THE BETTER MOUSE TRAP CO. · COMPLETED METHOD RECORD

DMAIC project — Basic latch yield

DocumentBMT-SIX-SIGMA-AND-DMAIC-D1
Revision / review dateD1 · 2027-06-30
Accountable ownerAlex Meadow

Scope: DMAIC project — Basic latch yield. Read the observations and decisions below within their stated conditions.

Charter and completed phases

PhaseWork / evidenceOutcome / owner
DefineBMT-B-DMAIC-D1; contain Basic dry-cycle escapes; exclude animal trials and field reliabilitySponsor Alex; target 0/1000 confirmation failures, due June 18
MeasureBL-B: 12/100 rebounds; operational definition door opens after dry closure; checker agreement improved 72/80 to 80/80Ira Bell; baseline yield 88%
AnalyzeHinge clearance crossover: shim reduced 12/100 to 0/100; operator crossover did not change resultSam Reed; stack-up is occurrence cause; visual check is escape cause
PhaseWork / evidenceOutcome / owner
ImproveKey hinge, positive latch and functional retention gauge; ECN-D1-010/1000 rebounds; 10/10 pulls at 5 N, June 18
ControlD1 control plan: each unit gap gauge and retention check, stop/quarantine on first failureSam trained; 200 follow-up cycles 0 failures June 30; Alex closed project

Record reviewed and signed: Alex Meadow, 2027-06-30. Technical review: Sam Reed / Jordan Vale; independent check: Ira Bell. Disposition: use for the stated internal scope only.

Compare the reference example. Teaching data and signed dispositions: D1 scenario register.