEL-DFMEA-001 Rev C1 and BMT-HOTEL-PFMEA-001 Rev C1, CP01 through CP16, T01 through T16, BMT-HOTEL-BOM-001 Rev C1 HOTEL-01 through HOTEL-08, the $58.67 piece, BMT-HOTEL-SENSITIVITY-001 Rev C1 volumes, the unsecured $60,000.00 allowance, and the FCC, battery, and privacy screening rows. A chamber-count change would also move CTQ16, DF16, the welfare ask, and any claim sentence. Paid orders stay at 0. The 16-row register on BMT-HOTEL-TEMPLATE-MARKET-EVIDENCE-001 remains the customer record. A later company decision would have to withdraw the 2026-08-16 deferral before that register becomes a launch file.

Result (Y/N/NA). Y

Explanation. Schedule dates are unfilled forecasts owned by Jordan Vale. Editing a forecast without a decision would make G1 look active while spend is still refused.

Status. open

Evidence / exact revision / URL and date. this sheet revision 1, 2026-10-24; BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1 2026-08-16; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1 piece $58.67; BMT-HOTEL-DFMEA-001 Rev C1.

Owner. Jordan Vale

Next action. Do not open a design ECN to add a chamber or a radio change. Next paper look 2027-02-15.

Reviewer / review date. Casey Holt, planned 2026-11-01, not held. PROJECT-18 Open.

Not-applicable reason. Applicable

Source guidance URLs. BMT-HOTEL-TEMPLATE-DECISION-LOG-001 Rev C1; BMT-HOTEL-TEMPLATE-COST-SHEET-001 Rev C1; BMT-HOTEL-DFMEA-001 Rev C1

Document administration

Preparation: Jordan Vale, scenario attribution, 2026-10-24. Signature: unsigned. Review: pending; no reviewer signature or date. Approval: withheld; no approver signature or date.

Prepared byDate
Reviewed byDate
Approved byDate