THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD
APQP summary — D1 internal pilot completion
Scope: APQP summary — D1 internal pilot completion. Read the observations and decisions below within their stated conditions.
APQP phases / evidence / decisions
| Phase | Basic | Mouse Hotel | Drone bench | Approval / actual date |
|---|---|---|---|---|
| Plan and define | B-RET-01; 12/100 baseline | H-IND-01; 8/100 baseline | D-INH-01; 3/100 baseline | Alex / May 03 |
| Product design | Keyed positive latch; DF01 addressed | Retained state; dropout addressed | Hardware inhibit; reset path addressed | Sam/Jordan / May 20–24 |
| Process design | Gauge + pull each unit; WI-D1 | Checksum + local/reset challenge | Isolation witness + inhibit challenge | Sam/Jordan / June 16 |
| Product/process validation | 0/1000 rebounds; 10/10 pulls | 0/1000 omissions; 100/100 valid resets | 0/1000 unsafe enables; 30/30 losses inhibit | Ira / June 18 |
| Feedback and action | 200 follow-up cycles, 0 failures | 200 follow-up events, 0 misses | 200 follow-up commands, 0 unsafe enables | Alex / June 30 |
Gate and submission disposition
| Record | Decision |
|---|---|
| D1 internal pilot packet, not an automotive customer submission. Product-specific FAI, control plan, MSA, results and internal PSW linked from sample index. | Alex signed June 25: accept Basic/Hotel scoped pilots and Drone bench; deny public release and flight. All listed gate decisions signed. |
Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.
Compare the reference example. Teaching data and signed dispositions: D1 scenario register.