THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD
Capacity and bottleneck study — pilot assembly
Scope: Capacity and bottleneck study — pilot assembly. Read the observations and decisions below within their stated conditions.
480-minute day; net available 420 min; demand 60 Basic / 20 Hotel units
| Product / step | Cycle min | Servers | Capacity per day | Constraint / action |
|---|---|---|---|---|
| Basic kit | 3 | 1 | 140 | Not constraint |
| Basic assemble | 6 | 1 | 70 | Not constraint |
| Basic inspect | 8 | 1 | 52.5 | Constraint; takt 420/60 = 7 min; add fixture |
| Basic inspect D1 | 5 | 1 | 84 | After fixture: assembly constraint 70; 60 demand met |
| Hotel assemble | 15 | 1 | 28 | Not constraint; takt 21 min |
| Hotel fault test | 24 | 1 | 17.5 | Constraint; two parallel fixtures → 35/day |
Verification
| Basis | Decision |
|---|---|
| Ten observed cycles per station, June 20; median shown; shared labor scheduled separately, not assumed simultaneous | Sam Reed verified 60 Basic and 20 Hotel-equivalent surrogate assemblies over separate shifts; Alex accepted June 25. Recheck before mixed-model scheduling. |
Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.
Compare the reference example. Teaching data and signed dispositions: D1 scenario register.